LONG TERM CONSTRUCTION
Question #11 Page 265
The following information relates to a flood control project of JJD Construction Co. which was started in
2015 and completed in 2016:
Cost incurred to date: Estimated total cost on completion
As at June 30, 2015 P 9,750,000 As at June 30, 2015 P 19,500,000
As at June 30, 2016 P15,750,000 As at June 30, 2016 P 20,250,000
The project is a 22,500,000 fixed price construction contract and JJD uses the percentage of completion
method of revenue accounting. On June 30, 2016, how much income would JJD report on the project?
a. 250,000
b. 300,000
c. 750,000
d. 900,000
Answer: A
06/30/15 06/30/16
Contract Price 22,500,000 22,500,000
Less: Total estimated Costs 19,500,000 20,250,000
Estimated Gross profit 3,000,000 2,250,000
Multiplied by: Percentage of completion 9750/19500 15750/20250
Recognized gross profit to date 1,500,000 1,750,000
Less: recognized gross profit in prior year - 1,500,000
Recognized gross profit each year 1,500,000 250,000