100% found this document useful (1 vote)
281 views78 pages

s2 07 Geotech Complete

This document summarizes geotechnical and seismic investigations and assessments for the Snowy 2.0 project. It describes site conditions, rock mass properties, and predicted ground behaviors along different project components. It also discusses seismic hazards and risks. Further investigations are recommended prior to final investment decision.

Uploaded by

Bar Avait
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
281 views78 pages

s2 07 Geotech Complete

This document summarizes geotechnical and seismic investigations and assessments for the Snowy 2.0 project. It describes site conditions, rock mass properties, and predicted ground behaviors along different project components. It also discusses seismic hazards and risks. Further investigations are recommended prior to final investment decision.

Uploaded by

Bar Avait
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 78

 

 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

Contents 
 

1   Summary  4 

2   Scope   and   exclusions  5 

3   Activities   undertaken  5 

3.1   Geotechnical   investigation  5 

3.1.1   Overview  5 

3.1.2   Rationale   of   investigations  7 

3.1.3   Drill   hole   naming   convention  7 

3.1.4   Tantangara   intake   area  7 

3.1.5   Nungar   Creek   area  8 

3.1.6   Tunnel   alignment   on   Long   Plain  9 

3.1.7   Long   Plain   Fault   (Plateau   option   power   station   complex)  9 

3.1.8   Yarrangobilly   River   Tolbar   Ridge   alignment  13 

3.1.9   Talbingo   Intake  13 

3.1.10   Access   tunnel   (Emergency   Cable   Ventilation   Tunnel   (EVCT))  13 

3.2   Ground   characterisation  14 

3.2.1   Soil   materials  14 

3.2.2   Engineering   geology   of   the   rock   materials  15 

3.3   Geological   model  20 

3.3.1   General  20 

3.3.2   Assumptions  20 

3.3.3   Summary   of   site   conditions  20 

3.3.4   Modelling   issues  22 

3.4   Rock   mass   design   parameters  23 

3.4.1   Approach   to   assessment   of   rock   mass   design   parameters  23 

3.4.2   Rock   mass   characterisation  23 

3.4.3   Rock   mass   models  24 

3.4.4   Assumptions  27 

3.7   Geotechnical   description   for   Project   components  28 

3.7.1   General  28 

3.7.2   Intakes  30 

3.7.3   Headrace   tunnel  31 

 
©   Snowy   Hydro   Limited   2017  Page   2  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.7.4   Headrace   surge   shaft   and   gate   chamber  33 

3.7.5   Pressure   shafts  33 

3.7.6   Cavern   complex  34 

3.7.7   Tailrace   tunnel  36 

3.7.8   Access   tunnels   to   the   cavern   complex  36 

3.8   Seismicity  40 

3.8.1   Seismo­tectonics   of   southeastern   Australia  40 

3.8.2   Seismic   hazard   classification  41 

3.8.3   Potential   for   active   faults  41 

3.8.4   Maximum   credible   earthquake  43 

3.8.5   Induced   seismicity  43 

3.8.6   Seismicity   monitoring  43 

3.9   Ground   characterisation   ­  results  43 

3.10   Rock   mass   characteristics   ­  predicted  47 

4   Underground   geotechnical   investigation  49 

5   Risks   and   opportunities  54 

6   Supporting   documents   and   appendices  55 

7   Further   work   required   prior   to   FID  56 

8   Definitions   and   Abbreviations  56 

9   Bibliography  56 

 
Tables 
 

Table   1:   Drill   hole   naming   convention 
Table   2:   Geotechnical   investigation   at   the   time   of   reporting 
Table   3:   Geotechnical   soil   characteristics   assumed   from   field   mapping   and   literature  
Table   4:   SMHEA   rock   mass   classification   and   support   practice 
Table   5:   Brief   description   and   schematic   presentation   of   tunnel   behaviour   types 
Table   6:   Tunnel   behaviour   chart   for   rock   masses 
Table   7:   Summary   of   main   rock   units   in   geological   model   with   respect   to   their   position   along   Project 
alignment. 
Table   8:   Geotechnical   characteristics   of   likely   rock   formations   along   the   Ravine   option   alignment 
Table   9:   Geotechnical   conditions   along   the   Plateau   option   alignment 
Table   10:   Comparison   of   predicted   geotechnical   conditions   for   alternative   power   cavern   locations 
Table   11:    Comparison   table   of   previous   underground   excavations   within   Snowy   Hydro   and   the   Project 
Table   12:   Supporting   documents   and   appendices 
 

