NO. KONTRAK:
a
ERT! IA
47% PERTAMINAGAS COMMISSIONING ‘S46LL0006A
NO DOKUMEN
PTG-BTG-00-COM-MN-005 ai talenen
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI, DAN
KOMISIONING (PPKK) PENGGANTIAN PIPA 16” MANIFOLD
STATION KM. 53 - SKG BONTANG
COMMISSIONING & START UP PROCEDURE
APPROVED FOR CONTRUCTION
Ten
(tee ULE]
DATE |
The Approval does not relieve
STOR of the responsibility to meet
quirement of the Contract
DATE
contr
RECEIPT
Approved for
(2011
sau : Construction
2erozo1e | Approved for
Design
2siiorzo1e | _'ssued for
Approval
20/10/2016 | Issued for review MzQ GUN
—
Diperiksa | Disetujui
Disetujui
Tanggal Kode Status
KONTRAKTOR
PERTAGASx
s* PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 83 - SKG BONTANG
Doc. No:PTG-BTG-00-COM-MN-
005,
Rev: 1 Commissioning & Start-up Procedure
Page 2 of 18
REVISION TABLE
REVISION
REVISION
REVISION
Ble[p]o|1
PAGE LAMPIRAN
Alele[pjojty2 ale
clolo[t2
>< [><] ><] >< | >< [>< [> | >¢] ><] pe] 9e |< [30 [50 |e [oe Pe Fe P=a
INA JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
M7 PERTAMINAGAS DAN KOMISIONING (PPKK) PENGANTIAN PIPA 46”
: MANIFOLD STATION KM. 53 - SKG BONTANG
Page 3 of 18
eee Rev: 1 Commissioning & Startup Procedure
RECORD OF REVISION
RevNo | Section | Page | CompanyComment | implemented (Y/N) | Explanation
A All All [Tole dileylopi valve Y
poses Check Ut yg ai
Pa ee
Cheers COL EF Mem oy
Hambshe kertke epect
Commit a holamer -.
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
Mf PERTAMINAGAS DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 = SKG BONTANG
Bos, NeiPTS-BTe- 0c: COM-UN Rev: 1 Commissioning & Start-up Procedure Page 0h6:
TABLE OF CONTENTS
PENDAHULUAN..
TUJUAN
DEFINISI....
DAFTAR SINGKATAN.
DOKUMEN REFERENSI, CODE DAN STANDARD
DOKUMEN REFERENSI.
ORGANISASI.,
JADWAL KOMISIONING.
PRA-SYARAT UMUM
KETERSEDIAAN PASOKAN GAS..
KETERSEDIAN PERALATAN, TOOLS, CONSUMABLES, DAN MATERIAL
MATERIAL LAIN...
KERJA SAFETY ..
KESIAPAN SAFETY...
SUMBER DAN IDENTIFIKASI HAZARD.
SUMBER CIDERA...
TIPE KECELAKAAN
KONDISI BAHAYA
. TINDAKAN TIDAK AMAN...
. FAKTOR PERSONAL.
10.3. TOOL DAN REFERENS!
10.3.1. ALAT PELINDUNG PERSONAL...
11, PERSIAPAN KOMISIONING ..
12, KRITERIA PENERIMAAN.
13. PROSEDUR DAN RENCANA KOMISIONING
13.1. RANGKUMAN PROSEDUR GAS-IN
13.2. PERSIAPAN GAS-IN
13.3. TAHAPAN KOMISIONING...r PERTAMINAGAS | JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 63 - SKG BONTANG
Doe, No:PTG-BTG-00-COMMN-
Rev: Commissioning & Start-up Procedure Page Sof 18
13.3.1.
13.3.2.
13.3.3.
13.4,
14,
14.4.
14.2.
14.3.
14.4.
15.
16.
GAS-IN UNTUK PIPELINE DARI MANIFOLD STATION 53 KE SKG
BONTANG ... 15
PRESSURIZING DARI MANIFOLD STATION KM. 53 STATION KE SKG
BONTANSG ...
NITROGEN P PACKING...
KOMISIONING SKG BONTANG ..
OPERAS! UJI COBA ..
TUJUAN OPERAS! UJI COBA.
START OPERAS! UJI COBA
AKTIVITAS DALAM OPERAS! UJI COBA.
PENYELESAIAN OPERAS! UJI COBA
vsa
s* PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 ~ SKG BONTANG
Pee Le eros Rev: Commissioning & Start-up Procedure Page ot 18
4, PENDAHULUAN
PT. PERTAMINA GAS KALIMANTAN AREA berencana untuk melakukan penggantian pipe 16”
yang beroperasi dari Valve Station MANIFOD STATION KM. 53 sampai dengan SKG Bontang dan
telah dibangun pada tahun 1975. Penggantian pipa dilakukan sebagai upaya untuk menghindari
hilangnya integritas (loss of integrity) dan kebocoran gas yang dapat mengakibatkan bahaya
keracunan, pencemaran lingkungan, kebakaran, kerusakan aset di sekitar jaringan pipa (pipeline),
dan kematian (fatality)
2, TUJUAN
Dokumen ini berisi tentang deskripsi tahap-tahap komisioning yang digunakan sebagai dasar acuan
PROYEK
3. DEFINISI
* KLIEN PT. PERTAMINA GAS (PERTAGAS) Kalimantan Area sebagai
pemilik dan pengguna fasilitas
+ PROYEK JASA PERANCANGAN, PENGADAAN, KONSTRUKSI, DAN
4.
* KONTRAKTOR
* KONSULTAN
KOMISIONING (PPKK) PENGANTIAN PIPA 16” MANIFOD
STATION KM, 53- SKG BONTANG
PT TEGMA ENGINEERING, perusahaan atau badan yang
ditunjuk oleh KLIEN untuk melaksanakan semua pekerjaan
PROYEK ini,
PT Surveyor indonesia (PTSI) yang ditunjuk oleh KLIEN sebagai
konsultan manajemen proyek.
+ VENDOR PERUSAHAAN atau badan yang menyediakan material ,
Peralatan dokumen/gambar teknis dan service untuk
melaksanakan pekerjaan PROYEK yang ditentukan oleh
KONTRAKTOR atau KLIEN.
+ micas Perwakilan dari Pemerintah Indonesia yang bertanggung jawab
dalam hal mengeluarkan ijin dan surat jjin fasilitas Minyak dan
Gas,
DAFTAR SINGKATAN
ASME ‘American Society of Mechanical Engineers
vbLr PERTAMINAGAS | ASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 63 - SKG BONTANG
Doc, No:PTG-BTG-00-COM-MN-
005,
Rev: ‘Commissioning & Start-up Procedure
Page 7 of 18
§
6.
BTU
GHV
MAOP
MMSCFD.
NPS
ROW
SG
SKG
‘sMyS
SUTS
British Thermal Unit
Gross Heating Value
Maximum Allowable Operating Pressure
‘Million Standard Cubic Feet per Day
‘Nominal Pipe Size
Right of Way
‘Specific gravity
:Stasiun Kompresor Gas
‘Specified Minimum Yield Strength
:Specified Ultimate Tensile Strength
DOKUMEN REFERENSI, CODE DAN STANDARD
Dokumen code dan standard yang digunakan sebagai referensi dokumen ini dapat dilinat pada
Tabel 4.1.
