Oklha Waste Management Company
Oklha Waste Management Company
Methodological Tool
(Version 02)
Net electricity generation refers to the difference between the total quantity of electricity generated by
the power plant/unit and the auxiliary electricity consumption (also known as parasitic load) of the power
plant/unit (e.g. for pumps, fans, controlling, etc).
Grid/project electricity system is defined by the spatial extent of the power plants that are physically
connected through transmission and distribution lines to the project activity (e.g. the renewable power
plant location or the consumers where electricity is being saved) and that can be dispatched without
significant transmission constraints.
UNFCCC/CCNUCC
Connected electricity system is an electricity system that is connected by transmission lines to the project
electricity system. Power plants within the connected electricity system can be dispatched without
significant transmission constraints but transmission to the project electricity system has significant
transmission constraint.
Under this tool, the emission factor for the project electricity system can be calculated either for grid
power plants only or, as an option, can include off-grid power plants. In the latter case, the conditions
specified in “Annex 2 - Procedures related to off-grid power generation” should be met. Namely, the total
capacity of off-grid power plants (in MW) should be at least 10% of the total capacity of grid power plants
in the electricity system; or the total power generation by off-grid power plants (in MWh) should be at
least 10% of the total power generation by grid power plants in the electricity system; and that factors
which negatively affect the reliability and stability of the grid is primarily due to constraints in generation
and not to other aspects such as transmission capacity.
Note that this tool is also referred to in the “Tool to calculate project emissions from electricity
consumption” for the purpose of calculating project and leakage emissions in case where a project activity
consumes electricity from the grid or results in increase of consumption of electricity from the grid outside
the project boundary.
Parameters
This tool provides procedures to determine the following parameters:
Parameter SI Unit Description
EFgrid,CM,y tCO2/MWh Combined margin CO2 emission factor for the project electricity system
in year y
EFgrid,BM,y tCO2/MWh Build margin CO2 emission factor for the project electricity system in
year y
EFgrid,OM,y tCO2/MWh Operating margin CO2 emission factor for the project electricity system
in year y
For determining the electricity emission factors, a project electricity system is defined by the spatial
extent of the power plants that are physically connected through transmission and distribution lines to the
project activity (e.g. the renewable power plant location or the consumers where electricity is being saved)
and that can be dispatched without significant transmission constraints.
Similarly, a connected electricity system, e.g. national or international, is defined as an electricity system
that is connected by transmission lines to the project electricity system. Power plants within the connected
electricity system can be dispatched without significant transmission constraints but transmission to the
project electricity system has significant transmission constraint.
If the DNA of the host country has published a delineation of the project electricity system and connected
electricity systems, these delineations should be used. If this information is not available, project
participants should define the project electricity system and any connected electricity system, and justify
and document their assumptions in the CDM-PDD. The following criteria can be used to determine the
existence of significant transmission constraints:1
• In case of electricity systems with spot markets for electricity: there are differences in electricity
prices (without transmission and distribution costs) of more than 5 percent between the systems
during 60 percent or more of the hours of the year;
• The transmission line is operated at 90% or more of its rated capacity during 90% percent or more
of the hours of the year.
Where the application of these criteria does not result in a clear grid boundary, use a regional grid
definition in the case of large countries with layered dispatch systems (e.g. provincial/regional/national).
A provincial grid definition may indeed in many cases be too narrow given significant electricity trade
among provinces that might be affected, directly or indirectly, by a CDM project activity. In other
countries, the national (or other largest) grid definition should be used by default. Document the
1
Project participants may propose other criteria or submit proposals for revision of these criteria for consideration
by the CDM Executive Board.
UNFCCC/CCNUCC
geographical extent of the project electricity system transparently and identify all grid power plants/units
connected to the system.
Electricity transfers from connected electricity systems to the project electricity system are defined as
electricity imports and electricity transfers to connected electricity systems are defined as electricity
exports.
For the purpose of determining the build margin emission factor, the spatial extent is limited to the project
electricity system, except where recent or likely future additions to transmission capacity enable
significant increases in imported electricity. In such cases, the transmission capacity may be considered a
build margin source.
