Period Highlight: 6 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
STANDARD SCOPE OF WORKS
Activities PLAN
START
PLAN
DURATION
ACTUAL
START
ACTUAL
DURATION
PERCENT
COMPLETE
STATUS
Date
6/25 6/26 6/27 6/28 6/29 6/30 7/1 7/2 7/3 7/4 7/5 7/6 7/7 7/8 7/9 7/10 7/11 7/12 7/13 7/14 7/15 7/16 7/17 7/18 7/19 7/20 7/21 7/22 7/23 7/24 7/25 7/26 7/27 7/28 7/29 7/30 7/31 8/1 8/2 8/3 8/4 8/5 8/6 8/7 8/8 8/9 8/10 8/11
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 28 29 30 31 32 28 29 30 31 32 28 29 30 31 32 33
1.0 Drydocking (Send Notice of Drydocking) 1 1 1 1 100% done
2.0 Scraping of bernacle and marine growth 2 2 2 2 100% done
3.0 Presure Jetwashing 2 1 2 1 100% done
4.0 Conduct UTG 3 2 3 2 50%
5.0 Sandblasting 2 2 wait paints
6.0 Crop-out/Re-plate thin plates/Doubler
6.1 Pull-out/return Wheel and Round fender 4 3 4 3 50%
6.2 Forward - repair of base plates ( round fender ) 4 6 4 6 50%
6.3 Aft - repair of base plates ( round fender ), P/S 5 4 5 4 50%
6.4 Repair of box fender 5 6 5 6 50%
6.5
7.0 Painting
8.0 Crop-out and Install Zinc/Aluminum Anodes 2 2
9.0 Propulsion Works
9.1 Pull-out Kurt Nozzle @ STB side 2 7 2 7 25%
9.2 Pull-out Kurt Nozzle @ Port side 6 7 6 7
9.3
10.0 Machine Shop Works
11.0 Turbo Repair and Re-conditioning c/o OR
12.0 Welding Inspection and Survey 2 2
13.0 Megger Test 4 2 4 2 100% done
14.0 Provide Shell Expansion
15.0 Tank cleaning Works
15.1 Tank cleaning prior for hotworks @ portside 4 3 4 2 75%
15.2 Bilge cleaning 6 4 6 4
16.0 Propeller Re-conditioning 3 3 3 3 100% done
17.0 Safety and Others
17.1 Pull-out all Sea Chest Valves & recon 4 5 4 5 50%
17.2 Hydraulic Winch for check-up and repair 6 3 6 3 25%
18.0 Carpentry @ Pilot House 4 6 4 6 25%
19.0 Chain and Anchor Works
19.1 Range down anchor & restow later 4 3 4 3 50%
19.2 Derusting of chian by dropping 1 1
19.3 Calibration of chain 1 1
19.4 Chain Locker Cleaning 2 2
19.5
19.0 Undocking 1 1