 
©   Snowy   Hydro   Limited   2017  Page   3  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

Figures 
 
Figure   1:   Drill   hole   locations   in   relation   to   Ravine   option 
Figure   2:   Example   drill   core   from   Tantangara   Intake   area 
Figure   3:   Example   drill   core   from   location   of   power   station   complex   in   Plateau   option 
Figure   4:   Example   drill   core   from   location   of   HRT   in   Ravine   option 
Figure   5:   Summary   of   the   geotechnical   characteristics   down   hole   of   BH4101 
Figure   6:   Geomorphological   features   of   Project   area 
Figure   7:   Section   A­A'   (from   Figure   6)   indicating   an   interpreted   extension   of   the   Yarrangobilly 
Limestone   towards   the   west 
Figure   8:   Geological   Strength   Index   chart 
Figure   9:   GSI   for   heterogeneous   rock   masses   such   as   flysch  
Figure   10:   General   arrangement   of   the   power   station   complex   (relevant   to   both   options) 
Figure   11:   Power   waterway   inferred   geological   long   section 
Figure   12:   Photo   of   the   Talbingo   Intake   location 
Figure   13:   General   arrangement   of   the   power   station   cavern   complex   in   detail,   relevant   to   both 
options 
Figure   14:   Comparison   of   predicted   geotechnical   conditions   for   alternative   power   cavern   locations 
Figure   15:   Access   road   locations 
Figure   16:   Seismic   hazard   Classification   Map 
Figure   17:   Distribution   of   earthquakes   and   mapped   faults   near   the   Project   location 
Figure   18:   Summary   block   diagrams   for   Kellys   Plain   Volcanics   and   Tantangara   Formation 
Figure   19:   Summary   block   diagrams   for   Boggy   Plain   Fault   and   Gooandra   Volcanics   (east   side) 
Figure   20:   Summary   block   diagrams   for   Gooandra   Volcanics   (west   side)   and   Long   Plain   Fault 
Figure   21:   Summary   block   diagrams   of   Ravine   Beds   (proximal   and   distal   to   Long   Plain   Fault) 
Figure   22:   Geology   and   anticipated   ground   conditions   starting   at   Tantangara   Intake   (left   side   of   dwg) 
for   the   Ravine   option 
Figure   23:   Geology   and   anticipated   ground   conditions   along   HRT   of   Ravine   option 
Figure   24:   Geology   and   anticipated   ground   conditions   at   power   station   complex   location   for   Ravine 
option 
Figure   25:   Geology   and   anticipated   ground   conditions   for   TRT   of   Ravine   option 
Figure   26:   Geology   and   anticipated   ground   conditions   for   MAT   of   Ravine   option 
Figure   27:   Geology   and   anticipated   ground   conditions   for   ECVT   of   Ravine   option 
Figure   28:   Layout   of   the   Dinorwic   power   station   complex   with   the   Machine   Hall   trial   enlargement 
shown   (item   3) 
Figure   29:   Dinorwic   power   station   complex   ­  Machine   Hall   trial   enlargement   shown   (item   3) 
Figure   30:   Geology   and   layout   of   Tumut   2  Site   including   location   of   exploratory   underground   tunnel 
and   associated   diamond   drill   holes 
Figure   31:   Exploratory   Tunnel   Portal   for   Tumut   2  Project 
Figure   32:   Sinking   of   Exploratory   Shaft   for   Tumut   2  Project 
Figure   33:   Schematic   of   potential   underground   geotechnical   investigations 
 

 
©   Snowy   Hydro   Limited   2017  Page   4  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
1   Summary 

