Important Definitions Total System Black Out: The Black Start Procedures Should Contain The Following Minimum Details
Important Definitions Total System Black Out: The Black Start Procedures Should Contain The Following Minimum Details
The black start procedures should contain the following minimum details.
1. Generation Securing
2. Generation build-up
· Survival and Start-up Power of Power Plant(s).
· Power Station(s) with Black-start facility.
3. Build-up of islands
4. List of black start facilities, inter-state/regional ties, synchronizing points and essential
loads to be restored on priority
5. Detailed State/Utility-wise Restoration plans
1. In systems with a fair dispersal of Generating stations with black start facilities, those generating
stations where black start facilities are available, should be started up and islands formed around
these generating stations by connecting essential loads. These islands are then interconnected at
predefined locations where synchronizing facilities are available. The speed of restoration enhances
with increase in number of black start facilities and their dispersal. Gujarat, Chhattisgarh and M.P
have considerable number of black start facilities while Maharashtra suffers from lack of adequate
number of black start generators. It is required to carefully monitor the operation of the island (re-
integration with rest of the grid) due to small stiffness in islands. One engineer shall be specifically
assigned to monitor one island.
2. While adding loads, care should be taken to ensure step by step addition keeping in view
load characteristics, ie., variation of load with respect to voltage and frequency and stiffness of
island. During cold load pick up sudden starting of motor loads or power plant auxiliaries like BFP, PA
fan etc., can cause voltage dips due to drawal of high starting currents. Essential loads can be
restarted in steps smaller than 5 MW. It is preferable to restore rotating type loads which co~tributes
to inertia of the island. In any case, load pick up should not cause frequency excursions greater than
0.5 Hz in the island.
3. The second approach could be followed in case self start facilities are available at only a
few power stations or the stqrt up power has to be imported from neighbouring regions at one0or
two points. In this approach, the start up power required to be extended to all the generating
stations on priority basis while restoring few loads and transformers for voltage control. The start up
power available from neighbouring regions at various interconnections have to be seriously explored
since considerable assistance can be availed and the restored system is connected to stable external
systems. The procedures have to be laid down for quickly harnessing these facilities.
The restoration through this approach could be delayed due to problems in charging the lines, high
voltage, lack of synchronising equipment at certain substations etc. and may involve system
disturbances during restoration.
OPERATIONAL GUIDELINES.
1. Each SLDC will coordinate synchronisation of units and transmission lines in its system in
consultation with WRLDC. For ISGS power stations , WRLDC will be coordinating for their
synchronisation. WRLDC will coordinate interstate/ inter-regional startup power availability and also
inter-state/inter-regionql synchronisation of the system.
2. Minimum 25 MW power flow from West to North will be maintained on HVDC back to
back link at Vindhyachal during normal operating condition.
4. Transmission corridors used for startup power should be isolated from any
damaged/faulty equipment and are of minimum length and minimum voltage level to reduce line
charging.
5. The constituent receiving assistance during restoration process should restrict to the
agreed quantum only since this may have an adverse effect on healthy system0rendering the
assistance.
GENERAL GUIDELINES
While each disturbance would be different and may require a different plan, nevertheless it would be
useful to formulate general guidelines for the benefit of the load despatchers. These may be
described as0below:
i. The operators at generating stations and substations should have the knowledge of pre-planned
synchronising locations and synchronising procedures. Synchronising should be done preferably at
generating stations.
ii. Switching procedures should be clearly laid down and periodically reviewed.
iii. The part systems should be reintegrated only after adequate stabilization.
iv. The transformer taps should be checked for desired settings to minimise voltage difference.
v. The substation operators and load despatchers sxould make a check of the capacitor banks and
reactors in service and accordingly to carry out the switching operations for voltage control.
vi. Energising long high voltage lines and cables should be avoided until enough generating
capacity is available.
vii. Provision of islanding schemes area-wise, power station-wise and unit-wise would enhance
the ability to restore faster. These should be fully exploited.
viii. Some of the generating units might have been saved due to successful islanding. Stabilization
of such online generation is of top most priority.
ix. Provision of start up power to nuclear plants should be given priority as poisoning of the
reactors would delay restoration of nuclear units.
x. In case of failure of main communication channels, guidelines for decision making should be
given to all the major substations and generating stations.
xi. Devising islands for power stations wherever small units could help in faster restoration of the
grid are available. One small unit at these power stations can be islanded with radial loads and/or
house load.
Survival power can be defined as the power needed for avoiding the damage to the equipment in
case of supply failure. This power is required for
The survival power required by 120 MW units is of the order of 250-350 kW while the requirement
of 210 MW units is of the order of 350-500 KW. As a general rule, the survival power requirement
would be around 0.25-0.30% of the unit capacity. Nuclear power plants should be supplied with
survival power on priority basis.
The start-up power is the power required for the auxiliaries while the generating unit is restored.
The requirement of start-up power by various units is as follows:-
Objective
Strategies
Concerns
Objective
Strategies
Concerns
Ø Size of load pick up depends upon the rate of response of prime movers
Ø Load pick up in large increments led to collapse of the restored systems
Twice in Gujarat on 9.12.95
Twice in Maharashtra on 9.12.95
Once in MP on 9.12.95
3 LOAD AND GENERATION CO- ORDINATION PRIORITIES
Restart Stage
Ø Priority to restore power supply to generating stations and load dispatch centers.
Ø Priority to supply start up power to hydro and gas units
Ø Priority for providing backup/survival/startup power to nuclear power stations
Ø Several load and generation islands formed
Ø Black starting of small hydro or gas units
Ø In each island, the objective is to supply station auxiliary power and start up power
Ø The number of islands limited by sources of black start units
Ø Each island should preferably be monitored by one load despatcher till reintegration.
Re-integration stage
Ø Location of the fault and extent of collapse of the system should be ascertained before
restoration
Ø Ensure communication links between control centers, power plants and sub-stations
Communications
¨ All important substations only to be kept in touch with and links with unimportant substations
to0be cut off to avoid draining of batteries.
¨ All communication channels required for restoration process shall be used for operatyonal
communication only till grid normalcy is restored (IEGC 6.8.e)
7. ENERGY STORAGE
Batteries
Battery chargers
UPS
Diesel sets
Could affect
9 Survival Power
Ensuring availability of back up power supplies such as batteries, battery chargers, D.G sets to avoid
effect on non operation of circuit breakers, communication systems etc., which can cause delay in
restoration.
Training and necessary documentation may be provided to Load Despatchers by respective LDCs.
11 Exchange of Information
Exchange of information among SLDCs and between RLDC and SLDCs is essential for proper co-
ordination.
1 Power flow
§ Multiple islands
§ Study voltage problems
§ Generator excitation limits
§ Transformer taps
2 Dynamic stability
3 EMTP
v Restart and supply start up power first to hydro and gas stations
v Co-ordination of power plant start up with load pick up to bring generators to their stable
minimum generation levels
v Reintegration of sub-systems
2. Equipment limitations
Circuit breakers
v Remove all sources of reactive power and switch off capacitor banks
v Run generators at maximum possible reactive power output to allow margin to adjust for
large charging reactive power during line switching
v To be controlled to 2.5 p.u for 400kV and 1.9 p.u for 800kV and 2.3 p.u for others
v Usually of fast front, low energy or slow front, high energy transients.
v Keep steady state voltage below 1.2 p.u. Keep generator terminal voltage around 0.8 p.u
5. Harmonic Resonance