For the purpose of determining the operating margin emission factor, use one of the following options to
determine the CO2 emission factor(s) for net electricity imports from a connected electricity system within
the same host country(ies):
(a) 0 tCO2/MWh; or
(b) The weighted average operating margin (OM) emission rate of the exporting grid, determined as
described in Step 4 (d) below; or
(c) The simple operating margin emission rate of the exporting grid, determined as described in
Step 4 (a), if the conditions for this method, as described in Step 3 below, apply to the exporting
grid; or
(d) The simple adjusted operating margin emission rate of the exporting grid, determined as
described in Step 4 (b) below.
For imports from connected electricity systems located in another host country(ies), the emission factor is
0 tons CO2 per MWh.
Electricity exports should not be subtracted from electricity generation data used for calculating and
monitoring the electricity emission factors.
Step 2: Choose whether to include off-grid power plants in the project electricity system (optional)
Project participants may choose between the following two options to calculate the operating margin and
build margin emission factor:
Option II: Both grid power plants and off-grid power plants are included in the calculation.
Option I corresponds to the procedure contained in earlier versions of this tool. Option II allows the
inclusion of off-grid power generation in the grid emission factor. Option II aims to reflect that in some
countries off-grid power generation is significant and can partially be displaced by CDM project activities,
e.g. if off-grid power plants are operated due to an unreliable and unstable electricity grid. Option II
requires collecting data on off-grid power generation as per Annex 2 and can only be used if the
conditions outlined therein are met. Option II may be chosen only for the operating margin emission
UNFCCC/CCNUCC
factor or for both the build margin and the operating margin emission factor but not only for the build
margin emission factor.
If Option II is chosen, off-grid power plants should be classified as per the guidance in Annex 2 in
different classes of off-grid power plants. Each off-grid power plant class should be considered as one
power plant j, k, m or n in the following steps, as applicable.
The calculation of the operating margin emission factor (EFgrid,OM,y) is based on one of the following
methods:
(a) Simple OM; or
(b) Simple adjusted OM; or
(c) Dispatch data analysis OM; or
(d) Average OM.
Each method is described under Step 4.
The simple OM method (option a) can only be used if low-cost/must-run resources2 constitute less than
50% of total grid generation in: 1) average of the five most recent years, or 2) based on long-term
averages for hydroelectricity production.
The dispatch data analysis (Option d) cannot be used if off-grid power plants are included in the project
electricity system as per Step 2 above.
For the simple OM, the simple adjusted OM and the average OM, the emissions factor can be calculated
using either of the two following data vintages:
• Ex ante option: If the ex ante option is chosen, the emission factor is determined once at the
validation stage, thus no monitoring and recalculation of the emissions factor during the crediting
period is required. For grid power plants, use a 3-year generation-weighted average, based on the
most recent data available at the time of submission of the CDM-PDD to the DOE for validation.
For off-grid power plants, use a single calendar year within the 5 most recent calendar years prior
to the time of submission of the CDM-PDD for validation.
• Ex post option: If the ex post option is chosen, the emission factor is determined for the year in
which the project activity displaces grid electricity, requiring the emissions factor to be updated
annually during monitoring. If the data required to calculate the emission factor for year y is
usually only available later than six months after the end of year y, alternatively the emission
factor of the previous year y-1 may be used. If the data is usually only available 18 months after
2
Low-cost/must-run resources are defined as power plants with low marginal generation costs or power plants that
are dispatched independently of the daily or seasonal load of the grid. They typically include hydro, geothermal,
wind, low-cost biomass, nuclear and solar generation. If coal is obviously used as must-run, it should also be
included in this list, i.e. excluded from the set of plants.
UNFCCC/CCNUCC
the end of year y, the emission factor of the year proceeding the previous year y-2 may be used.
The same data vintage (y, y-1 or y-2) should be used throughout all crediting periods.
For the dispatch data analysis OM, use the year in which the project activity displaces grid electricity and
update the emission factor annually during monitoring.
The data vintage chosen should be documented in the CDM-PDD and not be changed during the crediting
periods.
Power plants registered as CDM project activities should be included in the sample group that is used to
calculate the operating margin if the criteria for including the power source in the sample group apply.
