LAMPIRAN PENAWARAN
PEKERJAAN URUGAN TANAH
PROYEK CO2 PLANT PROJECT - CIKAMPEK
NO ITEM SPECS. UNIT QTY
A Pekerjaan Pesiapan, Prasarana & Penunjang (Preliminaries)
1 Mobilisasi & Demobilisasi ls 1
2 Survey dan Pengukuran ls 1
3 Management dan Administrator Proyek ls 1
4 Keamanan termasuk Koordinasi Aparat & Masyarakat ls 1
5 Kantor / Bedeng sementara ls 1
6 Kebersihan Jalan Lintasan ls 1
B Site Development
Top-soil which includes trees, grass, crops, weeds,
Top-Soil and other similar matter, stripped to a depth of
Stripping 200 mm including disposal, transportation.
1 m2 29,200.00
and
Clearing Including removing root of trees
Use excavated materials
Not more than 200 mm in loose depth for each
2 Soil Filling layer m3 20,440.00
Compaction : 95% of the maximum density
Including compaction
TOTAL
PEMBULATAN
PPN 10%
GRAN TOTAL
Hal. 1
LABOR
MATERIAL Manday Cost
U. PRICE AMOUNT UNIT TOTAL U. PRICE AMOUNT
- - 14.00 14.00 421.92 Rp 12,320,000
Rp 135,882 Rp 2,777,435,294 60 60.00 Rp 2,583 Rp 52,800,000
Hal. 2
CONST. EQUIPMRNT T&C
U. PRICE AMOUNT U. PRICE AMOUNT
Rp 16,500 Rp 481,800,000 Rp 5,500 Rp 160,600,000
Rp 33,000 Rp 674,520,000 Rp 11,000 Rp 224,840,000
Hal. 3
CONST. EQUIPMRNT T&C
U. PRICE AMOUNT U. PRICE AMOUNT
Hal. 4
Total
U. PRICE AMOUNT
Rp 25,000,000.00
Rp 15,000,000.00
Rp 20,000,000.00
Rp 30,000,000.00
Rp 15,000,000.00
Rp 55,000,000.00
Rp 160,000,000.00
Rp 22,422 Rp 654,720,000.00
Rp 182,466 Rp 3,729,595,294.12
Rp 4,384,315,294.12
Rp 4,544,315,294.12
Rp 4,544,315,000.00
Rp 454,431,500.00
Rp 4,998,746,500.00
Hal. 5
Total
U. PRICE AMOUNT
Bekasi, 12 Maret 2018
PT. KALIABANG JAYA PRATAMA
HANDRI WINATA
Direktur Utama
Hal. 6