This chapter describes the Project’s predicted geotechnical and seismic conditions, the 
purpose and scope of the proposed Geotechnical Investigation Program (GIP), and how 
potential underground geotechnical investigations (UGIP) could refine the design of the 
power station complex. 
This   chapter   describes   the   Project’s   predicted   geotechnical   and   seismic   conditions.   The   existing   GIP 
is   outlined   and   the   chapter   describes   how   it   was   developed   to   validate   or   modify   the   geotechnical 
predictions   and   thereby   reduce   the   overall   project   risks.   The   chapter   describes   how   potential 
underground   geotechnical   investigations   could   be   utilised   to   finalise   refinement   of   the   power   station 
complex   design. 

As   described   in  C
  hapter   Nine   ­  Facilities,  i nfrastructure   for   this   Project   is   predominantly   underground. 
Therefore   the   design   and   construction   of   the   Project   is   linked   to   the   rock   geotechnical   properties   at 
various   depths   down   to   1,100m   below   surface   for   the   proposed   excavations.  

Presently,   the   underground   conditions   for   depths   ranging   as   deep   as   1,000m   are   predicted   from   the 
surface   mapping   and   regional   geology   as   outlined   in  C   hapter   Six   ­  Geology   and   terrain   of   this   report. 
Given   the   geology   is   complex,   this   level   of   information   is   clearly   not   sufficient   for   final   design   and 
optimisation   of   the   Project.   As   a  result,   early   in   the   Study,   a  GIP   was   initiated   to   provide   confirmation 
of   underground   conditions   through   a  combination   of   drilling,   rock   testing,   and   monitoring   of   rock   and 
water   properties.  

This   chapter   describes   the   ongoing   GIP   and   preliminary   results   along   with   the   progress   of   the 
remaining   portions   scheduled   for   completion   prior   to   Final   Investment   Decision   (F   ID ).   The 
geotechnical   prediction   and   seismic   interpretation   of   the   Project   are   summarised   based   on   the 
preliminary   GIP   results   along   with   available   geologic   and   hydrologic   information   (see  C   hapter   Six ).   

2   Scope   and   exclusions 

This   chapter   describes   the   GIP   and   initial   results   along   with   the   progress   of   the   remaining   portions 
scheduled   for   completion   prior   to   FID.   Based   on   preliminary   results   of   the   GIP   along   with   information 
from  C  hapter   Six,   the   geotechnical   and   seismic   preliminary   assessment   of   the   Project   Area   (see 
definition   below)   are   presented   in   this   chapter. 

In   addition,   the   potential   expansion   of   the   GIP   to   include   underground   investigations   is   outlined   in   an 
UGIP.   Based   on   selection   of   a  preferred   cavern   location   from   results   of   surface   GIP   results   in   the 
coming   months,   the   final   stage   of   the   GIP   would   be   developed   based   on   Project   needs.   This   could 
include   an   exploratory   tunnel   and   or   shaft   from   which   detailed   underground   drilling   and   or   trial 
excavations   could   be   completed.    Results   from   this   potential   underground   program   would   be   used   to 
finalise   information   critical   to   the   detailed   engineering   of   the   power   station   complex. 

3   Activities   undertaken 

3.1   Geotechnical   investigation 
3.1.1   Overview 
The   design   of   the   Project   is   based   on   a  combination   of   hydromechanical   requirements   and   the 
underground   geotechnical   conditions   in   which   tunnels   and   chambers   are   proposed   to   be   constructed. 
At   present   the   underground   conditions   are   predicted   from   the   surface   mapping   and   regional   geology 
as   outlined   in  C
  hapter   Six   of   this   Report.   This   level   of   information   is   not   sufficient   for   final   design   and 
optimisation   of   the   Project.   The   GIP   has   been   developed   to   provide   the   confirmation   of   underground 
conditions   through   a  combination   of   drilling,   rock   testing,   and   monitoring   of   rock   and   water   properties.  