Tabel 4.1. Code dan Standard
Dokumen Judul Dokumen
ASME B 31.3 Process Piping
ASME B 31.8 Gas Transmission and Distribution Piping Systems
NORSOK P-001 Process Design
API RP 14 Recommended Practice for Design and Installation of
Offshore Production Platform Piping Systems
API RP 554 Process Instrumentation and Control
DOKUMEN REFERENS!
No | No Dokumen Judul Dokumen
1 | PTG -BTG -PRO -DB-001 Process Design Basis
2 | PTG-BTG-00-PRO-DB-003
Philosophy
Instrumentation and Control System
3 | PTG -BTG -PRO-HM -001
Heat And Material Balancea
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
#7A FERTAMINAGAS) | “Th KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 = SKG BONTANG
Doc. No:PTG-BTG-00-COM-MIN-
a Rev:
Commissioning & Start-up Procedure
Page 8 of 18
10.
4 | PTG -BTG -PRO-CL -002
Line Sizing Calculation
5. | PTG-BTG -PRO -PF -001
Process Flow Diagram
6. | PTG-BTG-PRO-PID -002
PID Tie-in Valve Station KM. 53
7. | PTG-BTG -PRO -PID -003
PID Pipeline Area
8. | PTG-BTG -PRO -PID -004
P&ID Tie-in SKG Bontang Area
ORGANISASI!
Lihat Lampiran -1 Organization Chart untuk gas-in.
JADWAL KOMISIONING
Lihat lampiran -2 untuk jadwal Komisioning.
PRA-SYARAT UMUM.
Sebelum melakukan Komisioning pekerjaan, Kontraktor harus mengkonfirmasi kondisi-kondisi
berikut kepada pihak-pihak yang bertanggung jawab. Lihat lampiran-3 "Pre-Requisite Check List’.
9.1. Ketersediaan Pasokan Gas
Pasokan gas dari Manifold Station KMS53 harus tersedia pada saat Komisioning (gas-in),
Proses “Gas-in" akan dilakukan sesuai dengan laju alir dan tekanan yang disyaratkan pada
saat gas-in. Pofil tekanan dan kecepatan gas selama “gas-in” di bawah laju aliran dan pasokan
tekanan ditunjukkan pada Lampiran-4 "Profil Tekanan dan Kecepaten Gas’.
9.2, Ketersedian Peralatan, Tools, Consumables, dan Material-material Lain
|tem-item berikut ini harus tersedia dilapangan dan siap untuk digunakan. Lihat lampiran-5
Peralatan dan Tool yang diperlukan dan bab 4.1
+ Peralatan dan tool yang dibutuhkan untuk mengencangkan flanges non-spark hammer, dll
+ Komunikasi antar stasiun, Handy talky yang akan digunakan di daerah bahaya harus
diperiksa oleh petugas keamanan untuk memastikan kesesuaiannya dengan peraturan
keselamatan. Lihat lampiran-6 Rencana Komunikasi,
KERJA SAFETYr PERTAMINAGAS | ASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 = SKG BONTANG
Doc, No:PTG-BTG-00-COM-MN-
oe Revi4 Commissioning & Startup Procedure Page Gof 18
10.1. Kesiapan Safety
Pipeline dan fasiitas terkait telah selesai dalam segala hal
‘Semua peralatan Kebakaran dan Keselamatan/fasilitas diuji dan dikomisioning
Ketersediaan komunikasi
Telah mendapatkan “Statutory Clearances” untuk peralatan pendukung
Tenaga Kerja yang diperlukan ditempatkan di semua lokasi
Area sekitar Manifold Station KM. §3 dan SKG Bontang dianggap sebagai daerah bahaya
(hazard). Safety Sign, barikade / pagar, iampu flash, megafon dan memasang poster ERP,
ERT, CES, EAS di sekitar daerah itu.
Lokasi di sekitar venting dianggap sebagai daerah bahaya. Alat deteksi gas metana harus
disediakan. Arah venting harus mempertimbangkan arah angin yang aman. Barikade atau
Pagar Sementara (temporary), wind shock dan Safety sign di sekitar venting harus
disediakan selama proses venting bekerja.
Fire Truck siap dilokasi venting.
Ambulance dan paramedis harus disediakan di area Manifold Station KM. 53 dan SKG
Bontang.
Alat pemadam kebakaran portable harus disediakan pada setiap stasiun.
lzin Kerja harus eda
Pastikan Basic Safely Training untuk semua personil lapangan telah dilakukan.
Patroli keamanan bersama harus dilakukan saat komisioning oleh Safety Officer Kontraktor
dan Klien.
Regular tool box meeting harus dilakukan setiap hari.
Alat detektor gas yang mudah terbakar atau gas metana tersedia di setiap stasiun
Tag Keselamatan (Safety tag) harus dicantumkan pada semua valve mengenai posisi
(menutup atau membuka).
Alat Non spark harus disediakan.
Rute evakuasi untuk darurat harus jelas dan bebas dari gangguan.
Alat Pelindung personal seperti kartu ID, pakaian safety, kacamata safety, Pelindung
Suara/telinga, sarung tangan, masker, Red safety jacket, petunjuk angin, dll harus
Gisediakan untuk personil komisioning.
Kotak pertolongan pertama harus tersedia untuk personil komisioning.
“ghM7 PERTAMINAGAS | JASAPERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 ~ SKG BONTANG
Doc. No:PTG-BTG-00-COM-MN-
005
Page 10 of 18
Rev: Commissioning & Start-up Procedure
* Dalam keadaan darurat ERP akan mengikuti peraturan Manifold Station KM. 53 dan SKG
Bontang.
10.2. Sumber dan Identifikasi Hazard
10.2.1.
10.2.3.
Sumber Cidera
Benda, Zat, Exposure atau gerakan yang dapat secara langsung mengakibatkan
cedera,
Mesin + Debu dan Partikel
Kendaraan « Permukaan Kerja
Hand Tools = Material
Bahan Kimia Lain-lain
Zat yang mudah terbakar dan
panas
Tipe Kecelakaan
Kejadian yang langsung mengakibatkan cedera
* Kena Hantaman
+ Terperangkap di atau antara atau bawah
* Menggosok, terkelupas atau Penetrasi
+ Jatuh dari ketinggian
Jatuh
+ Kontak dengan arus listrik
+ Kontak dengan suhu ekstrim
* Kontak dengan radiasi, Racun atau zat Beracun (s)
* Kecelakaan Transportasi
© Lain lain
Kondisi Bahaya
Kondisi atau keadaan fisik yang berbehaya yang diizinkan atau disebabkan
terjadinya kecelakaan
« Susunan, prosedur yang tidak benar, dil
« Cacat
+ Tidak kecukupan (Penerangan/cahaya, Ruang, Lainnya)
tea
s* PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 46”
MANIFOLD STATION KM. 53 - SKG BONTANG
Doc, No:PTG-BTG-00-COM-MN-
005
Rev:1
Commissioning & Start-up Procedure
Page 11 of 31
+ Kelebihan (Kecepatan, Panas, Lainnya)
+ Informasi yang tidak memadai
10.2.4. Tindakan Tidak Aman
Kondisi dimana pekerjaan dilakukan dengan tidak aman
* Beroperasi tanpa otoritas, salah memberi aba-aba atau peringatan
+ Berada pada posisi atau postur yang tidak aman
+ Operasi atau Bekerja dengan kecepatan yang tidak aman
+ Menggunakan peralatan yang tidak aman, Tangan sebagai ganti peralatan.