Step 4: Calculate the operating margin emission factor according to the selected method
(a) Simple OM
The simple OM emission factor is calculated as the generation-weighted average CO2 emissions per unit
net electricity generation (tCO2/MWh) of all generating power plants serving the system, not including
low-cost/must-run power plants/units.
The simple OM may be calculated:
Option A: Based on the net electricity generation and a CO2 emission factor of each power unit;3 or
Option B: Based on the total net electricity generation of all power plants serving the system and the fuel
types and total fuel consumption of the project electricity system.
Option B can only be used if:
3
Power units should be considered if some of the power units at the site of the power plant are low-cost/must-run
units and some are not. Power plants can be considered if all power units at the site of the power plant belong to
the group of low-cost/must-run units or if all power units at the site of the power plant do not belong to the group
of low-cost/must-run units.
UNFCCC/CCNUCC
∑ EG ⋅ EF m,y EL,m,y
EFgrid,OMsimple,y = m
(1)
∑ EG m
m,y
Where:
EFgrid,OMsimple,y = Simple operating margin CO2 emission factor in year y (tCO2/MWh)
EGm,y = Net quantity of electricity generated and delivered to the grid by power unit m in year y
(MWh)
EFEL,m,y = CO2 emission factor of power unit m in year y (tCO2/MWh)
m = All power units serving the grid in year y except low-cost / must-run power units
y = The relevant year as per the data vintage chosen in Step 3
Determination of EFEL,m,y
The emission factor of each power unit m should be determined as follows:
• Option A1. If for a power unit m data on fuel consumption and electricity generation is available,
the emission factor (EFEL,m,y) should be determined as follows:
Where:
EFEL,m,y = CO2 emission factor of power unit m in year y (tCO2/MWh)
FCi,m,y = Amount of fossil fuel type i consumed by power unit m in year y (Mass or
volume unit)
NCVi,y = Net calorific value (energy content) of fossil fuel type i in year y (GJ/mass
or volume unit)
EFCO2,i,y = CO2 emission factor of fossil fuel type i in year y (tCO2/GJ)
EGm,y = Net quantity of electricity generated and delivered to the grid by power
unit m in year y (MWh)
m = All power units serving the grid in year y except low-cost/must-run power
units
i = All fossil fuel types combusted in power unit m in year y
y = The relevant year as per the data vintage chosen in Step 3
• Option A2. If for a power unit m only data on electricity generation and the fuel types used is
available, the emission factor should be determined based on the CO2 emission factor of the fuel
type used and the efficiency of the power unit, as follows:
EFCO2,m,i,y ⋅ 3.6
EFEL,m,y = (3)
η m,y
UNFCCC/CCNUCC
Where:
EFEL,m,y = CO2 emission factor of power unit m in year y (tCO2/MWh)
EFCO2,m,i,y = Average CO2 emission factor of fuel type i used in power unit m in year y
(tCO2/GJ)
ηm,y = Average net energy conversion efficiency of power unit m in year y (ratio)
m = All power units serving the grid in year y except low-cost/must-run power
units
y = The relevant year as per the data vintage chosen in Step 3
Where several fuel types are used in the power unit, use the fuel type with the lowest CO2
emission factor for EFCO2,m,i,y.
• Option A3. If for a power unit m only data on electricity generation is available, an emission
factor of 0 tCO2/MWh can be assumed as a simple and conservative approach.
Determination of EGm,y
For grid power plants, EGm,y should be determined as per the provisions in the monitoring tables.
For off-grid power plants, EGm,y can be determined using one of the following options:4
• Option 1. EGm,y is determined based on (sampled) data on the electricity generation of off-grid
power plants, as per the guidance in Annex 2.
• Option 2. EGm,y is determined based on (sampled) data on the quantity of fossil fuels combusted
in the class of off-grid power plants m, as per the guidance in Annex 2, and the default efficiencies
provided in Annex 1, as follows:
Where:
EGm,y = Net quantity of electricity generated and delivered to the grid by power
unit m in year y (MWh)
FCi,m,y = Amount of fossil fuel type i consumed by power plants included in off-grid
power plant class m in year y (mass or volume unit)
NCVi,y = Net calorific value (energy content) of fossil fuel type i in year y (GJ/mass
or volume unit)
ηm,y = Default net energy conversion efficiency of off-grid power plant class m in
year y (ratio), as per the default values provided in Annex 1
m = Off-grid power plant class considered as one power unit (as per the
provisions in Annex 2 to this tool)
y = The relevant year as per the data vintage chosen in Step 3
i = Fossil fuel types used
4
Note that different options can be applied to different classes of off-grid power plants; however, the same option
should be applied to all (sampled) off-grid power plants within one class.
