Sep Mgse DC Pro 0001 3
Sep Mgse DC Pro 0001 3
SEP-MGSE-DC-PRO-0001
DOCUMENT MANAGEMENT PROCEDURE REV. 3
PAGE 2 of 15
TABLE OF CONTENTS
1 PURPOSE ......................................................................................... 3
2 SCOPE ............................................................................................. 3
3 DEFINITIONS ..................................................................................... 3
4 RESPONSIBILITIES ............................................................................. 3
6 INSTRUCTIONS .................................................................................. 4
11 APPENDIX ...................................................................................... 11
1 PURPOSE
2 SCOPE
The scope covers all the administrative and technical document types applied in this
project, including but not limited to plan, report, management system document, quality
inspection plan, work instruction, safety instruction, technical specification, record, design
document, nonconformity document, standard and code, etc. The management procedure
of communication and correspondence, including Letter, Transmittal, Technical Query,
Minutes of Meeting etc. refers to SEP-MGSE-DC-PRO-0002.
3 DEFINITIONS
Project name: Saudi Aramco Master Gas System Expansion - Phase I. "COMPANY"
means "ARAMCO OVERSEAS COMPANY BV' if it is used in relation to WORK to be
performed Out-Of-Kingdom under the OOK Contract, and it shall mean "SAUDI ARAMCO"
if it is used in relation to work to be performed In-Kingdom under the IK Contract.
DCC means Document Control Center reporting to the Project Controls Manager (PCM).
4 RESPONSIBILITIES
DCC is responsible for receiving, issuing, distribution, logging, preserving and archiving of all
documents & data, and handover of As-Built Drawings and related documents as
necessitated.
The functional division is in charge of document preparation, modification and
implementation after approval.
The sub-contractor is responsible for the establishment of document management system in
accordance with the required MGSE/SEPCOs specifications, project procedures & working
instructions and other concerned documents applied in this project.
SEP-MGSE-DC-PRO-0001
DOCUMENT MANAGEMENT PROCEDURE REV. 3
PAGE 4 of 15
5 RELEVANT CODING
Please refer to SEP-MGSE-DC-PRO-0003 Document & Drawing Coding Index for details.
6 INSTRUCTIONS
Revision Details
Management Documents
Submittal as new documents is all revision 0. Issued for Approval
0
(IFA)
If Accepted with Comments (AWC), or Resubmit (TRS), the
1, 2, 3 documents will be modifies as per Owner comments and re-
submittal.
If Accepted or Information, the document will be issued for final
00
document.
Technical Drawings/Documents
Revision Details
i) New Drawings
First revision Issued for Review (IFR). Developmental revision.
Further revisions if any up to IFC. If Accepted with Comments
(AWC), or Resubmit (TRS), the document will be modified as per
Owner comments and re-submitted for review, Issued for Review
(IFR) and finally Issued for Construction (IFC). AWC coded
documents can be issued IFC with prior clarification and acceptance
with Owner for the comments. Continue the same series if any
revisions after IFC before entering to iPlant.
00A, 00B, 00C, etc. The IFC issue status.
ISSUED FOR CONSTRUCTION shall be clearly indicated on the
face sheet of text documents and on upper part of title block of
drawings.
All previous Revision clouds shall be removed from the IFC
deliverables.
Note: For the new documents which are not in Auto-Sacs format,
use revision numbers as A, B, C, etc.
While uploading to iPlant as IFC as accepted by Aramco, change
revision to 00. Any Drawings entering the iPlant as new drawings
are all revision 00.
00
Grass-roots LSTK Project new drawings may be made as-built
(Revision 01) without submitting initial revision (00) into iPlant.
ii) Existing Drawings (not as-built)
If the existing drawing from iPlant is 00,
Development revisions of drawing (rev 00) from iPlant. (When the
0A1, 0A2 (HOLD Note1) construction documents need to be updated as per Vendor
information, field comments, etc.)
iii) Existing As-Built Drawings
If the as-built drawing from iPlant is 01
01A, 01B If the as-built drawing from iPlant is 01
Note 1: Rev No. to be used shall be confirmed with PM as Auto-Sacs allows only numeric for first
two characters of Rev No.