+ Bekerja pada Peralatan Berbahaya atau bergerak
‘+ Salah menggunakan pakaian yang aman atau Peralatan pelindung diri (APD)
10.2.8. Faktor Personal
‘= Tindakan tidak aman yang dikerjakan
© Sikap
+ Kurang Pengetahuan atau Skill orang lain
+ Cacat Fisik + Lain-ain
10.3. Tool dan Referensi
10.3.1. Alat Pelindung Personal
a. Pelindung Kepala
Topi pelindung yang sesuai aturan harus dipakai setiap saat.
b. Pelindung Mata
Kacamata keselamatan yang disetujui harus dipakai oleh semua personel yang
melaksanaken kegiatan yang dapat menyebabkan cedera mata. Ini juga berlaku
untuk orang lain terletak di daerah di mana pekerjaan yang sedang dilakukan.
Kacamata harus dipakai saat menangani atau membawa bahan kimia. Pelindung
wajeh dan kacamata keselamatan yang disetujui harus dipakai oleh semua personil
yang menggunakan grinder atau buffer.
©. Pelindung Pendengarana
M77 PERTAMINAGAS | ASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 - SKG BONTANG
Doc. No:PTG-BTG.00-COM-MN-
ae Revit Commissioning & Startup Procedure Page 12 of 31
Pelindung Pendengaran harus dipakai di daerah-daerah dimana tingkat kebisingan
yang tinggi (lebih dari 85 db) di mana suara tidak bisa dikurangi atau diisolasi. Contoh
wilayah tersebut adalah:
- Operasi Jack hammer atau tamper
- Operasi atau berdekatan dengan alat berat,
- Grinding
- Bila Anda tidak dapat mendengar seseorang berbicara kepada Anda karena
kebisingan di sekitar
- Operasi Sand Blast
- Operasi Batu bor
Rule of Thumb: Jika Anda tidak dapat berkomunikasi secara normal dengan orang
lain dalam jarak 3 feet dari Anda, pelindung Telinga harus dipakal.
4. Pelindung Tangan
Sarung tangen kerja yang cocok untuk dikenakan saat membawa material panas,
tajam, bahan kasar atau pecah. Sarung tangan tahan kimia harus dipakai seat
bekerja dengan bahan kimia, pelarut, semen, dil
e. Pelindung Kaki
‘Semua orang harus menyediakan dan memakai sepatu yang memenuhi Standar
untuk pekerjaan konstruksi
f. Pelindung Pakaian
Perhiasan atau pakaian longer yang menciptakan bahaya untuk pekerja tidak boleh
Gipakai. Kemeja lengan panjang dan celana panjang harus dipakal setiap saat. Kaos
tanpa lengan tidak boleh dipakai. Kebutuhan untuk pakaian kerja tahan api akan
dievaluasi atas dasar job-to-job oleh Superintendent Proyek dan/atau Project Safety
Supervisor.
9. Pelindung Pernafasan
Pelindung pernapasan yang direkomendasikan, memenuhi syarat yang disetujui,
seperti masker debu atau katrid kimia harus dipakai/digunakan di mana diperiukan.
fh. Pelindung Jatuh
Full Body Hamess harus dipakai dan diikat secara aman ketika bekerja di ketinggian
dan sebagai standard dinyatakan oleh Klien.
SSE
“iePr PERTAMINAGAS | ASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 83 ~SKG BONTANG
Doc. No:PTG-BTG-00-COM-MN-
ne Rev: 1 Commissioning & Start-up Procedure Page 13 of 31
11.
12,
PERSIAPAN KOMISIONING
* Siapkan peralatan komisioning, brass hammer, APAR dan peralatan yang diperiukan untuk
membuka, menutup valve dan HT radio untuk komunikasi.
* Pastikan MDR untuk mekanikal (pipeline, pipa, valve), elektrik, instrumentasi, PSV, peralatan
berputar/ kompresor udara, peralatan pemadam kebakaran, sipil, as built drawing, dan SKPP
yang disetujui oleh pihak terkait (QA / QC dan Pemimpin Proyek).
+ Pastikan peralatan seperti valve Operasi Gas, instrumentasi, unit kompresor udara, dan sistem
sistem kelistrikan dalam keadaan baik (dapat dibuka / ditutup) dan siap untuk dioperasikan sesuai
dengan sertifikat pra-Komisioning.
+ Pastikan peralatan keselamatan (pemadam kebakaran, detektor multi-gas yang telah dikalibrasi,
dll) sudah cukup untuk mendukung pelaksanaan keselamatan kerja selama komisioning
+ Pastikan JSA sesuai dengan SOP yang disetujui oleh Manajer Operasional atau Pejabat yang
memiliki otorisasi untuk pelaksanaan pekerjaan.
* Siapkan tim Komisioning & Start Up, Team Leader untuk Komisioning dan start up.
+ Siapkan kru instrumentasi, mekanikal, dan elektrikal
* Siapkan kru kontraktor (PT. TE), yang memahami pengoperasian peralatan operasi (valve, unit
kompresor udara, instrumentasi,listrik, dan sistem venting).
* Pastikan unit kompresor udara bekerja dengan baik dan pasokan udara instrumen untuk semua
peralatan instrumentasi normal untuk melakukan tes fungsi individual.
+ Pastikan komposisi kimia sesuai untuk injeksi
+ Pastikan Pompa injeksi Kimia bekerja dengan balk.
+ Mempersiapkan dan pastikan suku cadang untuk komisioning sehingga tidak mengganggu
Jadwal komisioning karena peralatan rusak.
+ Melakukan safety talk dan berdoa sebelum pekerjaan dimulai.
KRITERIA PENERIMAAN
Komisioning (gas-in) dianggap selesai jika memenuhi kriteria berikut ini,
@. Pipeline dan stasiun diisi dengan minimal komposisi 85,68% dari gas alam (metana) diukur
dengan gas kromatografi Manifold Station KM. 53. Titik pendekteksian gas akan berada di titik
venting dan SKG Bontang.
b. Komisioning sistem pipeline distribusi gas (Manifold Station KM. 53 ke SKG Bontang) akan
SSSPr PERTAMINAGAS | /ASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 - SKG BONTANG
Doe, No:PTG-BTG-00-COM-MN-
oe Rev.t Commissioning & Startup Procedure Page 14 of 31
13.
dilakukan di bawah kondisi operasi normal sebagai berikut:
[ Gas Flow Rate 98 MMSCFD
Gas Supply Pressure 900 psig di Manifold Station KM. 53
ee epee reer
Lalu aliran dan tekanen pasokan ke dan tekanan keluer gas di Manifold Station KM. §3 yang
sesuai jadwal operasi Klien. Jika laju aliran dan tekanan pasokan di Manifold Station KM. 53
Station tidak dipenuhi jadwal operasi Perusahaan selama Operasi Uji Coba Kontraktor, di atas
kriteria penerimaan No.2 diatas harus diperiksa hanya berdasarkan estimasi perhitungan
maksimum laju aliran yang tersedia dan tekanan pasokan selama Operasi Uji Coba.
