Zawtika General Specifications
Specification Master List
Date : 7-Feb-11
Revision
ZGS Discipline No. Description Revision Book Remark
Date
Volume 1 of 13
General
ZGS GEN 001 Definition of General Specification 0 1-Oct-10 1
ZGS GEN 002 Minimum Requirements for Contractor's Final Documentation 0 1-Oct-10 1
ZGS GEN 003 Zawtika Site Conditions and Climate 0 13-Dec-10 1
ZGS GEN 004 Material Traceability 0 1-Oct-10 1
ZGS GEN 005 Specification for Packing 0 1-Oct-10 1
ZGS GEN 006 QA/QC Inspection and Testing 0 1-Oct-10 1
ZGS GEN 007 AutoCAD Standard and Procedures 0 1-Oct-10 1
ZGS GEN 008 PTTEPI Standard Numbering Procedure 0 1-Nov-10 1
ZGS GEN 009 Minimum Requirements for Vendor's Documentation 0 25-Nov-10 1
ZGS GEN 010 QA/QC Requirements for Vendor 0 1-Oct-10 1
ZGS GEN 011 PDMS Standards and Procedures 0 13-Dec-10 1
Volume 2 of 13
Surveys
ZGS GEO 001 Offshore Geotechnical Soil Survey 0 10-Nov-10 1
ZGS GEO 002 Offshore Geophysical Surveys 0 9-Nov-10 1
ZGS GEO 003 Geophysical Survey for Offshore Pipeline Installation 0 9-Nov-10 1
Volume 3 of 13
Process
ZGS PRO 001 Process Documents to be Prepared during Engineering Phase 0 3-Nov-10 1
ZGS PRO 101 Process Sizing Criteria 0 3-Nov-10 1
Volume 4 of 13
Safety
ZGS SAF 101 Layout 0 11-Nov-10 1
ZGS SAF 103 Liquid Drainage 0 11-Nov-10 1
ZGS SAF 104 Emergency Shut-Down and Emergency De-Pressurisation (ESD & EDP) 0 11-Nov-10 1
ZGS SAF 105 Pressure Protection Relief and Hydrocarbon Disposal Systems 0 11-Nov-10 1
ZGS SAF 107 Escape, Evacuation and Rescue from Fixed Installations 0 11-Nov-10 1
Volume 5 of 13
Mechanical
ZGS MEC 101 Unfired Pressure Vessels 0 24-Sep-10 1
ZGS MEC 111 Air Cooled Heat Exchangers 0 24-Sep-10 1
ZGS MEC 121 Cranes for Fixed Offshore Installations 0 24-Sep-10 1
ZGS MEC 201 Centrifugal Pumps 0 24-Sep-10 1
ZGS MEC 202 Positive Displacement Reciprocating and Metering Pumps 0 24-Sep-10 1
ZGS MEC 211 Packaged Reciprocating Compressors 0 24-Sep-10 1
ZGS MEC 212 Fuel Gas Treatment Units 0 24-Sep-10 1
ZGS MEC 213 Rotating Machinery Packages 0 24-Sep-10 1
ZGS MEC 401 Installation of Offshore Mechanical Equipment 0 24-Sep-10 1
ZGS MEC 501 Equipment Vibration 0 24-Sep-10 1
ZGS MEC 502 Equipment Noise Limits 0 24-Sep-10 1
Page 1 of 4
Zawtika General Specifications
Specification Master List
Date : 7-Feb-11
Revision
ZGS Discipline No. Description Revision Book Remark
Date
Volume 6 of 13
Piping and Valves
ZGS PIP 101 Piping Design, Fabrication and Installation 0 13-Oct-10 1
ZGS PIP 102 Piping Stress Analysis 0 7-Dec-10 1
ZGS PIP 191 Model Review Check List 0 8-Dec-10 1
ZGS PIP 201 Piping and Valve Materials 1 7-Feb-11 2
ZGS PIP 501 Pressure Testing of Platform Piping Systems 0 4-Nov-10 1
ZGS PIP 601 Insulation 0 13-Oct-10 1
Volume 7 of 13
Structural
ZGS STR 001 Reference Levels for Offshore Platforms 0 12-Nov-10 1
