En 1090 Technical Requirement
En 1090 Technical Requirement
Cutting
1. Hand thermal cutting should be used only if the machine thermal cutting not able to use pratically
Holing
1. Go & no-go gauges shall be used to check both ends of the hole
Cut outs
1. Sharp edges shall not be permitted
2. All corners must be rounded-off with min 5 mm radius to be maintained
Preheating
1. The pre heating temperature shall meet the requirement mentioned in EN 1011-2 Clause 12 Figu
Welding
1. Welding parameters ans specification apply EN ISO 3834 or 14554 as applicable
2. Welding procedure test pieces need to be produced under supervision of certification body
3. For EX2 clause materials S355 is acceptable to use pre-qualified welding procedures
4. EX2, EX3 & EX4 require that welding co-ordinator need to be appointed
5. The welding co-ordinator needs to be suitably or experienced specified in EN ISO 14731
6. The welding co-ordinator must be knowing the technical knowledge specified in EN ISO
7. EX2, EX3 and EX4 require tack welds are included in a qulaified welding procedure
8. The inspection of welds in accordance with EN 970