©. Tidak ada kebocoran selama pengiriman gas pada tekanan operasi dengan mengecek
menggunakan detektor gas pada semua flange ditutupi oleh selotip selama dan setelah gas-in.
d. Berhasil menyelesaikan Operasi Uji Coba.
PROSEDUR DAN RENCANA KOMISIONING
13.1. Rangkuman Prosedur Gas-in
Gas-in akan dilakukan dari Manifold Station KM. 53 ke SKG Bontang. Sebelum gas-in,
Pastikan tekanan nitrogen didalam pipeline minimal 7 psig. Laju alir selama gas-in harus
dikendalikan oleh valve blok di pipa kicker (Manifold Station KM. 53). Perkirakan laju alir gas
akan berapa pada 10 MMSCFD pada awal gas-in dan kecepatan gas akan 42,6669 m/s. (Lihat
lampiran -4)
Maksimum laju aliren gas yang dapat digunakan untuk komisioning diharapkan sebesar 99
MMSCFD dan disebut dalam prosedur ini, Pertagas akan mengkonfirmasi laju aliran yang
‘sebenamys tersedia berdasarkan kondisi operasi aktual dengan menyesuaikan bukaan valve.
Ball valve akan dioperasikan secara Hand wheel selama tekanan internal pipa rendah. Ketika
tekanan intemal pipa cukup untuk pengoperasian aktuator, aktuator akan dioperasikan oleh
tekanan gas.
13.2. Persiapan Gas-in
a. Periksa dan catat tekanan pipeline di hulu (tekanan Manifold Station KM, 53)
', Periksa nitrogen purging di hilir selesai dan tekanan nitrogen di pipeline (min 7 psig).
. Periksa kesiapan Metering di SKG Bontang untuk menerima gas.Pr PERTAMINAGAS | /ASA PERANCANGAN, PENGADAAN, KONSTRUKS!,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 ~ SKG BONTANG
Doo. No:PTG-B8TG-00-COM-MN-
005.
Rev: 1 ‘Commissioning & Startup Procedure Page 15 of 31
d. Mengatur posisi valve sesuai dengan lampiran-7 posisi valve check list.
e. Letakkan Lockout tagout (LOTO) di semua valve.
13.3. Tahapan Komisioning
Komisioning dari Manifold Station KM. 53 ke SKG Bontang akan dikendalikan oleh Operator
Manifold Station KM. 53 sesuai dengan instruksi dari control room SKG Bontang berdasarkan
prosedur KONTRAKTOR
Bab ini akan menjelaskan prosedur komisioning untuk setiap stasiun. Untuk tahapan prosedur
komisioning yang lebin rinci dapat dilihat pada lampiran-8.
13.3.1.
Gas-in untuk Pipeline Dari Manifold Station 53 Ke SKG Bontang
Gas-in Pig Launcher Area — Pig Receiver Area (Lihtat lampiran 12 P&ID)
Gas-in Pig Launcher Lokasi - Pig Receiver Lokasi akan dilakukan dengan prosedur
berikut.
- Pastikan valve pipa kicker V-1529-6"BA003 (6'-PG-A03B-1510) di Pig Launcher
dibuka dan V-1506-16"BA003 (16’-PG-A03B-1501) ditutup, Perkiraan laju alir gas
akan menjadi 10 MMSCFD pada awal gas-in. Dengan memeriksa indikator
tekanan PG-001 (di Pig Launcher J5-03-PLR-M002B) dan PG-002 (Pig Receiver
J5-03-PRC-M002B), laju aliran akan dikendalikan ..
Gas kemudian dilewatkan ke Pig Launcher (J5-03-PLR-MO002B) dan mengalir
melalui Manifold Station 53 ke SKG Bontang,
b. Gas-in untuk pipeline dari Manifold Station KM. 53 ke SKG Bontang
~ Buka valve V-1513-16"BA003 dan valve dekat V-1512-16"BA003 ditutup ketika
Manifold Station KM. 53 telah dimulai gas-in.
~ Vent nitrogen dengan throttling %GA087 (PG 5303) dan V1521(J5-03-PRC-
Mo02B) ketika tekanan di PG 5303 mencapai 10 psig dan menjaga tekanan ini
dengan secara bertahap meningkatkan bukaan %GA087 (PG 5303) dan
16521 (J5-03-PRC-M002B). Pelepasan tekanen dengan membuka valve secara
perlahan untuk menghindari penyebaran gas ke sekitar daerah.
~ Setelah metana terdeteksi dalam gas yang dibuang minimal komposisi 85,6% dari
gas alam (metana) diukur dengan “gas chromatograff’ SKG Bontang dengan
detektor “portable gas". Periksa valve vent sepenuhnya ditutup dengan melakukana
| 47 PERTAMINAGAS | ASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 = SKG BONTANG
005
Doc, No:PTG-BTG-00-COMMN-
Rev: Commissioning & Start-up Procedure Page 16 of 31
13.3.2.
13.3.3.
tes gelembung.
Pressurizing Dari Manifold Station KM. §3 Station Ke SKG Bontang
= Setelah menyelesaikan gas-in dari Manifold Station KM. 53 Station ke SKG
Bontang akan mula ditekan.
~ Selama pressurizing, laju alir gas harus dijaga 99 MMSCFD. Dengan memeriksa
pengukur tekanan PG-001 (Pig Launcher J5-03-PLR-M002B di Manifold Station
KM. 53) dan PG-002 (Pig Receiver J5-03-PRC-M002B di SKG Bontang), flow rate
akan dikendalikan.
~ Ketika tekanan up-stream dan hilir hampir sama kedudukan, valve V1508 (16"-PG-
A03B-1501) dan V1512 (16°-PG-A03B-1505) dibuka, dan valve V1503 (8°-PG-
A0SB-1510), V1513 dan V1517 (16'-PG-AO3B-1505) serta V1514 (8"-PG-A03B-
1507) ditutup. Ketika tekanan di pipa mencapai tekanan operasi saat ini,
pemberian tekanan selesai.
= Depressurize Pig Launcher J5-03-PLR-MO02B di Manifold Station KM, 3 dengan
membuka V1526 dan Pig Receiver J5-03-PRC-MO02B dengan membuka V1521
sampai tekanan akhir 0 psig.
Nitrogen Packing
- Kegiatan Nitrogen blanketing dilaporkan dalam Laporan harian Komisioning dan
ditanda tangani oleh Pertagas/PMC and TE, Lihat Laporan Harian Komisioning
pada lampiran -11,
- 4" bypass vent line harus diisi dengan nitrogen pada tekanan 10 psig.
