Energypac Fashions Ltd.
Ext.Project,Monipur,Gazipur
Work schedule
S/L Task name Duration Start Completed
Upvc Frame delivery at site for Single
1 14 days 15.04.18 28.04.18
glass
Upvc FrameInstallation at site for Single
2 06.05.18
glass
Single Glass delivery at site
3 14.05.18 15.05.18
4 Single Glass Fitting at site 15.05.18 18.05.18
Selicone with additional necessary
5 18.05.18 20.05.18
support, finishing all completed
Upvc Frame delivery at site for double
6 glass
Upvc Frame Installation at site for
7 double glass
Double Glass panel delivery at site
8 15.06.18 20.06.18
Double Glass panel Fitting at site
9 16.06.18 28.06.18
Selicone with additional necessary
10 25.06.18 28.06.18
support, finishing all completed
Door supply ,fitting & fixing all
11 25.06.18 28.06.18
completed
Energypac Fashions Ltd.
Ext.Project,Monipur,Gazipur
Updated date: 23.05.18
Work schedule
Status Remarks
uPVC Window Frame
fabrication started on
15.04.18. All uPVC frame 100% Complete
fabrication completed on
28.04.18
There are eight window gaps.
Only 1 gap remaining. Our team
went today to complete work
1pc window gap frame today but installation ceased due
installation completed to bad weather. Egr. Liton is
advised. Installation will
complete on next favorable
weather day.
Glass purchased today
06.05.18 at Tk. 35/sft
premium price due to
scarcity in market for 6mm
China Clear glass. Glass
will be cut and sent to 100% Complete
glass tempering factory 3D
Architectural Industries Ltd
on 09.05.18. We will
receive tempered glass
delivery on 13.05.18
There are eight window gaps.
Glass Installation will Only 1 gap remaining. Our team
complete in 4 working went today to complete work
days if allowed to work today but installation ceased due
continuosly. Per day we to bad weather. Egr. Liton is
can install upto 40pc glass advised. Installation will
units. complete on next favorable
weather day.
100% complete for 7 window
gaps out of 8 window gaps
100% Frame ready for delivery at
Frames ready. Delivery Arterior Windows Ltd
upon advice of Energypac warehouse. Waiting for Egr. Liton
site engineer advise to deliver to Energypac
after he manages storage space
suggested to start
installation after Insulating uPVC Double Glass frame
Glass Unit (IGU) ready. installation completion
Need 12 working days to dependent on weather and
complete all Double Energypac's work schedule
Glazed window frames
Low-E glass delivery to
temperign house from Euro
Bangla. Low-E Tempered Glass
and non-tempered clear glass
We paid Euro Bangla for qty delivery to Arterior Windows
Low-E Glass. We will Ltd expected on 31.05.18.
receive delivery on Double glazing process to
14.05.18 after their complete by 03.06.18. Gas
consignment reaches charge to commence from
Bangladesh. Tentative 07.06.18 in prescence of Egr.
Double Glass delivery on Liton after insulating glass glue
15.06.18 sealant dries in 4 days from
03.06.18. So insulating glass unit
delivery to Energypac firm from
10.06.18 owards
Double Glass installation Double Glass installation
25pc/day because of completion dependent on
heavy weight of glass weather and Energypac's work
units. schedule