Installing Primavera P6 Professional
A step-
step-by-
by-step guide for installing Stand-
Stand-alone P6 Professional R8.2
Installing Oracle Primavera P6 Professional
Hardware Requirements
Intel compatible CPU, 1 GHz or better
4GB Memory or greater
Microsoft Windows 7 Home, Professional or Ultimate
Software Requirements
Java 6 Update 27 runtime environment (JRE) or Software Developer Kit (JDK)
Oracle Primavera P6 Professional for EPPM R8.2 installation Media zip file V29692-01.zip
Microsoft .NET Framework 4 (x86 and x64) may already be installed on your system.
Overview
Primavera P6 Professional R8.2 stand-alone is installed from a single media package that can be
downloaded from Oracle e-delivery software cloud at https://edelivery.oracle.com/.
Follow these instructions to install a stand-alone copy of Primavera P6 Professional Release 8.2 on your
PC or Laptop.
Step 1 Install Java 6 Update 27 JRE or JDK
The Oracle XE database that will be installed with Primavera P6 Professional requires java be installed on
the system. The Java Runtime Environment (JRE) or Java Developer Kit (JDK) can be installed; either will
work.
It is very important to make sure a supported Java version is installed. For Primavera P6 Professional
R8.2 the supported Java 6 Update 27 version should be installed. Other (newer) versions may not be
compatible and may give problems with the database portion of the installation or database operations
after installation.
To install Java, right-click on the java media file you have downloaded for your machine. In the following
example the jdk-6u27-windows-i586.exe is being run.
Follow the installation instructions on the screen to complete the installation. In most cases the
installation defaults presented by the wizard will give a clean installation of the Java environment.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
2
Installing Oracle Primavera P6 Professional
Step 2 Prevent Java Automatic Updates
Use the Java icon in the Control Panel of your Windows environment to run the Java Control
Panel dialog.
In the Update tab, un-check the Check for Updates Automatically option to prevent future updates of
you Java installation.
When prompted, click on the Never Check button.
Click the OK button in the Java Control Panel dialog to save and close.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
3
Installing Oracle Primavera P6 Professional
Step 3 Install Primavera P6 Professional R8.2
Unzip the V29692-01.zip media delivery file to your Downloads or other convenient folder on the
computer. The installation media image will create the following folder structure:
C:\Downloads\Primavera P6 Professional for EPPM R8.2\P6_R82_Professional_Client
Locate the Setup.exe file in the P6_R82_Professional_Client folder and right-click on it.
Select the Open option from the menu. You can also double-click to start the installer.
The installer may prompt you to install certain prerequisite programs on your machine. These include
the DHTML Editing Component and Microsoft .NET Framework 4 (x86 and x64). If prompted, allow the
installer to proceed with these installations.
Once the prerequisites are installed, the main Primavera P6 Professional R8.2 Setup dialog will appear.
Click Next.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
4
Installing Oracle Primavera P6 Professional
In the Choose Setup Type dialog, click on the Standalone button.
You will now be prompted to install the database for P6. Enter a password and confirmation password
into the field provided.
Important: be sure to make a careful note of this password. It will be used for all the database
passwords and the P6 administrative users once you login.
The password you enter should be 8 characters in length or the following prompt will appear.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
5
Installing Oracle Primavera P6 Professional
In the Sample Data dialog, check the option to load the sample data as part of your P6 installation.
Training Note: if you are loading this in order to participate in a Ten Six online or on-site training class,
the sample data must be loaded.
Click Next.
In the Ready to install dialog, click the Install button.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
6
Installing Oracle Primavera P6 Professional
The installer will load all the necessary files automatically from this point. It may take several minutes to
load both the P6 Professional software client and the Oracle XE database.
During the installation you will see the Oracle Database 10g Express Edition icon appear on the
desktop.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
7
Installing Oracle Primavera P6 Professional
When the installation is complete, you will see the following dialog.
Click Finish to close the installer.
Primavera P6 Professional R8.2 is now loaded on your computer along with the Oracle 10g XE database
and sample data. Some of the prerequisites installed may cause the installer to prompt you that a
restart of the computer is required. If so, click Yes to restart your machine.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
8
Installing Oracle Primavera P6 Professional
Step 4 Getting Started with P6
Primavera P6 Professional can now be started using the Primavera P6 R8.2 option in the Programs
section of the Windows Start menu.
To login to P6, enter a Login Name of admin and then enter the password you provided the installer
earlier.
The first time you login, you will see the following prompt.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.
9
Installing Oracle Primavera P6 Professional
To set the appropriate Industry option, click on the Admin | Admin Preferences menu option.
In the Admin Preferences dialog, click on the Industry tab and select your desired industry sector
option.
This will determine the terminology and default settings P6 uses for subsequent sessions.
Training Note: If you are participating in a Ten Six Primavera P6 Professional online or on-site training
class, please select the Government, Aerospace and Defense option.
Installing Oracle Primavera P6 Professional - Copyright Ten Six Consulting, LLC 2012. All rights reserved.