13.4, Komisioning SKG Bontang
Lihat lampiran -13,
14. OPERAS! UJI COBA
14.1, Tujuan Operasi Uji Coba
Setelah selesai komisicning, Operasi Uji Coba harus dilakukan.
Tujuan Operasi Uji Coba adalah untuk memverifikasi bahwa fasilitas pipeline dapat beroperasi
ata
s* PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16” |
MANIFOLD STATION KM. 83 ~ SKG BONTANG
Doc. No:PTG-BTG-00-COM-MN-
005
Rev:
‘Commissioning & Start-up Procedure Page 17 of 31
dalam kondisi yang stabil untuk jangka waktu minimal 14 hari, Setiap shutdown atau
kegagalan karena masalah yang timbul dari pipeline selama Operasi Uji Coba, Operasi Uji
Coba harus direstart dan re-run,
14.2, Start Operasi Uji Coba
Setelah menyelesaikan proses kenaikan tekanan pada pipeline (pressurization of pipeline)
hingga SKG Bontang tekanan operasi pipeline di Manifold Station KM. 53 dialinkan dari 12"
garis kicker ke 12" jalur utama, yang merupakan kondisi operasi normal. Kemu
n Operasi
Percobaan dimulai. Mengacu pada Laporan Kegiatan pada lampiran-10 konfirmasi dimulainya
Operasi Uji Coba.
14.3. Aktivitas Dalam Operasi Uji Coba
Sesuai dengan tujuan Operasi Uji Coba disebutkan di atas Bagian 14.1, kegiatan utama
adalah untuk memantau kondisi operasi dari sistem pipa untuk memverifikasi apakah pipa dan
stasiun beroperasi di bawah kondisi yang stabil
Parameter operasi berikut dipantau dan dicatat selama Operasi Uji Coba.
- Flowrate
- Pressure
- Gas Temperature
Parameter operasi dicatat setiap 1 jam dan dilaporkan kepada Pertagas dan PMC oleh harian
selama Operasi Uji Coba
Parameter operasi dirangkum dalam "Parameter Operasi Selama Uji Coba Operasi" dalam
lampiran-10.
Juga mengacu pada Laporan Harian Komisioning di lampiran-11 untuk data yang tercatat di
Manifold Station KM. 53 dan SKG Bontang.
14.4, Penyelesaian Operasi Uji Coba
Pengoperasian pipeline dilanjutkan dalam kondisi stabil tanpa adanya shutdown sejak awel
Operasi Uji Coba sampai melewati 14 hari. Ini berarti bahwa Operasi Uji Coba berhasil
diselesaikan.
Mengacu pada ‘Laporan Pemyataan Operasi Uji Coba Komisioning’ pada lampiran-10 untuk
konfirmasi penyelesaian Operasi Uji Coba antara Tim komisioning Pertagas, PMC dan TE.
15. REPORT(7% PERTAMINAGAS | ASA PERANCANGAN, PENGADAAN, KONSTRUKSL
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16" |
MANIFOLD STATION KM. 53~-SKGBONTANG =
|
Doc. No:PTG-BTG-00-COM-MN-
005
Rev: ‘Commissioning & Start-up Procedure Page 18 of 31
16.
Kegiatan komisioning harus dilaporkan tiap hari ke Klien/Engineer. Check List komisioning
dilampirkan sebagai
lampiran-3, lampiran-7 dan lampiran-8 harus ditandatangani oleh
Klien/Engineer pada setiap kegiatan dan akhimya diserahkan sebagai bagian dari Laporan
komisioning,
LAMPIRAN
LAMPIRAN 1
LAMPIRAN 2
LAMPIRAN 3
LAMPIRAN 4
LAMPIRAN 5
LAMPIRAN 6
LAMPIRAN 7.
LAMPIRAN 8
LAMPIRAN 9
LAMPIRAN 10
LAMPIRAN 11
LAMPIRAN 12
LAMPIRAN 13
Chart Organisasi
Jadwal Komisioning
Pre-Requisite Check List
Pressure Profile and Gas Velocity
Equipment And Tools List
Rencana Komunikasi
Valve Position Check List
Step by Step Commissioning Procedure
Activity Report
Record Of Operating Parameters During Trial Operation
Commissioning Daily Report
PaiD
Langkah Komisioning SKG BontangPr PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 - SKG BONTANG
Doc. No:PTG-BTG-00-COMMN-
005
Rev t
Commissioning & Startup Procedure
Page 19 of 31
LAMPIRAN 4
Chart Organisasi-aysequeg
L10z 340% BueWoR
Loney
sO
soswuodng
sosniodng Suorssqut09
Byvorssqunuo, 9 BueIoR OAS es wot unsas pomuen
Josniadng 3SH Jeourbu3 BuessusWOD 422480q Bujuorssqus0S
preupieog as werisey
Wal SNINOISSINWOD NOILVZI. 5SuOa
s* PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 83 - SKG BONTANG
Doc. No:PTG-BTG-00-COM.MN-
005
Rev: 1 Commissioning & Start-up Procedure
Page 20 of 31
LAMPIRAN 2
Jadwal Komisioning
ofne
ay ues
cr0z8HN tueo9
mann
(840 9.035010 18e1 ene nee
‘us3dojnuny Out
Jenga dso pf Ge 8 oe
(omooy Kemi S08 0106}
18
"7 099) SH EF EIKSEH oH rr ~
23 emg
ov wo wep
ej voteunaiica es -
(918 98 “ea04 SH) oo n1-
edd poem
‘4s 6 ONIMOIESINNOD P2D0% erase onsa
urseg lemper Z~- wesydure,
ony
stoe-rr-2:310a
s* PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 = SKG BONTANG
Doc, Ne:PTG-BTG-00-CONLMN-
005
Rev:
Commissioning & Start-up Procedure
Page 21 of 31
LAMPIRAN 3
Pre-Requisite Check ListPRE-REQUISITE CHECK LIST
——
No. Deverpton
ate | Hour
Remarks
[cox Pipaine can Staton "Ready lo Guedes per Mechanical
[compton
[are ear ands Stason dan 6K Bortarg adh
lrs nazar. Stety ir, barcadeence, fash ight
jrevopnene end cosayed ERP, ERT, EOF, EAS horse
|spesang cere
[cca soar vering cananen scbapal ara fararé at eas
los Mehana nan desist ara vera Pas
2 |rampersmsangian aah engin menu oka yang amen,
|Beccede stu pagers sack dan sat sgn Terporany
lectrvenung ers desdaan seams proses verng.