ZGS STR 002 Weight Control 0 19-Nov-10 1
ZGS STR 101 Miscellaneous Minor Steel Structures 0 18-Nov-10 1
ZGS STR 102 Skid Mounted Assemblies 0 18-Nov-10 1
ZGS STR 201 Offshore Structural Materials 0 17-Nov-10 1
ZGS STR 301 Structural Steel Fabrication 0 9-Nov-10 1
ZGS STR 302 Offshore Structural Welding and Inspection 0 10-Nov-10 1
ZGS STR 401 Load-out, Transportation and Installation of Offshore Structures 0 18-Nov-10 1
ZGS STR 501 Offshore Living Quarter Module Architectural 0 12-Nov-10 1
Volume 8 of 13
Electrical
ZGS ELE 101 Electrical Engineering Guidelines 0 24-Sep-10 1
ZGS ELE 102 Electrical Requirements for Mechanical Packaged Equipment 0 24-Sep-10 1
ZGS ELE 203 Distribution Board 0 24-Sep-10 1
ZGS ELE 205 Solar Power System 0 24-Sep-10 1
ZGS ELE 206 Navigation Aids System 0 24-Sep-10 1
ZGS ELE 207 Hybrid Power System 0 24-Sep-10 1
ZGS ELE 401 Electrical Bulk Materials 0 24-Sep-10 1
ZGS ELE 402 Electrical Installation Specification 0 24-Sep-10 1
Volume 9 of 13
Instrument
ZGS INS 101 Instrumentation Engineering, Supply and Construction General Requirement 0 1-Oct-10 1
ZGS INS 102 Instrumentation Symbols and Identification 0 1-Oct-10 1
ZGS INS 103 Design and Installation of Instrument Links 0 1-Oct-10 1
ZGS INS 104 Fire and Gas System 0 1-Oct-10 1
ZGS INS 105 On/Off Valves and Control Valves sizing, Selection and Specification 0 1-Oct-10 1
ZGS INS 106 Design and Supply of Integrated Control and Safety System 0 1-Oct-10 1
ZGS INS 201 Electrical and Instrument Cables 0 1-Oct-10 1
ZGS INS 203 Instrument for Package Units 0 1-Oct-10 1
Volume 10 of 13
Telecommunication
ZGS TEL 101 Design, Supply and Installation of Telecommunication Systems 0 22-Oct-10 1
Page 2 of 4
Zawtika General Specifications
Specification Master List
Date : 7-Feb-11
Revision
ZGS Discipline No. Description Revision Book Remark
Date
Volume 11 of 13
Pipelines and Risers
ZGS PLR 101 Submarine Pipeline Systems 0 17-Sep-10 1
ZGS PLR 102 Design of Submarine Pipelines as per API RP 1111 and ASME B 31.4/31.8 0 17-Sep-10 1
ZGS PLR 103 Onshore Pipeline Systems 0 17-Sep-10 1
ZGS PLR 111 Pipeline Span Rectification 0 17-Sep-10 1
ZGS PLR 211 Fabrication of Seamless Pipes for Pipelines (Mild, Intermediate and Severe Sour Service) 0 17-Sep-10 1
Fabrication of Longitudinally Submerged Arc Welded Pipes for Pipelines (Mild , Intermediate
ZGS PLR 212 0 17-Sep-10 1
and Severe Sour Service)
ZGS PLR 213 Fabrication of ERW Line Pipe for Pipelines (Mild, Intermediate and Severe Sour Service) 0 24-Sep-10 1
Carbon Steel Flanges and Branch Outlet Fittings for Pipelines (Mild, Intermediate and Severe
ZGS PLR 231 0 17-Sep-10 1
Sour Service)
ZGS PLR 232 Carbon Steel Tees for Pipelines (Mild, Intermediate and Severe Sour Service) 0 17-Sep-10 2
Design, Materials and Fabrication of Pig Launchers and Receivers (Mild, Intermediate and