UNFCCC/CCNUCC
• Option 3. EGm,y is estimated based on the capacity of off-grid electricity generation in that class
and a default plant load factor, as follows:
Where:
EGm,y = Net quantity of electricity generated and delivered to the grid by power unit m
in year y (MWh)
CAPm = Total capacity of off-grid power plants in included in off-grid power plant
class m (MW)
PLFdefault,off-grid,y = Default plant load factor for off-grid generation in year y (ratio)
m = Off-grid power plant class considered as one power unit (as per the provisions
in Annex 2 to this tool)
y = The relevant year as per the data vintage chosen in Step 3
The default plant load factor for off-grid generation (PLFdefault,off-grid,y) should be determined using
one of the following two options:
• Use a conservative default value of 300 hours per year, assuming that the off-grid power
plants would at least operate for one hour per day at six days at full capacity (i.e.
PLFdefault,off-grid,y=300/8760); or
• Calculate the default plant load factor based on the average grid availability and a default
factor of 0.5, assuming that off-grid power plants are operated at full load during
approximately half of the time that the grid is not available, as follows:
Tgrid, y
PLFdefault,off −grid, y = 8760 × (1 − ) × 0.5 (6)
8760
Where:
PLFdefault,off-grid,y = Default plant load factor for off-grid generation in year y (ratio)
Tgrid,y = Average time the grid was available to final electricity consumers in
year y (hours)
Option B - Calculation based on total fuel consumption and electricity generation of the system
Under this option, the simple OM emission factor is calculated based on the net electricity supplied to the
grid by all power plants serving the system, not including low-cost/must-run power plants/units, and based
on the fuel type(s) and total fuel consumption of the project electricity system, as follows:
Where:
EFgrid,OMsimple,y = Simple operating margin CO2 emission factor in year y (tCO2/MWh)
FCi,y = Amount of fossil fuel type i consumed in the project electricity system in year y (mass
or volume unit)
NCVi,y = Net calorific value (energy content) of fossil fuel type i in year y (GJ/mass or volume
unit)
EFCO2,i,y = CO2 emission factor of fossil fuel type i in year y (tCO2/GJ)
EGy = Net electricity generated and delivered to the grid by all power sources serving the
system, not including low-cost/must-run power plants/units, in year y (MWh)
i = All fossil fuel types combusted in power sources in the project electricity system in
year y
y = The relevant year as per the data vintage chosen in Step 3
For this approach (simple OM) to calculate the operating margin, the subscript m refers to the power
plants/units delivering electricity to the grid, not including low-cost/must-run power plants/units, and
including electricity imports5 to the grid. Electricity imports should be treated as one power plant m.
∑ EG × EF
m, y EL, m, y ∑ EG × EF
k, y EL, k, y
EFgrid,OM -adj, y = (1 − λ y )⋅m
+ λy ⋅k
(8)
∑ EG
m
m, y ∑ EG
k
k, y
Where:
EFgrid,OM-adj,y = Simple adjusted operating margin CO2 emission factor in year y (tCO2/MWh)
λy = Factor expressing the percentage of time when low-cost/must-run power units are on
the margin in year y
EGm,y = Net quantity of electricity generated and delivered to the grid by power unit m in year y
(MWh)
EGk,y = Net quantity of electricity generated and delivered to the grid by power unit k in year y
(MWh)
EFEL,m,y = CO2 emission factor of power unit m in year y (tCO2/MWh)
EFEL,k,y = CO2 emission factor of power unit k in year y (tCO2/MWh)
m = All grid power units serving the grid in year y except low-cost/must-run power units
k = All low-cost/must run grid power units serving the grid in year y
y = The relevant year as per the data vintage chosen in Step 3
5
As described above, an import from a connected electricity system should be considered as one power source.
