Time Estimation of A Building
Time Estimation of A Building
PROJECT ADVISORY
Prof. Vivek Garg
(Asst. Professor Civil Engg. Dept.)
PROJECT TEAM
1
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Acknowledgement
We, the students are very grateful to many people who helped
and
supported us during the project. Our deepest thanks to our
guide
Prof. Vivek Garg (Asst. Professor) in Structure Engineering,
Department
of Civil Engineering, MANIT, Bhopal for his valuable help,
guidance and
suggestions during project studies.
2012
We would like to thank our honorable HOD Dr. Vishnu Prasad
for his
faith in us and last but not the least we would like to thank our
Director
of our Institute Dr. Appu Kuttan.
2
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
CERTIFICATE
This is to certify that the project entitled TIME ESTIMATION
OF A BUILDING submitted by afore mentioned students to
the Department of Civil Engineering towards partial fulfillment
of curriculum requirement for 7-8th semester is a bonafide
record of the work carried out by them under my supervision.
They have carried out this project with utmost sincerity and
hard work.
3
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Prof.
Vishnu Prasad
(HOD Civil
Engg. Department)
PREFACE
Time estimation is a process of calculating the approximate
time required for the completion of the project given the dead
line and start time of the project. Initially we focus on
deadlines, cost comes next.
4
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
CONTENTS
1. INTRODUCTION
6
2. NEED FOR TIME ESTIMATE
8
3. PROPOSED DESIGN 9
4. OPERATIONAL PLAN 10
5. STEPS FOR TIME ESTIMATION 11
Excavation
PCC work foundation
RCC work foundation
Plinth Beam
Columns
Slab beam and slab
Finishing
Flooring and tiling
Wood work
Steel work
Services
5
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
6. GANTT CHART 42
7. ABSTRACT 43
8. CONCLUSION 46
9. REFERENCES 47
INTRODUCTION
Accurate time estimation is a crucial skill in civil construction.
Without it, you won't know how long your project will take to
complete and the various steps adopted to complete it.
6
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
CONSTRUCTION ACTIVITIES
Excavation
PCC work for foundation
RCC work for foundation
o Reinforcement Tying
o Shuttering
o Concreting
Plinth
o Reinforcement Tying
o Shuttering
o Concreting
Columns
o Reinforcement Tying
o Shuttering
o Concreting
Slab beam and slab
o Reinforcement Tying
o Shuttering
o Concreting
Finishing
o Plastering
o White washing
o Painting
Flooring and tiling
Wood work
Steel work
Services
o Road work
o Sanitary installation
o Water supply
o Drainage
o Aluminum work
7
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
o Water proofing
o Electrical fitting
Scheduling of rates
Activity time
Event tie
CPM and PERT analysis
Representation by Gantt chart.
8
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
9
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
OPERATIONAL PLAN
We have taken into account many factors, including task
dependencies,
constraints, and interruptions, such as holidays or vacation
days. Most
importantly we have scheduled each task using the formula.
10
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
PROJECT DEADLINE
EXCAVATION
It comprises of digging of trenches, holes, foundations,
extracting the material from the ground by digging.
Machines used:
a. 2 JCB Digger
b. 6 dumpers
Efficiency of digger:
8 m3 digging and loading per hour.
11
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
12
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Pcc work
13
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
No. of labors
a) 4 beldar
b)6 Mazdoors
c) 3/2 Bhistri
d) mason
Total efficiency is 5.66 m3 per day
14
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
15
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Steps involved:
1) Laying reinforcement
2) Centering and shuttering
3) Laying of M-25
1) Laying of reinforcement.
Labors used
a. 4 Blacksmith
b. 4 Beldar
Efficiency of work
Can bend and lay 100kg/day.
16
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Efficiency of work
4.8m2/day.
17
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
3) Laying M-25
Machinery and setup
a) Batching Plants
b) Mixers
c) Concrete Pumps
d) Dumpers
e) Concrete Placers
Efficiency: 45 m3/hr.
18
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Steps involved:
1) Laying reinforcement
2) Centering and shuttering
3) Laying of M-25
1) Laying of reinforcement.
Labors used
a) 8 Blacksmith
b) 8 Beldar
Efficiency of work
Can bend and lay 100kg/day.
The time for reinforcement of plinth beam is 5.7 days.
20
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Labors used:
a. 4 Beldar
b. 4 Carpenters.
Efficiency of work
4.8m2/day.
3) Laying M-25
21
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
a) Batching Plants
b) Mixers
c) Concrete Pumps
d) Dumpers
e) Concrete Placers
Efficiency
45 m3/hr
22
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
COLUMNS
Steps involved:
1) Laying reinforcement
2) Centering and shuttering
3) Laying of M-25
1) Laying of reinforcement.
Labors used
a. 10Blacksmith
b. 10Beldar
Efficiency of work
Can bend and lay 100kg/day.
23
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Efficiency of work
4.8 m2/day.
24
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
3) Laying M-25
Efficiency
45 m3/hr.
25
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
26
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
27
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
SLABS
Steps involved:
1) Laying reinforcement
2) Centering and shuttering
3) Laying of M-25
1) Laying of reinforcement.
Labors used
a. 16 Blacksmith
b. 16 Beldar
Efficiency of work
Can bend and lay 100kg/day per Beldar per Blacksmith.
The time for reinforcement is 2.85 days.
28
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Efficiency of work
4.8 m2/day.
3) Laying M-25
29
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
30
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
BRICK WORK
Erection of walls:
Types of wall:
200mm thick..
Labours used:
a. 2 mason.
b. 4 mazdoor
c. bishti.
Efficiency of work
2.83 m3/day.
WHITE WASHING
31
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Labours used:
a. 1 whitewasher
b. 1 mazdoor.
Efficiency:
60 m3/day.
32
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
PAINTING
Painting involves coating the walls with distemper or
acrylic paint over the whitewash layer. It is intended
for aesthetic and hygienic purpose.
Labours used:
a. 6 painters
b. 4mazdoor.
Efficiency:
20 m3/day.
33
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
FLOORING/TILING
This involves laying of the tiles on the floor slab for its
finishing and aesthetical importance.
34
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Labour used:
a. 2 carpenters.
b. 1 beldar.
Efficiency : 0.18m3/day.
35
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
SANITARY INSTALLATIONS
This work includes installing water closets, wash
basins, other bathroom utilities in toilet and
bathrooms.
36
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
37
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
WATER SUPPLY
38
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
39
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
DRAINAGE
40
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
WATER PROOFING
41
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
GANTT CHART
42
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
ABSTRACT
43
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
44
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
45
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
CONCLUSION
The work started on January 2, 2012 and as per the
above mentioned time estimate it should complete
46
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
REFERENCES
47
MAJOR PROJECT: DESIGN AND TIME ESTIMATION OF A BUILDING
Reinforced Concrete.
IS 1786:1985 Indian Standard Specification For High
Strength Deformed Steel Bars And Wires For Concrete
Reinforcement.
http://www.interventions.org/pertcpm.html
Civil Engineering Graphics by BP Verma (khanna
publications).
http://www.ecf.utoronto.ca/apsc/courses/civ235s
/
A management guide to CPM PERT by Jerome D.
Wiest, Ferdinand K. Levy.
CPM PERT by BC Punmia.
48