SEP-MGSE-DC-PRO-0001
DOCUMENT MANAGEMENT PROCEDURE REV. 3
PAGE 6 of 15
6.3.2 Status
Issued for Review
Issued for Approval
Issued for Information
Issued for Construction
Issued for Enquiry
Issued for Purchase
Issued as Final
As-Built
One Document / Drawing may not undergo all the status indicated here.
According to the approval and the purpose at the time of issue, the status shall be
given.
6.3.5 Typeset
Default text font of the document can be Arial and the font size
should be 11 for document contents. Heading can be bold with
font size 12. Front page main title will be 14 in font size.
Standard line spacing of paragraph can be single line.
Please refer this procedure in the other typeset.
Drawing Name must comply with the file naming convention. Vector,
Hybrid (Vector and Raster), Microsoft Excel, Word and Acrobat PDF
files shall have a naming format as follows:
Vector drawings
Excel
Word
PDF
PDF (for Data-Centric only. Refer to section 15.12 of SAEP-334 for
details)
7.1 Management/Procedure
A-MGSE-X-Z-EEEE
Where:
Example: SEP-MGSE-QC-PRO-0005
Means the 5th Procedure document sent by Quality Control Department of SEPCO (OOK
CONTRACTOR).
MR documents are coded as SEP-MGSE-EM-MR-EEEE.
SEP-MGSE-DC-PRO-0001
DOCUMENT MANAGEMENT PROCEDURE REV. 3
PAGE 9 of 15
7.2 Procurement
Documents Numbering shall be adopted within SEPCO for convenience and can
be followed the following methodology;
A-MGSE-X-Z-EEEE
Where:
Example 1: SEP-MGSE-PLD-PO-0001
Means the 1st Purchase Order placed by Procurement & Logistics Dept. of
SEPCO for MGSE Project.
Example 2: SEP-MGSE-PLD-RFQ-0005
Means the 5th Request for Quotation by Procurement & Logistics Dept. of SEPCO
for MGSE Project.
Saudi Aramco numbering system as per SAES-202 shall be used. A typical drawing
numbering scheme is as below:
Example: VA-765432
where
V=Prefix letter: a single alpha letter, as below:
765432=Identifying no. : 6 digit numbers, and this no. should be provided from iPlant
SEP-MGSE-DC-PRO-0001
DOCUMENT MANAGEMENT PROCEDURE REV. 3
PAGE 11 of 15
10 REFERENCE DOCUMENTS
11 APPENDIX
6600033892(OOK)
Contract No. : Document No.: SEP-MGSE-XX-XXX-XXXX
6600035463 (IK)
TABLE OF CONTENTS
1 XXXX ................................................................................................ 2
1 XXXX
SEP-MGSE-DC-PRO-0001
DOCUMENT MANAGEMENT PROCEDURE REV. 3
PAGE 12 of 15
DISC. ENGR
DOCUMENT NAME
DATE
PROJ. ENGR
DATE
CERTIFIED
ISSUED CODE
DATE
CONST. GENCY
DATE
OPERATIONS
DATE
EDSDVERIFICATION
CONTROL NUMBER
DATE:
BY:
THIS INDICATES THAT REV. NO. _______
REVISION CERTIFICATION
OF THIS DRAWING IS COVERED, FOR
_______________________________
REQUIREMENTS,BY DOCUMENT
ALL APPROVAL/CERTIFICATION
COMPLETION CERTIFICATE
-G- - -G-
DATE
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
JOB ORDER/EWO NO.
PRINCIPAL CORROSIVES: Inorganic Salts / HYDR. COUPL. SPEED RANGE % % OF DRIVER SPEED
pH CI PPM
CONSTRUCTION DATA
PUMP TYPE
OPERATING CONDITIONS HORIZONTAL (BET. BRGS) / OVERHUNG
/ VERT. IN-LINE INTEGRAL SHAFT
IS COVERED, FOR ALL APPROVAL
DATA SHEET FOR EQUIPMENT DWG. TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.