The   development   and   implementation   of   the   GIP   has   the   following   objectives: 

 
©   Snowy   Hydro   Limited   2017  Page   5  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
1. Provide   sufficient   detailed   geotechnical   information   for   the   preparation   of   representative 
geological   and   geotechnical   models   for   the   development   of   the   design; 
2. Identify   key   geotechnical   design   issues   /  implications   along   the   alignment   and   implications   for 
the   Project   along   with   sufficient   information   to   enable   appropriate   design   and   construction; 
3. Based   on   the   above   objectives,   undertake   a  detailed   geotechnical   study   that   includes   the 
following   activities: 
a. Physical   investigations,   materials   testing   and   data   collation; 
b. Analysis,   interpretation   and   commentary   on   all   aspects   of   the   investigations;   and 
c. Development   of   representative   geological   and   geotechnical   models   for   the   entire 
project. 
4. Provide   sufficient   detailed   hydrogeological   and   geothermal   information   to   assist   in   the   design. 

The   GIP   is   primarily   focused   on   the   information   supporting   design   and   construction   of   major   Project 
components   such   as   significant   anticipated   geological   and   geotechnical   features,   surge   and   pressure 
shafts,   cavern   for   power   station   and   associated   underground   openings,   significant   river   crossings   and 
tunnel   intake   and   outtake   sites. 

As   of   the   date   of   the   Study,   the   GIP   is   a  live   document   with   ongoing   updates   as   the   investigations 
progress.   The   information   gathered   during   the   site   investigations   is   integrated   with   historical 
information   and   utilised   by   the   design   team   to   refine   the   remaining   drill   hole   locations   and   testing 
regime.  

A   summary   of   the   GIP   scope   of   work   as   at   the   date   of   the   Report   includes: 

1. Procurement   of   contractors   and   resources; 
2. Implementation   of   a  Construction   Environmental   Management   Plan   (C   EMP ); 
3. Implementation   of   a  Safety   Management   Plan   (S   MP ); 
4. Implementation   of   the   GIP; 
5. Project   and   site­based   management   of   investigation; 
6. Drill   holes   varying   in   lengths   between   55m   and   approximately   1,200m   below   ground   surface; 
7. Installation   of   vibrating   wire   piezometers   (V   WPs ); 
8. Installation   of   open   standpipes   with   pressure   and   temperature   loggers; 
9. Water   pressure   /  packer   tests   to   assess   rock   mass   permeability; 
10. Geophysical   investigations   including   marine   continuous   seismic   reflection   survey,   land­based 
seismic   refraction   survey,   and   land­based   electrical   resistivity   tomography   survey; 
11. Downhole   survey   tooling   including   High   Resolution   Acoustic   Televiewer   (H   RATV ),   drill   hole 
verticality   survey,   downhole   temperature   logging   and   downhole   sonic   profiling; 
12. In   situ   stress   testing   of   the   rock   mass   at   five   locations; 
13. Geotechnical   and   environmental   laboratory   testing; 
14. Coordinate   survey   of   completed   investigation   locations; 
15. Transport   and   storage   of   soil   samples,   rock   core   and   water   samples,   and 
16. Production   of   a  Geotechnical   Data   Report   (G   DR ). 

A   program   of   geotechnical   and   environmental   laboratory   testing   of   associated   soils   and   rock   is 
progressing   concurrently   as   part   of   the   GIP. 

The   location   of   the   drill   holes   are   shown   in   Figure   1  below.  

 
©   Snowy   Hydro   Limited   2017  Page   6  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

Figure   1:   Drill   hole   locations   in   relation   to   Ravine   option1 

Details   of   the   drill   holes   regarding   depths,   drilling   inclination,   orientation   and   testing   regime   are 
outlined   in   the   following   sections. 