UNFCCC/CCNUCC
EFEL,m,y, EFEL,k,y, EGm,y and EGk,y should be determined using the same procedures as those for the
parameters EFEL,m,y and EGm,y in Option A of the simple OM method above.
If off-grid power plants are included in the operating margin emission factor, off-grid power plants should
be treated as other power units m.
Net electricity imports must be considered low-cost/must-run units k.
Number of hours low - cost / must - run sources are on the margin in year y
λ y (% ) = (9)
8760 hours per year
Step (i) Plot a load duration curve. Collect chronological load data (typically in MW) for each hour
of the year y, and sort the load data from the highest to the lowest MW level. Plot MW against
8760 hours in the year, in descending order.
Step (ii) Collect power generation data from each power plant/unit. Calculate the total annual
generation (in MWh) from low-cost/must-run power plants/units (i.e. ∑k EGk,y).
Step (iii) Fill the load duration curve. Plot a horizontal line across the load duration curve such that the
area under the curve (MW times hours) equals the total generation (in MWh) from low-
cost/must-run power plants/units (i.e. ∑k EGk,y).
Step (iv) Determine the “Number of hours for which low-cost/must-run sources are on the margin in
year y”. First, locate the intersection of the horizontal line plotted in Step (iii) and the load
duration curve plotted in Step (i). The number of hours (out of the total of 8760 hours) to the
right of the intersection is the number of hours for which low-cost/must-run sources are on the
margin. If the lines do not intersect, then one may conclude that low-cost/must-run sources do
not appear on the margin and λy is equal to zero.
In determining λy only grid power units (and no off-grid power plants) should be considered.
UNFCCC/CCNUCC
Intersection Point
MW
X hours
λ = X / 8760
Hours
0 8760
Note: Step (ii) is not shown in the figure; it deals with organizing data by source.
Where:
EFgrid,OM-DD,y = Dispatch data analysis operating margin CO2 emission factor in year y (tCO2/MWh)
EGPJ,h = Electricity displaced by the project activity in hour h of year y (MWh)
EFEL,DD,h = CO2 emission factor for grid power units in the top of the dispatch order in hour h in
year y (tCO2/MWh)
EGPJ,y = Total electricity displaced by the project activity in year y (MWh)
h = Hours in year y in which the project activity is displacing grid electricity
y = Year in which the project activity is displacing grid electricity
If hourly fuel consumption data is available, then the hourly emissions factor is determined as:
∑ FC i, n, h ⋅ NCVi, y ⋅ EFCO2,i, y
EFEL, DD, h = i, n
(11)
∑ EG
n
n, h
Where:
EFEL,DD,h = CO2 emission factor for grid power units in the top of the dispatch order in hour h in
year y (tCO2/MWh)
FCi,n,h = Amount of fossil fuel type i consumed by grid power unit n in hour h (Mass or volume
unit)
NCVi,y = Net calorific value (energy content) of fossil fuel type i in year y (GJ/mass or volume
unit)
EFCO2,i,y = CO2 emission factor of fossil fuel type i in year y (tCO2/GJ)
EGn,h = Electricity generated and delivered to the grid by grid power unit n in hour h (MWh)
n = Grid power units in the top of the dispatch (as defined below)
i = Fossil fuel types combusted in grid power unit n in year y
h = Hours in year y in which the project activity is displacing grid electricity
y = Year in which the project activity is displacing grid electricity
Otherwise, the hourly emissions factor is calculated based on the energy efficiency of the grid power unit
and the fuel type used, as follows:
∑ EG × EF n,h EL , n , y
EFEL,DD, h = n
(12)
∑ EG n
n,h
Where:
EFEL,DD,h = CO2 emission factor for grid power units in the top of the dispatch order in hour h in
year y (tCO2/MWh)
EGn,h = Net quantity of electricity generated and delivered to the grid by grid power unit n in
hour h (MWh)
EFEL,n,y = CO2 emission factor of grid power unit n in year y (tCO2/MWh)
n = Grid power units in the top of the dispatch (as defined below)
h = Hours in year y in which the project activity is displacing grid electricity
UNFCCC/CCNUCC
The CO2 emission factor of the grid power units n (FEEL,n,y) should be determined as per the guidance for
the simple OM, using the Options A1, A2 or A3.