|amauiane can paramos hau deck are nto
Stoves Wo 58 an SxG Berar
|v pernacar abotaran porate nus Gece pace
© | setap staan
Mens tanun 1 83
oxG octane
Mantas M53
‘SKS Beary
Manto Sasa M83
‘Ske bern
Mnfls Ses 59
'SkG Beran
Mant Sas 058
‘SK Bertarg
afl San eM 53
‘SKC Bonny
Manto Staton KU 83
‘Ske Berare
ail Stes eM 53
‘SG Born
Mani stasun 1M 53
‘Sk Bonar
anos Sask 53
‘Sx6 Born
Mantld Sasi 0453
‘So Boron
ans Stasin kM 53
‘SG Botan
Mantld Sain 53
‘KG Born
Manto Sasin kM 53
‘sk sorarg
Manfld asin XM 53
‘SO Berang
same
soft
‘CHECKED BY PERTAGAS ‘CHECKED BY PMC
[Date bate
“gea
s* PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16"
MANIFOLD STATION KM. 83- SKG BONTANG
Doc. No:PTG-BTG-00-COMMN-
005
Rev: 1 ‘Commissioning & Start-up Procedure
Page 22 of 31
LAMPIRAN 4
Pressure Profile and Gas Velocityan
ZvPxuxy/T=V seoveo0 = (any)
L608c0'9 = (s0ynu) re
goearor = (puooes) =) UONEANG
gece’? se000%9 600% «= «= (S/W) (A) Arto 0}0, SED
secoeol l6chzze L2628VS = (S/MN) apy oyesmoy
zo Mtow/ues8}aexla/ BO L/v6E 18'L0962 pees: = cw ° nd #0
Kevan] ZA)=4 LELOSEZ COBEILE eo8eLtL = (H/e) sia
02 sh ot =(agoswn) (4) BPIMOld SO
ew aw aw
Live fz 7Z__[veee [vase (4) gosez0 = (y) Buedweueg sem
(w/a)? d[ew/ai) © fav/a) © |leu/ad +o (au ovevsn == (aya siEcz = (6) Aysueg 90H
L661 =
880 =
£LL80 =
OD ve'eee = (3) ve69 = 1) 7N9 eynexeduio,
Ease eisqe uNe|LZ d/T XT A=ZA Ob zesez = (08 = 1) uf exmereduo
qe une st'9e = @sd) igies = (Gd) 319 eunssoig
sqe une 72'19 = 96) 006 = (ld) uf eunssoag
"Pe ZyPXUX G/T
(4) LSOL9L =
w QOOEt = (uy) ob =
w 9p0r0 = (uy OL =
Buequog DIS ~ CSW PIOHUEW 91 Suéjodid UeRUERFUEG BuIUE}s!N0,
APOOjaA SB PUe a[YO1d eINSSAg
6
Leta
M® PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 - SKG BONTANG
Doc. No:PTG-BTG-00-COM-MIN-
005
Rev: 1
Commissioning & Start-up Procedure
Page 23 of 31
LAMPIRAN 5
Equipment And Tools Listwaz | ouvert a ruLona st
wp aL ‘Beug] ee
= TRISTE WONT
- re SSSSS088 JESS. NYY ASVD Vay S¥AKY
a” cl =e aL ‘suttys Suyuan |
> Dino wapeEN eA Ta
5 Serr) Tnmegeieg hopes]
z DSW ‘wu aka ommaea) OF
=a [oun esror | a ee
= a avmaal
we eras) a aemewa mo enmoeal_c
Be aL Tommaayeis| 9 |
ee a Bae Buea) §
BOL a WSL EINES Aouatowg] —p
aL
— a ———_}—2 aaaee i
aL
| eae = | me a a “ava sadnal
no@nso | oun res eM at | Gopangyoesntunea one oneal]
= 001 a Trae a
Zl Or aL sassuit Kayes y|
eee ala as OF a a i ~yeoomey 3] |
7 bor | a so pot a
of Loo re | oa a us Ayes | |
wor aL ay Ayes“
a SSeS wor | | mee
7 jr saa] 1
Sars V]
TT oa aa, cs cn i=
SSOUNINA ——L
Trea
ia 817 81001 B wowldinbz:ae aL soeud wopsotdta ape foun] ex |
DISS WN a agers 04 tN] EE
~| a
aa el st ee
Tk wr aL ‘ys sounumy seg -|
aan : ae 7 a}
xo aL (qesaw99) 19g J001]
a dea
fa a aL © odes sodeg unysey -|
er : aL i oeotoe 94
an [at ra
Mos Z aL Bey -|
eee Io eect | eet aa i etwas =|
ata | ae : :
es | = poe mee ne
a = = “a spiquamsung ¥y eg aKS| GT
i oo 99
nae 7 2 i a a Na -951m/a0H0q 7
eos i “aL sous |
a © a Peary - sours
i: Sates Pra ata wAKO/VEDS ¥|
if ah 7 MPN) 8
t aL auoudwiow VOL
z a “pos pa
L
Tea
“Thoziviee
bono
IST st001 @ wowdindsDig AS GORD,
Dw a OID
Loney
aL ‘o107] Fe
aL ‘ayo al] et
Pet En (yom zi Amana] ze
aL sea + Bumsoia) Te
wr aL sous) OF
mea a (oOPIA ¥ 8104) wopewouNd0G] Gz
we “Ss nuy Ts wd si spnpuy preoa ana) 6
ep Sa eS WO an “a a9ppET yay] gE
wae, Due eS aL samy] iz
wun Dua es an ew] 9
wns DLA Pes WH a wedues won] sz
wns eH au wou} 1
a eid [Sad avec vse, wone3eT
sou
Thoaiez
SMT S104 8 wowinga
tt PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI, |
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16"
MANIFOLD STATION KM. 63 = SKG BONTANG
©
‘Dos. No:PTG-BTG-00.COM-MN-
005
Revit
Commissioning & Startup Procedure
Page 24 of 31
LAMPIRAN 6
Reneana KomunikasiLiz WHEW “FuewoR,
wees woooWd |!
voneredo sedeved |!