3.1.2   Rationale   of   investigations 
The   most   appropriate   information­gathering   methods   include   surface   core   drilling,   surface   geophysical 
and   laboratory   testing   investigations.   The   background   for   selecting   the   various   investigative 
techniques   is   as   follows: 

1. Drill   hole   drilling   ­  to   obtain   information   (rock   core   samples)   at   proposed   tunnel   and 
underground   structure   elevations   and   to   facilitate   downhole/in   situ   stress   testing   of   rock   mass 
conditions; 
2. In   situ   stress   testing   ­  to   determine   magnitude   and   direction   of   principal   rock   stresses   e.g. 
(over­coring   technique)   expected   at   depth   for   critical   infrastructure   areas; 
3. Water   pressure   /  packer   tests   ­  to   assess   the   permeability   of   the   rock   mass; 
4. Acoustic   teleview   imaging   ­  the   HRATV   provides   in   situ   imaging   of   the   structure   of   the   rock 
mass   including   defect   type   and   defect   orientations; 
5. Temperature   logging   ­  facilitates   ongoing   studies   into   the   potential   impacts   of   the   Project   on 
thermal   groundwater   gradients   and   conditions; 
6. Geophysical   surveys   ­  provide   information   on   depth   of   weathering   and   rock   structure; 
7. Verticality   surveys   ­  provide   an   accurate   assessment   of   the   final   depth   and   position   of   the 
drill   holes   drilled   and   will   be   used   on   holes   greater   than   200m   target   depth; 
8. Laboratory   testing  ­    determines   engineering   properties   of   soil   and   rock   that   will   be   used   in 
design;   and 
9. Groundwater   monitoring   devices  ­    are   required   to   establish   a  regional   groundwater   model 
(elevations   and   pressures)   to   determine   design   solutions   for   underground   structures   and   to 
assess   the   potential   impacts   of   the   scheme   on   the   regional   groundwater   system. 
3.1.3   Drill   hole   naming   convention 
A   scope   of   drilling   investigations   has   been   developed   to   target   individual   elements   of   the   proposed 
scheme.   A  drill   hole   naming   convention   that   corresponds   to   each   key   element   of   the   scheme   was 
adopted   for   the   GIP   (see   Table   1). 
 
 
 
 
 

1
  SMEC   Dwg   25,   Borehole   Location   Plan,   Date   22/11/2017. 

 
©   Snowy   Hydro   Limited   2017  Page   7  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

Series   (Drill   hole)  Zone 
1000  Tantangara   intake   area 
2000  Access   shaft   and   Nungar   Creek 
3000  Tunnel   alignment   on   Long   Plain  
4000  Long   Plain   Fault   and   Plateau   option   power   station   complex 
5000  Surge   /  pressure   shaft   /  Ravine   option   power   station   complex 
6000  Yarrangobilly   River   /  Tolbar   Ridge   alignment 
7000  Talbingo   outlet   /  intake 
8000  Emergency   Cable   Ventilation   Tunnel 
Table   1:   Drill   hole   naming   convention 

The   detail   of   each   zone   of   investigation   and   rationale   of   investigative   technique   selection   is   described 
below. 
3.1.4   Tantangara   intake   area 
Drill   holes   BH1114   to   BH1117   have   been   completed   within   and   on   the   shoreline   of   Tantangara 
Reservoir   targeting   the   Kellys   Plain   Volcanics   at   the   proposed   intake   area.   All   drill   holes   have   been 
drilled   vertically   with   depths   varying   from   30.3   to   93.1m.   seismic   refraction   surveys   are   planned   in   the 
GIP   in   land­based   holes   to   obtain   weathering   profile   along   with   intact   soil/rock   velocity   structure. 
Acoustic   televiewing   and   permeability   testing   were   also   completed   on   the   land­based   holes. 

The   ground   at   this   location   has   been   described   in   drill   hole   logs   as   porphyritic   dacite:   dark 
blueish/greenish   grey   with   white,   green,   grey   phenocrysts   (larger   crystals   of   quartz   and   feldspar).  
Weathering   of   the   dacite   is   shallow   with   fresh   rock   encountered   at   approximately   3m   below   ground 
level   (B
  GL )  at   BH1115   (Intake   Pit   location).   An   example   of   the   core   is   shown   in   Figure   2  below. 
Please   refer   to   the   Engineering   Geology   Assessment   Report   (E   GAR )  for   additional   details.2 

 
3
Figure   2:   Example   drill   core   from   Tantangara   Intake   area  

Preliminary   rock   strength   varies   from: 

1. Extremely   low   to   very   low   strength   when   the   rock   appeared   extremely   to   highly   weathered; 
2. Low   to   medium   strength   when   moderately   weathered;   and 
3. High   to   very   high   strength   when   the   rock   is   slightly   weathered   or   fresh. 

