JEPL Toll Plaza Weekly Progress Report

The weekly progress report summarizes the work completed on the Jadcherla Expressways Toll Plaza Project over the past week. Key accomplishments include: completing the basement of the admin building and making progress on the ground floor columns. Box culverts and tunnels on both sides were completed. Paver block manufacturing is in progress, with over 4.3 lakh blocks cast so far meeting strength requirements. Foundation work is ongoing for buildings like the maintenance building, canteen building and wayside amenities. Drain and road work are ongoing. Guard post casting and kerb casting are also in progress. Overall the project is progressing well across multiple work streams.

Uploaded by

vijking
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
179 views19 pages

JEPL Toll Plaza Weekly Progress Report

The weekly progress report summarizes the work completed on the Jadcherla Expressways Toll Plaza Project over the past week. Key accomplishments include: completing the basement of the admin building and making progress on the ground floor columns. Box culverts and tunnels on both sides were completed. Paver block manufacturing is in progress, with over 4.3 lakh blocks cast so far meeting strength requirements. Foundation work is ongoing for buildings like the maintenance building, canteen building and wayside amenities. Drain and road work are ongoing. Guard post casting and kerb casting are also in progress. Overall the project is progressing well across multiple work streams.

Uploaded by

vijking
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

Weekly Progress Report

11

Welcomes You !

Jadcherla
Expressways Toll
Plaza Project
JEPL TOLL PLAZA– Project Progress:-
Progress Photographs: Admin Building Work Progress:-

Admin Building Basement Completed


Ground Floor Column Work in Progress :-

2
Progress Photographs: Box Culvert at Ch:54:080 :-

R.H.S :-Raft Casting Completion L.H.S :- -Raft Casting Completion


JEPL TOLL PLAZA–
Truck Lay Bay Progress Photographs:

blob:file:///95ff32c6-3488-4eab-a399-ac590b45d299

WMM Laying for 2 Lane on Site, for MC50 LHS & RHS:-
Road No. MC 50 ,MC40, MC30, Sub-grade & GSB Top Level Completed.
Total Area:-24000 Sqm. Completed Area For Subase:-17000 Sqm.
JEPL TOLL PLAZA–Drain & Tunnel
Tunnel Progress Photographs: L.H.S Side

Tunnel L.H.S 30m Length Completed.Back Filling in Progress

5
JEPL TOLL PLAZA–Drain & Tunnel
Tunnel Progress Photographs:R.H.S Side

Tunnel Side R.H.S Completed:-

6
Progress Photographs: Canopy Foundation :-
4 Nos Canopy Foundation Completed, Total Foundation-12 Nos.:-
Progress Photographs: Paver Block Manufacturing in
Progress:-

Paver Block Machine Erected at Site & 4 Lakh 30 Thousand pieces are
Casted, Average 10000 thousand casting per day:-
Total -12 Lakh required for Truck Lay bay Area
Grade:- M40
3 days Results :- 27 N/mm2
7 days Result :-32 N/mm2
28 days test Result :-42 N/mm2
Progress Photographs: Traffic & Security Aid Post :-
Traffic & Security Aid Post RCC Completed , PCC Work Completed:-
Progress Photographs: Medical Aid Post :-
Medical Aid Post R.C.C Completed, Soiling Work in Progress :-
Progress Photographs: Maintenance & Canteen building:-
Maintenance Building:- Footing Completed & Plinth Beam in Progress
Canteen Building:-Footing Completed & Plinth Beam in Progress
Progress Photographs: Way Side Amenities :-
Dhaba.:- Plinth Work in Progress, Anchoring for PEB in progress:-
Progress Photographs: Admin Area :-
Septic Tank Work , Brick work in progress:-
Progress Photographs: Electrical Work :-
Transformer Charged & Connected to Toll Plaza:-
Relocation of Existing Transformer in Progress:-
Road Work :-
L.H.S Road Work:-

L.H.S Side :-Subgrade Work in Progress


Cleaning & Grabbing Completed
Road Work :-
R.H.S Road Work:-

R.H.S Side :-Subgrade Completed, GSB Top Completed for 1700 Sqm :-
Guard Post Casting in Progress:-Total Quantity 600
Completed:-498 Casted Till Date, Daily 8 is been Casted

Kerb Casting Work in


Progress:-
JEPL TOLL PLAZA–Drain & Tunnel
Drain Progress Photographs:
Drain Work:-
Completion:- 470m !br0ken!!
Excavation:-560m

18
JEPL TOLL PLAZA– Project Plans and its Review