Nepal Red Cross Society Banke District Chapter Nepalgunj, Bank
Nepal Red Cross Society Banke District Chapter Nepalgunj, Bank
NEPALGUNJ , BANK
A FOUNDATION WORKS
1 EARTHWORK
Earthwork in excavation
All footing 21 1.500 1.500 1.500 70.875
In wall
Long wall 3 9.756 0.600 4.390
Short wall 7 3.201 0.250 0.600
Next wall 1 3.000 0.250 0.600 0.450
In septic tank 1 3.650 3.048 2.000 22.250
In front step foundation 1 21.000 0.230 0.300 1,449
2 Earthwork in filling
Earthwork in filling in
foundation
All Trenchs 21 31.205 cum 31.205
3 SAND FILLING
Room area 1 18.750 6.097 0.6 68.59
Deduct tie beam
Long beam & wall 1 18.750 0.250 0.6 (2.81)
Short wall & beam 5 6.097 0.250 0.6 (4.57)
Next wall & beam 1 3.000 0.250 0.6 (0.45)
cum 60.756
4 SOILING
Stone Soiling
All Footing 21 1.500 1.500 0.200 9.450
Room Area 1 18.750 6.097 0.200 22.864
In septic Tank 1 3.650 3.650 0.200 2.665 cum 34.978
5 Flat Brick Soiling
All Footing 21 1.500 1.500 47.250
In wall
Long Wall 3 19.220 0.25 14.415
Short wall 7 6.097 0.25 10.670
Next wall 1 3.000 0.250 0.750
Sqm 73.085
6 Brickwork in 1:6 cement
sand ratio
Upto plinth level 250mm
In long wall 3 17.073 0.250 1.200 15.366
In short wall 7 5.640 0.250 1.200 11.844
Next wall 1 3.000 0.250 1.200 0.900
cum 28.110
7 PCC,RCC & PRECAST
WORK
(PCC M15)
S.N Item Nos Length breadth Height Quantity Unit Sub Item Remarks
Total total
S.N Item Nos Length breadth Height Quantity Unit Sub Total Item Remarks
total
Short Beam 7 7.317 0.250 0.300 3.841
Slab
Slab for Ground floor 1 19.207 8.231 0.125 19.762
Deduct staircase space 1 (3.510) (3.000) (0.125) 1.316
Staircase
All flight 2 3.000 1.268 0.150 1.141
Steps 19 1.067 0.279 0.177 0.501
Landing 1 2.439 1.220 0.150 0.223
Roof slab for staircase 1 5.000 4.500 0.100 1.125 cum 38.708
Projection part in lintel
In ventilation 7 0.914 0.600 0.076 0.146
12 iron works(for hold Fast)
For Door 4 2.000
For six ventilation 24 12.000
Kg 14.000
C FINISHING WORKS
S.N Item nos Length breadth Height Quantity unit Sub Total Item Remarks
Total
On four side 1 6.670 2.000 13.340
sqm 17.435
16 3mm thick 1:1 cement sand
punning
Ground floor
Room area 1 18.750 6.097 114.32
Deduct tie beam -5 -6.097 -0.23 (7.01)
Step (front of entrance) 1 10.207 1.29 13.17
Staircase
All flight (on trade) 20 1.220 0.250 6.10
All flight (on rise) 19 1.220 0.190 4.40
Landing 1 2.134 1.220 2.60
sqmt 133.582
17 PAINTING WORKS
Internal paint, Distemper
Wall (outside) 1 51.524 4.500 231.86
Wall (inside) 1 49.695 3.350 166.48
On ceiling 1 19.200 8.380 160.90
sqmt 559.232
External paint-weather coat
Wall (out side) 1 51.524 4.500 231.86
Inside 1 49.695 3.350 166.48
On ceiling 1 18.750 8.830 165.56
sqmt 563.899
18 Reinforcement 9,577.657 Kg 9577.657
19 Formworks
All footing 21 6.080 0.3 38.30
Column 21 1.200 4.4 110.88
Plinth tie beam
Long beam 3 19.207 0.800 46.10
Short beam 7 6.097 0.800 34.14
Ground floor beam
Long beam 3 19.207 0.800 46.10
Short beam 7 7.920 0.800 44.35
Staircase
Four flight 2 3.000 1.220 7.32
Landing 1 2.130 1.220 2.60
Slab
Slab Ground floor 1 19.209 8.384 161.048
Deduct staircase space (1) (3.510) (3.000) (1.000) (10.530) sqm 480.31
Reinforcement Details
Description Nos Diameter Length Total Length Wt/m Total wt Remarks
Mat for Footing
All footing (21) 504 16 1.6 806.4 1.580 1274.311
1274.311 Kg
Column
Foundation, Ground floor
All column (21) 168 16 7.315 1228.92 1.580 1941.997
2495.913 Kg
Ground floor slab
Bottom Bar
X-axis Bar 152 10 8.524 1295.648 0.617 799.783
Y-axis Bar 66 10 19.347 1276.902 0.617 788.211
Add 30% Extra Bar 476.398