NV1d NOLLVSINNINWOD:a
M® PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 ~ SKG BONTANG
Doe, No:PTG-BTC-00-COMMN-
005
Rev
Commissioning & Start-up Procedure
Page 25 of 31
LAMPIRAN 7
Valve Position Check List‘VISANOGNI HOASAUNS “1d AG GEIIHO
WoqSSuIOD ein
WO di Fie TeNBOe
90 di OF 8UrT UE
90 dil OF 8UrT WIE
90.41 oF SUT UIE
Bo dil 01 98ND ASd Jonsooy
20 di 0} 9ury sseu Ag
20 di ovaury s8d Fa
20 di 0) 8un $Sed AG
WS) TONOOY
‘OURIER JONESER
20} 0] S| cvfeafor] $]os]ov
IS
Bunse our Ue
Teiul Jeno
a ‘ONVLNOS OS
$00-NW-NOD-00-D18-D1d weierimeae conwod on
waeWNN LNaWND0G Ps
ONVLNOa
‘OMS - £S WM NOLLVLS CIO4INVW 91 Vdld NVLLNVDONAd (dd) svownnvie ull
ONINOISINOY NV ISMNYLSNOM ‘NVVGVONAd ‘NVONVONVaad VSVr A
ONVINOS OS: NOLLW9O1
biOF
2> LNSWHOWLLV ( LSI HOSHO NOLISOd SAA TWA Z- 318VLa
M® PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 46”
MANIFOLD STATION KM. 53 = SKG BONTANG
Doc. No:PTG-BTG-00-COM-MN-
005
Rev: 1
Commissioning & Startup Procedure
Page 26 of 31
LAMPIRAN 8
Step by Step Commissioning ProcedureJ208S OAJEA eyNquoU UeBUEP UeUeys} UESeda[eq
(GZ00W-OUd-€0-SP) 8¥00-A UEP (VrOO-Id) LOOvA
ueeyng ueyeyBuluow deyeyeg eseo9s ueBUEP
ueueyo} eGefuew uep Bisd g} fedeouew ypOO-Id
Ip weuero} eM (AZOOW-OUd-0-S7) GPO0-A UEP
(P00 -Id) LOWS .% Buygouyy UeBuep Uabo.U TUS,
urseb re|nUuIp Ye}ey
£5 "WH UOISeIS ployueW exe dnNYP EOOVE.OE
“ELLA JEMOP enIEA UEP EOOVELOI-LZL-A ene B4NG
Buewuog ONS OF UONEIS projNveW wo oujedid 10) ur-seD
‘Buejuog OS 24 UONEIS eS
UoISeyg PloJUeYY Injejau ay}eBUAW UEP (GZOOW-UTd
~80-Sf) JeyoUNe] Big @¥ UEMEMEHP UEIPNWIEY SED
~ URHIFEpUBP UEHE
ewe nfe} \(2Z00N-ONd-£0-SP 4enI208y Bid) VO
“Id uep (GZOOW-ATd-€0-Sf 4o4oUNET Bid IP) Szes
“id UeUEYa} JO}E>Ipul esxOWEW UeGYEG “Ul-seB
Jeme eped GJOSINW O} Ipeluew ueye se6 aye nile
ueewieg “dnynyp (LOS}-Ee0W-Od-.91) £00WE.9b
Gb-A vep exNaIp seyoune? Bid |P (0LSL-GEOW-Od-.8)
S00VE.8 Bb-A UEP SS-A JOyO14 Edid enjen LENSE
eely 10nj600y Bid — eouy 10yoUNE Bid USED
‘Dia | S¥DVINId on | S34 |
an 8 vone201 ons oN
seUION ee OH ned oune v
‘DNINOIS SNINOBSIMINOT dS Aa gas:
£s0T“1es@jas UeUE Noy
uevequied ‘iu yees yseiedo ueueye; redeouow
edid 1p ueueys; eyney “dmynyp (Z0S1-Ge0V
“Od-.8) ¥LI-A UEP OBL-A EHS (G0S}-BE0V-Od
~.91) ZLL-A UEP LZL-A (OLS1-GE0V-Od-.8) BP-A UEP
SS-A OAJeA Uep ‘exNeIP (GOSL-BEOV-Od-.91) ELL
“A. uep (L0S1-GE0¥-Od-.91) 6A aA/eA ‘UeYNPNPSy
ewes sidwey uy uep weans-dn ueveys} exNey| 6
“weyJepuaIP
ueye eye moy ‘(Buejog OS IP EZ00W-DYd-€0-S
48N}9094 Bid) VOO-Id UEP (ES W> UOISEIS PIO!UEW
IP GZOOW-H1d-€0-St seyoune] Big) Szes-Od
ueueye} anjnBued esyyewow ueBuEg “GJOSINN,
66 e6ellp sniey se6 aye nfei ‘Suzunssaid ewes] ¢
“ueuey9} Leqip tejnw Ueye Buewwog OS O1 ES W>1
UOISe}S PIOJUEW LEP Ul-seB ueresejeKuew YeI}eS |Z
Buejuog OS © YOREIS € "WH UOHEIS plosueW 14eq BulZyNssog
‘Bunquieje6
S08} ueyMefou ueBuep dnynyp ekuynuedes:
quan anfen esyued “e|qeyod se6 Jopjajep ueBuep
Buewwog oS se6 yesBojewory ueGuep anynip
(euejow) weje se6 uep %9'¢9 Jsisodwoy yeunurus
Buengp Suef se6 weep 1sye}eps0} eueyeu ye|sIeg | ¢
“Yelsep JEWS:
ay se6 ueseqefued wepurySuew ymun ueyeyed
e107 ‘DDNINOW SNINONSINNOD GIS AT aaISoe
[)= uendure) eped Buorsiwioy
ueye}y uesode7 yeUr “BL pue OWa/SeBeLed YeIo
jueBue} epueyp uep GulLlolsiuoy, ueweY UeLode
weep uepodeyp Guyeyueq vabomN ueVeIBey| LL
Buppeg webonN
“Bysd 0 ype UEUENE, feduies @yOO-/ exnquIEW
ueBuep gZ00N-ONd-E0-sf seNs9¢y Bid UEP
OIZSI-A eyNquiow UeBuEp Eg “W>i LOISEIS PIO}UEW
1 GZOOW-AId-0-SP sYoUNe] Big ezuNssoideq | OF
E10€
‘SONINOIS ONINONSININGS GALS AT aSa
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
PERTAMINAGAS | SAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
3 MANIFOLD STATION KM. 53 - SKG BONTANG Zs
Doc. No:PTG-BTG-00-COM-MN-
sit Rev: 1 ‘Commissioning & Startup Procedure Page 27 of 31
LAMPIRAN 8
Activity ReportLAPORAN KEGIATAN
Kami telah melakukan Gas-in and Pressurizing di Manifold Stasion KMS3 ke SKG
Bontang pada Maret,2017 AM/PM
Kami konfirmasi seperti dibawah ini:
18:00 Cek tekanan
Tekanan Operasi saat ini : psi
Tekanan i psi
Flow rates Manifold Stasion KMS3_ : MMSCFD
Open 12”°BA016 (SP-50-12”-PG-A06B-108/SP-50-12"-PG-A06B-111)
Close 12"BA016 (SP-50-12"-PG-A068-110),
Close 16” BAO15 (SP-58-16"-PG-H068-104/SP-58-16"-PG-H068-105)
No. Nama Perusahaan ‘Tanda tangan
L. PERTAGAS
2. PMC
neKomisioning Tahap ke 2
LAPORAN PERNYATAAN OPERASI UJI COBA
Kami menyatakan bahwa Operasi Uji Coba telah selesai_ seperti dibawah ini.
Mulai
Selesai
Maret 2017, hours
Maret 2017, hours
Selama Operasi Uji Coba ini, pipeline instalasi aksesoris beroperasi sebagaimana
mestinya,tidak ada shutdown operasi dan kondisi flow stabil, Oleh karena itu
dinyatakan bahwa pipeline, stasiun dan SKG telah beroperasi dalam kondisi stabil
selama periode 14 hari.
