7/16/2014
EE 3043 Power Systems III
Power System Protection
by
Dr. Lidula N. Widangama Arachchige
Department of Electrical Engineering
University of Moratuwa, Sri Lanka
Field Visit
Victoria Power Plant breaker and half scheme
1
7/16/2014
Field Visit
Victoria Power Plant - Synchroscope
Field Visit
Victoria Power Plant - Controller
2
7/16/2014
Field Visit
Victoria Power Plant - Generator
Field Visit
Victoria Power Plant - Turbine
3
7/16/2014
Field Visit
Victoria Power Plant Breaker (Single Pole)
Field Visit
Victoria Power Plant Generator SS
4
7/16/2014
Field Visit
Victoria Power Plant Isolator
Field Visit
Victoria Power Plant CVT
10
5
7/16/2014
Field Visit
Victoria Power Plant CT
11
Field Visit
Victoria Power Plant Power-line Carrier Signaling
12
6
7/16/2014
Field Visit
Victoria Power Plant Protection
13
Learning Outcomes
After completing this module the student should be able
to:
demonstrate knowledge of the general requirements of
protective relaying.
select suitable instrument transformers for metering and
protection, optimization of their protection functions.
demonstrate knowledge of relaying principles of electro-
mechanical, static and numeric relays.
design protection schemes using over current, earth fault and
directional relays and to calculate the relay settings.
design appropriate protection schemes for generators and
transformers.
apply different distance relay techniques for transmission line
protection.
14
7
7/16/2014
Reference
Juan M. Gers and Edward J Holms, Protection of Electricity
Distribution Networks, 2nd Edition, IET Power and Energy
Series 47, IEEE, London, UK, 2011, ISBN 0 86341 537 7.
15
Outline
Introduction to power system protection
Necessity for protection
Protection Requirements
Zones of Protection
Primary and backup protection
Breaker Failure Protection
16
8
7/16/2014
Goal of a Power System
Power system is expected to provide electricity at an
acceptable level of,
Reliability
Quality
Safety
Price
17
Objective of Power System Protection
To design, install and maintain the power system to
limit the cumulative faults and to overcome the
possible risk of damage.
18
9
7/16/2014
Necessity for Protection
Faults will occur in power systems despite how well
the system is designed
Lightening
Contact of tree branches
Deterioration of insulators causing flashover
Vandalism
Contact of animals
Majority of faults are transient in nature and can be
cleared with no or short interruptions
19
Faults in Power Systems
Faults are associated with
Rapid growth of currents to very large values
Considerable voltage deviations
Liberation of large amount of heat at the fault
Overheating of healthy lines and equipment
A risk to life/property
20
10
7/16/2014
Functions of the Protection System
Primary function
Fast removal of any element of a power system when it suffers a
short circuit, or when it starts to operate in any abnormal
manner
Permits the rest of the system to remain in service
Limits the possibility of damage to other equipment
Secondary function
Provides an indication of the location and type of fault
Essential elements in a protection system
Relays to detect faults and issue trip signals
Circuit breakers to disconnect the faulty section from rest of
the network
21
Protection Requirements
Availability
Simplicity
Economical
Flexibility
Cost
Reliability
Speed Functional
Selectivity
Sensitivity
It is practically impossible to satisfy all the abovementioned needs
at the same time
Compromise is required to obtain the optimum protection
22
11
7/16/2014
Economical Requirements
Availability
Minimum time for repair and maintenance
Simplicity
Minimum equipment and circuitry
Flexibility
For an easy adaptation to the power system
23
Functional Requirements
Reliability
Neither over nor under reaction (i.e. Should be dependable and secure)
Dependability
Certainty of correct operation
Security
Ability to avoid incorrect operation
Causes for incorrect operation
Incorrect design/setting
Incorrect installation/testing
Deterioration during the service
Rough or burnt contacts, damaged electronic components, open circuited coils,
stuck mechanical parts, etc.
Need regular testing long periods between relay operation 24
12
7/16/2014
Functional Requirements Cont...
Speed
Clear the fault as fast as possible
To ensure power system stability
Loss of synchronism
Clearing before the critical clearing time
To avoid equipment damage due to heat
Energy dissipation (IF2)t
25
Functional Requirements Cont...
Selectivity
Disconnect only the minimum section of the network to isolate
the fault
Maintain supply to unfaulted sections
Methods of introducing selectivity :
Time grading
Operating times of the relays in successive zones are arranged so that
only the relay in faulty section complete the operation
Operating time is proportional to the fault severity
Unit protection
Protections systems that respond to faults in a clearly defined zone
Relatively fast operation
Speed is independent of the fault severity
26
13
7/16/2014
Functional Requirements Cont...
Methods of introducing selectivity cont...
Directional Protection
The relay can determine the direction of power flow
Trips circuit breakers only if the direction of fault current is according
to the relay setting
Very important in proving protection to
Meshed networks
Networks with various generating sources
Parallel elements
27
Functional Requirements Cont...
Sensitivity
Minimum level of operating parameter required to
complete the relay operation
Voltage, current, power, etc.
Electromechanical relays
Sensitivity of the measuring movement
Digital relays
Sensitivity is usually limited by the current/voltage transformer
parameters
28
14
7/16/2014
Zones of Protection
To limit the extent of power system that is disconnected during
a fault, the protection is arranged in zones.
Zone 1
Generators
Transformers
Groups of generator transformers Zone 2
Motors
Busbars
Lines Zone 3
Zone 4
Zone 5 Zone 6 29
Zones of Protection Cont...
Ideally, a protection zone must overlap with the
adjacent zones
30
15
7/16/2014
Primary and Backup Protection
It is essential that any fault is isolated
But failure/unavailability of main protection scheme is
possible
Backup Protection provides the second line of
defense
Unit type protection relays operate only for faults within
the zone (Can only be used as primary protection)
Other relays can detect faults in adjacent zones, and can
be used as backup protection
Whenever possible, every element must be protected by
primary and backup systems
31
Primary Protection
Primary protection must operate every time an
element detects a fault
One primary protection element may cover group of
equipments
One equipment may be protected by a number of primary
protection relays for different types of faults
Usually a unit type protection, and therefore operate
faster
32
16
7/16/2014
Backup Protection
Operate when the primary protection failed to operate
Backup protection usually involve a timedelay before the
operation
Allow time for primary protection to operate
One relay can provide backup protection to several
different pieces of equipment
A primary relay for one equipment may provide backup
protection to several other equipment
A single piece of equipment can have several backup
protection systems
33
Redundancy
Ensure the fault detection and isolation in the event
of component failure
At least two redundant schemes for each zone
Schemes A and B
Two schemes are independent from each other
Measurements from different CTs/VTs
Relays from different manufacturers
Two trip coils in circuit breakers; one operated by Scheme
A and the other operated by Scheme B
Separate DC power supplies/Battery banks
34
17
7/16/2014
Breaker Failure Protection
Detects and isolates the circuit breakers that fails to
open to isolate a fault
Faulted breakers
Very critical protection scheme
Additional actions must be initiated to isolate the
fault
Operation of remote protection
Local protection
35
Breaker Failure Protection Cont...
36
18
7/16/2014
Breaker Failure Protection by Remote Backup
Remote Backup
37
Breaker Failure Protection by Relaying
Breaker Failure Relaying
BFR on breaker [3] detects breaker failure condition
BFR trips a Lockout relay on Bus B
Lockout relay trips breakers [2], [5], and [7]
Lockout relay blocks close of [2], [5], and [7]
Transfer Trip (remote signalling) to breaker [4]
Cancel reclose of [4]
38
19
7/16/2014
Example
39
Answer
40
20