Work Schedule For UPVC Glass Works 23 05 18

The document outlines a work schedule for Energypac Fashions Ltd. for an extension project in Monipur, Gazipur. It details tasks, durations, start and end dates for delivering and installing single pane glass and double pane insulated glass units. Key dates include completing single glass installation by May 18th and anticipating delivery of double pane glass units on June 15th for installation through the end of the month. The status section notes that single glass installation is 100% complete except for one remaining window, and double pane frames will be ready upon advice from the site engineer.

Uploaded by

asmjewel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
113 views4 pages

Work Schedule For UPVC Glass Works 23 05 18

The document outlines a work schedule for Energypac Fashions Ltd. for an extension project in Monipur, Gazipur. It details tasks, durations, start and end dates for delivering and installing single pane glass and double pane insulated glass units. Key dates include completing single glass installation by May 18th and anticipating delivery of double pane glass units on June 15th for installation through the end of the month. The status section notes that single glass installation is 100% complete except for one remaining window, and double pane frames will be ready upon advice from the site engineer.

Uploaded by

asmjewel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Energypac Fashions Ltd.

Ext.Project,Monipur,Gazipur

Work schedule
S/L Task name Duration Start Completed

Upvc Frame delivery at site for Single


1 14 days 15.04.18 28.04.18
glass

Upvc FrameInstallation at site for Single


2 06.05.18
glass

Single Glass delivery at site

3 14.05.18 15.05.18

4 Single Glass Fitting at site 15.05.18 18.05.18

Selicone with additional necessary


5 18.05.18 20.05.18
support, finishing all completed
Upvc Frame delivery at site for double
6 glass

Upvc Frame Installation at site for


7 double glass

Double Glass panel delivery at site

8 15.06.18 20.06.18

Double Glass panel Fitting at site

9 16.06.18 28.06.18

Selicone with additional necessary


10 25.06.18 28.06.18
support, finishing all completed
Door supply ,fitting & fixing all
11 25.06.18 28.06.18
completed
Energypac Fashions Ltd.
Ext.Project,Monipur,Gazipur
Updated date: 23.05.18
Work schedule
Status Remarks

uPVC Window Frame


fabrication started on
15.04.18. All uPVC frame 100% Complete
fabrication completed on
28.04.18

There are eight window gaps.


Only 1 gap remaining. Our team
went today to complete work
1pc window gap frame today but installation ceased due
installation completed to bad weather. Egr. Liton is
advised. Installation will
complete on next favorable
weather day.

Glass purchased today


06.05.18 at Tk. 35/sft
premium price due to
scarcity in market for 6mm
China Clear glass. Glass
will be cut and sent to 100% Complete
glass tempering factory 3D
Architectural Industries Ltd
on 09.05.18. We will
receive tempered glass
delivery on 13.05.18

There are eight window gaps.


Glass Installation will Only 1 gap remaining. Our team
complete in 4 working went today to complete work
days if allowed to work today but installation ceased due
continuosly. Per day we to bad weather. Egr. Liton is
can install upto 40pc glass advised. Installation will
units. complete on next favorable
weather day.

100% complete for 7 window


gaps out of 8 window gaps
100% Frame ready for delivery at
Frames ready. Delivery Arterior Windows Ltd
upon advice of Energypac warehouse. Waiting for Egr. Liton
site engineer advise to deliver to Energypac
after he manages storage space

suggested to start
installation after Insulating uPVC Double Glass frame
Glass Unit (IGU) ready. installation completion
Need 12 working days to dependent on weather and
complete all Double Energypac's work schedule
Glazed window frames

Low-E glass delivery to


temperign house from Euro
Bangla. Low-E Tempered Glass
and non-tempered clear glass
We paid Euro Bangla for qty delivery to Arterior Windows
Low-E Glass. We will Ltd expected on 31.05.18.
receive delivery on Double glazing process to
14.05.18 after their complete by 03.06.18. Gas
consignment reaches charge to commence from
Bangladesh. Tentative 07.06.18 in prescence of Egr.
Double Glass delivery on Liton after insulating glass glue
15.06.18 sealant dries in 4 days from
03.06.18. So insulating glass unit
delivery to Energypac firm from
10.06.18 owards

Double Glass installation Double Glass installation


25pc/day because of completion dependent on
heavy weight of glass weather and Energypac's work
units. schedule