Kondisi Flow pada akhir Operasi Uji Coba adalah ;
Manifold Stasiun KMS3
Flow Rate (MMSCFD)
Pressure (psig)
SKG Bontang
Flow Rate (MMSCFD)
Pressure (psig)
Confirmed by:
No. Nama Perusahaan Tanda Tangan
1 PMC
2 PERTAGAS
i Commissioning
3. PERTAGAS Operasi
Atea
M® PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 46"
MANIFOLD STATION KM. 53 - SKG BONTANG
Doc, No‘PTG-BTG-00-COM-MN-
005:
Rev: Commissioning & Start-up Procedure
Page 28 of 31
LAMPIRAN 10
Record Of Operating Parameters During Trial OperationI loshse ut pee sebeseame,
Co meuad rego
LAMPIRAN -10.. CATATAN PARAMETER SELAMA GAS‘IN" PRESSURIZING
DARI MANIFOLD STASIUN KMS KE PIPELINE & SKG SONTANG
Report No
no} oare ME
a0EM prcanitens 2
4
LAMPIRAN - 10 . CATATAN PARAMETER SELAMA OPERAS! UJI COBA
DARI MANIFOLD STASIUN rs
E PIPELINE & SKG BONTANG
Location
me
QkMs3
Pipsig) | tempt Remarks
0700
08.00
10:00
1200
19:00
14:00
18:00
0
1600
17:00
18:00a
A PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 46”
MANIFOLD STATION KM. 53 = SKG BONTANG.
Deo, No:PTG-BTG-00-COM-MIN-
005
Rev: Commissioning & Start-up Procedure
Page 29 of 31
LAMPIRAN 11
Commissioning Daily ReportTANGGAL
LAPORAN HARIAN
KOMISIONING
KEGIATAN
DIPERIKSA OLEH PMC DIPERIKSA OLEH PERTAGAS:JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 46”
MANIFOLD STATION KM. 53 - SKG BONTANG
a
A PERTAMINAGAS
Doo, No:PTG-BTG-00-COM-MN-
oe Rev: Commissioning & Start-up Procedure Page 30 of 31
LAMPIRAN 12
PaiDSs __
ia
4
{
Iz}
Ls a
zl ea lols ers = ry
} acsocmer| | Sls aeeat sy
Fad =e peng hay
i a
| ld
i 9)
|
LI H
G G
L | Resetaeuzit H
ie = 4 {el
z| oe 2]
Hy lee L
4 'La
eS A: SE aS SS SS SSS a ee «a
M# PERTAMINAGAS
JASA PERANCANGAN, PENGADAAN, KONSTRUKSI,
DAN KOMISIONING (PPKK) PENGANTIAN PIPA 16”
MANIFOLD STATION KM. 53 - SKG BONTANG
Doe, No:PTG-BTG-00-COM.MN-
05
Rev: 1
Commissioning & Start-up Procedure
Page 31 of 31
LAMPIRAN 13
Langkah Komisioning SKG Bontang
midLANGKAH-LANGKAH RENCANA PELAKSANAAN
COMMISSIONING
Tanggal:_ Maret 2017
Pelaksana : PT. Pertamina Gas
A. PERSIAPAN COMMISSIONING
1. Safety Talk / Tool Box Meeting sebelum kegiatan Commissioning dimulai
2. Pastikan name tag sudah terpasang sesuai dengan schematic terlampir
3. Pengisian nitrogen pada tekanan 100 psig dan leak test
4. Funetion Test harus dilakukan terlebin dahulu meliputi : Actuator, PCV, PSDV,
Transmitter, dan HMI (Human Machine Interface)
5. Pastikan masking tape sudah terpasang di setiap flanges
6. Memastikan seluruh jalur pipa yang akan dilakukan Commissioning telah terisi Na
Mulai dari valve V-45 sampai valve V-173 dan kadar oksigen di dalam pipa maksimal
2% dan tekanan minimal 0.5 bar
7. Memastikan peralatan-peralatan dan kelengkapan sudah terpasang dengan benar,
laporan kesiapan mulainya pekerjaan Commissioning dilaporkan oleh masing-masing
koordinator group kepada Ketua Tim Commissioning. Commissioning dapat
dilaksanakan setelah ada instruksi dari ketua Tim
B, PERALATAN YANG DIGUNAKAN
Gas Detector 9. Waming Board
Too! Kit anti spark 10. Valve Tag Number
N2 (Nitrogen) 11. APD
Bubble Test
Masking Tape (Isolasi)
Emergency Car (ambulance)
Tenaga medis
Fire Brigade
@NOARON=
C, PROSEDUR LANGKAH KERJA COMMISSIONING
C.ATAHAP N2
1. Pastikan rangkaian spool sudah terpasang dengan baik sesuai dengan gambar
2. Pastikan sudah dilakukan leak test 1.1 x MOP dengan hasil yang baik (BA terlampir)
3. Pastikan semua valve terbuka kecuali valve di V-48, V-55, V-50, V-51 (Launcher Area)
dan V-171, V-172, V-180, V-174 (Receiver Area) dalam kondisi tertutup sempumna
(Closed) atau sesuai tabel kondisi awal valve sebelum Commissioning
4. Pastikan N2 sudeh terisi pada jalur pipa tersebut dengan ketentuan kadar oksigen di
dalam pipa maksimal 2% dan tekanan minimal 0.5 barg
45, Jika kadar dan tekanan N2 didalam pipa belum memenuhi syarat diatas maka
dilakukan penambahan N2 melalui venting V-5321J dan dicheck Kembali kadar
oksigen pada V-004C untuk memastikan kadar oksigen sesual dengan yang
disyaratkan
C.2COMMISSIONING
1. Buka valve V-48, V-55 periahan sampai dengan 5% bersamaan dengan valve
venting V-1621C & V-004B sampai kadar gas methane 85% kemudian tutup Kembali
valve venting V-1521C & V-004B .
2. Setelah mencapai tekanan 150 psig tutup V-48 dan V-85. Tahan selama 60 menit
dan Lakukan leak test, jika ditemukan kebocoran maka lakukan pengencangan baut
pada flange yang leak.
3. Naikkan tekanan dengan membuka valve V-45 secara perlahan hingga tekanan
operasi
4. Tahan selama 60 menit setelah itu lakukan leak test, jika ditemukan kebocoran maka
lakukan pengencangan Baut pada flange yang leak.
5. Buka valve V-45 perlahan sampai full open (100%) dan tekanan sama dengan
tekanan pada main line dan lakukan stabilisasi tekanan selama 15 menit
6. Setting SDV sesuai kebutuhan operasi
7. Setting nilai PSDV-A dan B dengan nilai
i, Set Point SDV-5321 : 18 barg
Set Point SDV-004 : 18 barg
8. Buka valve V-49 & V-45_periahan sampai dengan 100% (full open)
9. Buka valve V-173 perlahan sampai dengan 100% (full open)
10. Tutup valve V-171, V-172 & V-50, V-51
11. Lakukan verifkasi pembacaan pada Flow computer.
12, Pastikan tekanan di downstream setelah PCV sesuai dengan operasi
13. Commissioning selesai
D, EMERGENCY RESPONSE PLAN
Jika terjadi kegagalan Commissioning maka
1. Tutup valve V-48, V-45, V-50, SDV-5321,SDV-004, V-173, V-172, dan V-174
2. Buka valve V-1521C, VS321E, V-63, V-54, V-5321J, V-5321K, V-179, V-O04H, V-
183, V-004C, V-004B dan V-6321FE. NOMOR TELEPHON GAWAT DARURAT
No. | Institusi [No Telp
1 | Pemadam Kebakaran 113/0551-32230
2 | Polisi (0548) 21110
3 | Rumah Sakit (0548) 22111
Bontang, Maret 2017
Ketua Tim Commissioning