To determine the set of grid power units n that are in the top of the dispatch, obtain from a national
dispatch centre:
• The grid system dispatch order of operation for each grid power unit of the system including
power units from which electricity is imported; and
• The amount of power (MWh) that is dispatched from all grid power units in the system during
each hour h that the project activity is displacing electricity.
At each hour h, stack each grid power unit’s generation using the merit order. The group of grid power
units n in the dispatch margin includes the units in the top x% of total electricity dispatched in the hour h,
where x% is equal to the greater of either:
(a) 10%; or
(b) The quantity of electricity displaced by the project activity during hour h divided by the total
electricity generation by grid power plants during that hour h.
(d) Average OM
The average OM emission factor (EFgrid,OM-ave,y) is calculated as the average emission rate of all power
plants serving the grid, using the methodological guidance as described under (a) above for the simple
OM, but including in all equations also low-cost/must-run power plants.
Option B should only be used if the necessary data for Option A is not available.
Step 5: Identify the group of power units to be included in the build margin
The sample group of power units m used to calculate the build margin consists of either:6
(a) The set of five power units that have been built most recently;or
(b) The set of power capacity additions in the electricity system that comprise 20% of the system
generation (in MWh) and that have been built most recently.7
Project participants should use the set of power units that comprises the larger annual generation.
As a general guidance, a power unit is considered to have been built at the date when it started to supply
electricity to the grid.
Power plant registered as CDM project activities should be excluded from the sample group m. However,
If the group of power units, not registered as CDM project activity, identified for estimating the build
margin emission factor includes power unit(s) that is(are) built more than 10 years ago then:
6
If this approach does not reasonably reflect the power plants that would likely be built in the absence of the project
activity, project participants are encouraged to submit alternative proposals for consideration by the CDM
Executive Board.
7
If 20% falls on part capacity of a unit, that unit is fully included in the calculation.
UNFCCC/CCNUCC
(i) Exclude power unit(s) that is (are) built more than 10 years ago from the group; and
(ii) Include grid connected power projects registered as CDM project activities, which are
dispatched by dispatching authority to the electricity system.8
Capacity additions from retrofits of power plants should not be included in the calculation of the build
margin emission factor.
In terms of vintage of data, project participants can choose between one of the following two options:
Option 1: For the first crediting period, calculate the build margin emission factor ex ante based on the
most recent information available on units already built for sample group m at the time of CDM-PDD
submission to the DOE for validation. For the second crediting period, the build margin emission factor
should be updated based on the most recent information available on units already built at the time of
submission of the request for renewal of the crediting period to the DOE. For the third crediting period,
the build margin emission factor calculated for the second crediting period should be used. This option
does not require monitoring the emission factor during the crediting period.
Option 2: For the first crediting period, the build margin emission factor shall be updated annually,
ex post, including those units built up to the year of registration of the project activity or, if information up
to the year of registration is not yet available, including those units built up to the latest year for which
information is available. For the second crediting period, the build margin emissions factor shall be
calculated ex ante, as described in Option 1 above. For the third crediting period, the build margin
emission factor calculated for the second crediting period should be used.
∑ EG × EF
m, y EL , m , y
EFgrid, BM, y =m
(13)
∑ EG
m
m, y
Where:
EFgrid,BM,y = Build margin CO2 emission factor in year y (tCO2/MWh)
EGm,y = Net quantity of electricity generated and delivered to the grid by power unit m in year y
(MWh)
EFEL,m,y = CO2 emission factor of power unit m in year y (tCO2/MWh)
m = Power units included in the build margin
y = Most recent historical year for which power generation data is available
8
This information shall be provided by the host country.
UNFCCC/CCNUCC
The CO2 emission factor of each power unit m (EFEL,m,y) should be determined as per the guidance in
Step 4 (a) for the simple OM, using options A1, A2 or A3, using for y the most recent historical year for
which power generation data is available, and using for m the power units included in the build margin.
For off-grid power plants, EGm,y should be determined as per the guidance in Step 4.
