This document provides a cost estimate for the construction of an Railway Over Bridge (ROB) at Ch. 67/9 Km on the Jagiroad-Morigaon Road in Assam, India. It lists 23 line items with quantities, rates, and amounts for works like land acquisition, shifting of utilities, earthworks, road construction, a reinforced earth wall, box culverts, drainage works, the ROB structure itself, and administrative costs like proof checking, contingencies, quality control, and agency charges. The total estimated project cost is Rs. 458,290,928 or approximately Rs. 458.3 crores.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views2 pages

ROB Estimate (Br. Proper & Approaches Etc.)

This document provides a cost estimate for the construction of an Railway Over Bridge (ROB) at Ch. 67/9 Km on the Jagiroad-Morigaon Road in Assam, India. It lists 23 line items with quantities, rates, and amounts for works like land acquisition, shifting of utilities, earthworks, road construction, a reinforced earth wall, box culverts, drainage works, the ROB structure itself, and administrative costs like proof checking, contingencies, quality control, and agency charges. The total estimated project cost is Rs. 458,290,928 or approximately Rs. 458.3 crores.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Name of Work :- Construction of R.O.B. at Ch. 67/9 Km (Railway) and at Ch. 0.

728 Km on
Jagiroad-Morigaon Road ( New N.H. 715 A)

Sl. No. Item of Works Unit Quantity Rate Amount


1 2 3 4 5 6
1 Land acquisition Bigha 20.175 3000000.00 60,525,000.00

2 Shifting of Electricals Poles & Lines M 1200.00 L.S. 15,000,000.00

3 Shifting of PHE Water Supply Lines M 1200.00 L.S. 5,000,000.00

4 Site Clearance M 1200.00 L.S. 650,000.00

5 Earth Work in Excavation Cum 7200.00 149.00 1,072,800.00

6 Earth Work in Filling in Embankment Cum 67272.00 230.00 15,472,560.00

7 Earth Work in Filling in Sub-grade Cum 11352.00 260.00 2,951,520.00

8 Construction of Granular Sub-Base Cum 4413.42 2100.00 9,268,182.00

9 Construction of Wet Mix Macadam Cum 6398.70 2250.00 14,397,075.00

10 Prime Coat Sqm 23350.00 75.00 1,751,250.00

11 Tack Coat Sqm 68400.00 15.00 1,026,000.00

12 BM Cum 1441.55 8500.00 12,253,175.00

13 DBM Cum 1296.24 12000.00 15,554,880.00

14 B.C. Cum 930.16 14500.00 13,487,320.00

15 Reinforced Earth Wall (RE Wall)


i)Precast Concrete Facia Panel M 35 Sqm 8712.00 7392.00 64,399,104.00
ii)P.C.C. Strip level footing Rm 1584.00 285.00 451,440.00
iii)600 mm Drainage Bay Cum 106.92 1089.00 116,436.00

16 Construction of C.D. ( 2 nos. of 2x2 Box Rm 52.00 200000.00 10,400,000.00


Culv.)

17 Construction of R.C.C Covered Drain Rm 2400.00 25000.00 60,000,000.00

18 Construction of R.O.B. ( Proper) Rm 89.651 784100.00 70,295,349.00

19 Road Safety Works (for Bridge and L.S. 6,000,000.00


Approaches)
(A) Total = 380,072,091.00
Sl. No. Item of Works Unit Quantity Rate Amount
1 2 3 4 5 6
Contd.

B.F. = Rs. 380,072,091.00


20 Proof Checking by IIT, Guwahati and
Departmental Charges 7.5% on (A) 28,505,407.00

21 Contingency 2.8 % on (A) 10,642,019.00


( B) Total = 390,714,110.00

22 Quality Control 1 % on (B) 3,907,141.00

23 Agency Charge 9 % on (B) 35,164,270.00


Total Project Cost = Rs. 458,290,928.00

Say Rs. 458,300,000.00

(Rupees Forty five crores eighty three lakhs only)