ZGS PLR 233 0 17-Sep-10 2
Severe Sour Service)
ZGS PLR 311 Induction Bends for Pipelines (Mild, Intermediate and Severe Sour Service) 0 17-Sep-10 2
ZGS PLR 321 Concrete Coating for Submarine Pipelines 0 17-Sep-10 2
ZGS PLR 331 Packaging and Transportation of Line Pipes 0 19-Nov-10 2
ZGS PLR 351 Riser Fabrication and Installation 0 17-Sep-10 2
ZGS PLR 401 Installation of Submarine Pipelines 0 17-Sep-10 2
Site Welding of Carbon Steel Pipelines to API 1104
ZGS PLR 412 0 17-Sep-10 2
(Mild, Intermediate and Severe Sour Service)
ZGS PLR 413 Automated Ultrasonic Testing (AUT) of Pipeline Girth Welds 0 17-Sep-10 2
ZGS PLR 421 Spoolpiece Fabrication and Installation 0 17-Sep-10 2
ZGS PLR 501 Hydrostatic Testing of Pipelines 0 17-Sep-10 2
ZGS PLR 502 Precommissioning of Submarine Gas Pipelines 0 17-Sep-10 2
Volume 12 of 13
Corrosion
ZGS COR 001 Protection of Oil and Gas Production Facilities Against Corrosion for Development Projects 0 21-Sep-10 1
ZGS COR 002 Protection of Oil and Gas Production Facilities Against Corrosion for Operations 0 21-Sep-10 1
ZGS COR 101 Design of Cathodic Protection of Offshore Structures by Sacrificial Anodes 0 21-Sep-10 1
Corrosion Spec on Design, Installation and Inspection of Cathodic Protection of Sealines by
ZGS COR 102 0 21-Sep-10 1
Sacrificial Anodes
ZGS COR 105 Design of Internal Cathodic Protection of Equipment and Storage Tanks 0 21-Sep-10 1
ZGS COR 111 Internal Corrosion and Erosion Control and Monitoring 0 21-Sep-10 1
ZGS COR 201 Materials for Sour Service 0 21-Sep-10 1
ZGS COR 202 Supply of Anodes and Monitoring Equipment for Cathodic Protection by Sacrificial Anodes 0 21-Sep-10 1
ZGS COR 203 Insulating Joints 0 21-Sep-10 1
ZGS COR 301 Painting of Offshore and Coastal Structures and Facilities 0 2-Dec-10 1
ZGS COR 303 External Anticorrosion Coating for Pipelines 0 19-Nov-10 1
ZGS COR 304 External Field Joint Coating for Pipelines 0 21-Sep-10 1
ZGS COR 305 Coating of Bends and Fittings for Pipelines 0 21-Sep-10 1
ZGS COR 306 Corrosion Coating of Pipeline Risers 0 21-Sep-10 1
ZGS COR 307 Corrosion Internal Coating of Pressure Vessels and Tanks 0 21-Sep-10 1
ZGS COR 308 Internal Coating of Water Injection Tubing and Lines 0 21-Sep-10 1
ZGS COR 501 Water Treatment for Hydrostatic Pressure Testing 0 21-Sep-10 1
Page 3 of 4
Zawtika General Specifications
Specification Master List
Date : 7-Feb-11
Revision
ZGS Discipline No. Description Revision Book Remark
Date
Volume 13 of 13
Precommissioning and Commissioning
ZGS PCC 101 Precommissioning and Commissioning Specification 0 2-Nov-10 1
ZGS PCC 102 Precommissioning and Commissioning Technical Preparation 0 8-Nov-10 1
ZGS PCC 103 Precommissioning Execution 0 2-Nov-10 2
ZGS PCC 104 Commissioning Execution 0 2-Nov-10 1
Page 4 of 4