Where:
EFgrid,BM,y = Build margin CO2 emission factor in year y (tCO2/MWh)
EFgrid,OM,y = Operating margin CO2 emission factor in year y (tCO2/MWh)
wOM = Weighting of operating margin emissions factor (%)
wBM = Weighting of build margin emissions factor (%)
The following default values should be used for wOM and wBM:
• Wind and solar power generation project activities: wOM = 0.75 and wBM = 0.25 (owing to their
intermittent and non-dispatchable nature) for the first crediting period and for subsequent crediting
periods;
• All other projects: wOM = 0.5 and wBM = 0.5 for the first crediting period , and wOM = 0.25 and
wBM = 0.75 for the second and third crediting period,9 unless otherwise specified in the approved
methodology which refers to this tool.
Alternative weights can be proposed, as long as wOM + wBM = 1, for consideration by the Executive Board,
taking into account the guidance as described below. The values for wOM + wBM applied by project
participants should be fixed for a crediting period and may be revised at the renewal of the crediting
period.
Guidance on selecting alternative weights
The following guidance provides a number of project-specific and context-specific factors for developing
alternative operating and build margin weights to the above defaults. It does not, however, provide
specific algorithms to translate these factors into quantified weights, nor does it address all factors that
might conceivably affect these weights. In this case, project participants are suggested to propose specific
quantification methods with justifications that are consistent with the guidance provided below.
Given that it is unlikely that a project will impact either the OM or BM exclusively during the first
crediting period, it is suggested that neither weight exceed 75% during the first crediting period.
9
Project participants can submit alternative proposal, for revision of tool or the methodology or deviation from its
use, if the weightage does not reflect their situation with an explanation for the alternative weights.
UNFCCC/CCNUCC
Predictability of project Can increase OM for Projects with output of an intermittent nature (e.g. wind
output intermittent resources in some or solar projects) may have limited capacity value,
contexts depending on the nature of the (wind/solar) resource
and the grid in question, and to the extent that a
project’s capacity value is lower than that of a typical
grid resource its BM weight can be reduced. Potential
adjustments to the OM/BM margin should take into
account available methods (in technical literature) for
estimating capacity value10
Suppressed demand Can increase BM weight for Under conditions of suppressed demand that are
the 1st crediting period expected to persist through over half of the first
crediting period across a significant number of hours
per year, available power plants are likely to be
operated fully regardless of the CDM project, and thus
the OM weight can be reduced11
For system management (nature of local electricity markets, planning, and actors) and other considerations no
guidance is available at present.
10
Capacity value refers to the impact of a capacity addition on the capacity requirements of a grid system, expressed
as fraction of contribution to meeting peak demands relative to a conventional, dispatchable capacity addition or
to a theoretical perfectly reliable one.
11
In other words, if, consistent with paragraph 46 of the CDM modalities and procedures, one assumes that
electricity could otherwise be supplied to meet suppressed demand, this electricity would need to be provided by
the construction and operation of new power plants, which is embodied in the build margin. In some cases, the
reason for suppressed demand may be the inability to operate existing power plants, due, for example, to lack of
spare parts or lack of availability or ability to pay for fuel. In such circumstances, the baseline scenario could
represent the operation of these power plants, in which case the baseline emission factor should reflect their
characteristics. This situation would likely require a new methodology.
UNFCCC/CCNUCC
• In case the simple adjusted operating margin is used: load data (typically in MW) for each hour of
the year y;
• In case the dispatch data operating margin is used: for each hour h where the project plant is
displacing grid electricity:
12
In case of the simple adjusted OM, this includes the five most recent years or long-term averages for
hydroelectricity production.
UNFCCC/CCNUCC
o Identification of the plants that are in the top of the dispatch and for each plant
information on electricity generation and, where hourly fuel consumption data is
available, data on the types and quantities of fuels consumed during that hour.
In case off-grid power plants are included, the guidance for monitoring data and parameters related to off-
grid plants provided in Annex 2 should also be followed.
The data should be presented in a manner that enables reproducing of the calculation of the build margin
and operating margin grid emission factor.
Measurement -
procedures (if any):
Monitoring • Simple OM, simple adjusted OM, average OM: Either once for each
frequency: crediting period using the most recent three historical years for which data is
available at the time of submission of the CDM-PDD to the DOE for
validation (ex ante option) or annually during the crediting period for the
relevant year, following the guidance in Step 3 above;
• Dispatch data OM: Annually for the year y in which the project activity is
displacing grid electricity or, if available, hourly. Further guidance can be
found in Step 3 above;
• BM: For the first crediting period, either once ex ante or annually ex post,
following the guidance included in Step 5. For the second and third crediting
period, only once ex ante at the start of the second crediting period
QA/QC procedures: -
Any comment: -
UNFCCC/CCNUCC
Generation Technology Old units (before and in 2000) New units (after 2000)
Coal - -
Subcritical 37% 39%
Supercritical - 45%
Ultra-upercritical - 50%
IGCC - 50%
FBS 35.5% -
CFBS 36.5% 40%
PFBS - 41.5%
Oil - -
Steam turbine 37.5% 39%
Open cycle 30% 39.5%
Combined cycle 46% 46%
Naural gas - -
Steam turbine 37.5% 37.5%
Open cycle 30% 39.5%
Combined cycle 46% 60%
Gas turbine systems 28% 32% 34% 35% 37% 40% 42%
Small 7% 7% 7% 7% 7% 7% N/A
boiler/steam/turbine
system
UNFCCC/CCNUCC
13
For example, information on off-grid power generation could only be available for some sectors of the economy.
In this case, only the plants from these sectors may be included in the grid emission factor. However, in including
selected plants, no systematic bias should be introduced (e.g. by including only coal fired plants).
UNFCCC/CCNUCC
In addition, other data may be collected, depending on how the requirements of this annex for inclusion of
an off-grid power plant p in the grid emission factor are assessed and on which options are used in Step 3
of the tool to calculate the emission factor for a class of off-grid power plants m (Option A1, A2 or A3)
and the electricity generation by a class of off-grid power plants m (Option 1, 2 or 3). This may include
the following data:
Note that the same data collection approach should be applied to all off-grid plants in one sector (e.g.
industrial, commercial and residential sector).
Step 1.4: Establish the survey design and management scheme (applicable if a survey is used)
Document transparently the design and methodology of the survey, following best practices in survey
design and statistics. In doing so, the following guidance shall be applied:
• The institution conducting the survey should have relevant experience with undertaking surveys;
• Ensure a proper stratification within the geographical area of the electricity system and within the
different users of off-grid power generation (e.g. considering relevant differences between sectors,
household income, etc). To this end, it may be necessary to conduct a pre-survey to collect
information which sectors, companies or households typically use off-grid power plants;
UNFCCC/CCNUCC
• The results of the survey should be used to derive global estimates adjusted for their uncertainty at
a 95% confidence level in a conservative manner (using the upper or lower uncertainty bound
whatever is conservative);
• The methods used to collect data should strive to avoid any bias and should ensure random
sampling in the various strata;
• Provide objective and transparent methods for data collection;
• Ensure that appropriate procedures for data verification are in place, including relevant quality
assurance and quality control methods;
The DOE should carefully evaluate and confirm that the survey was conducted in accordance with these
principles and best practices for conducting and evaluating surveys.
estimates for the total population, for each class of off-grid power plants m, adjusting conservatively for
the uncertainty at a 95% confidence level.14
• The total capacity of off-grid power plants (in MW) is at least 10% of the total capacity of grid
power plants in the electricity system; or
• The total power generation by off-grid power plants (in MWh) is at least 10% of the total power
generation by grid power plants in the electricity system.
If one of these conditions are not met, then off-grid power plants cannot be included in the calculation of
the grid emission factor of the electricity system. Otherwise, proceed to next step.
Step 5: Assess the reliability and stability of the grid and that this is primarily due to constraints in
generation, and not to other aspects such as transmission capacity
It has to be demonstrated that the grid to which project participants have access is not reliable and not
stable and that this is primarily due to constraints in generation and not due to other issues, such as limited
transmission capacity. To this end, it needs to be demonstrated that
• Shortages, blinks, black-outs, load shedding and/or large variations in frequency and voltage
ranges are common practice in the grid operation. Supporting evidence describing the number,
duration and extent of events related to instability and unreliability of the grid has to be provided
based on project participants or third parties statistics or surveys; and
• This situation is primarily due to constraints in generation, and not to other aspects such as
transmission capacity.
-----
14
Note that this should not include power plants which did not qualify as off-grid following the procedures in Step 2.
UNFCCC/CCNUCC