Chloritic   alteration   was   observed   in   fresh   rock,   changing   the   colour   of   the   rock   fabric   to   pale   greenish 
grey   and   reducing   the   rock   strength   to   medium   to   high   strength.   Additionally,   indurated   clay   up   to 
2
 S  2­0600­REP­011506­B   ­  Engineering   geology   assessment   report   (SMEC). 
3
  See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   8  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
5mm   thickness   was   observed   as   a  joint   infill   in   most   of   the   drill   holes.   Slickensided   surfaces   were 
observed   throughout   the   drill   holes   suggesting   prior   movements   within   the   rock   mass.   The   rock   mass 
has   been   found   to   be   “blocky”   with   defect   spacing   varying   typically   between   0.1m   to   2m.   Three   main 
discontinuity   sets   were   identified   within   the   dacite   rock   mass   using   downhole   imaging   and   later   data 
analysis   with   DIPS   software.4  

Drill   hole   BH1114   was   drilled   over   water   using   a  barge   as   a  drilling   platform.   The   hole   provided   the 
depth   of   sediment   over   fresh   rock   for   the   construction   of   the   approach   channel   during   construction   of 
the   intake   structures.  

This   series   of   drill   holes   were   sampled   for   soil   testing   as   well   as   Unconfined   Compressive   Strength 
( UCS )  testing   for   rock   strength   properties   (currently   underway).   Drill   holes   BH1115   to   BH1117   were 
converted   to   open   standpipes   with   data   loggers   installed   following   completion   of   drilling   to   monitor 
groundwater   levels. 

3.1.5   Nungar   Creek   area 
Drill   holes   of   the   2000s   series   comprise   BH2101   to   BH2103.   These   drill   holes   will   be   drilled   in   the 
Nungar   Creek   plain   to   obtain   information   on   the   tunnel   alignment,   headrace   structure   of   the   nearshore 
zone.   Drill   holes   BH2102   and   BH2103   are   inclined   holes   to   target   faults   and   will   be   converted   into 
open   standpipes   to   interrogate   the   groundwater   levels   related   to   the   faults,   shallow   depth   of   cover 
related   to   Nungar   Creek   in   particular,   and   proximity   to   the   reservoir.   In   situ   stress   testing   will   be 
conducted   in   BH2101   (the   only   vertical   hole   in   this   series).   To   enable   water   monitoring   of   the   drill   hole, 
a   vibrating   wire   piezometer   installation   is   planned. 

Seismic   refraction   surveys   are   also   planned   in   order   to   obtain   information   on   the   weathering   profile 
and   soil   /  rock   velocity   of   Kellys   Plain   Volcanics   /  Peppercorn   Formation   /  Tantangara   Formation. 
Furthermore,   this   investigation   will   assist   with   determining   the   possible   buried   faults   which   are   not 
visible   from   site   observations.   The   plans   include   two   separate   seismic   refraction   survey   traverses   with 
a   combined   length   of   approximately   3km. 

3.1.6   Tunnel   alignment   on   Long   Plain 
The   3000s   series   of   drill   holes   will   be   drilled   in   the   Tantangara   Creek   area   for   the   Headrace   Tunnel 
( HRT )  and   mainline   tunnel   alignment.   All   drill   holes   are   planned   to   be   drilled   vertically   with   the 
exception   of   BH3106   and   BH3107   which   are   to   be   drilled   an   inclination   of   75°   to   intercept   the   Boggy 
Plain   and   Kiandra   Faults   at   depth.   BH3102   is   positioned   to   target   the   Boggy   Plain   Suite   intrusion   as 
mapped   in   the   literature,   as   no   outcrop   of   this   unit   was   observed   during   the   site   mapping. 

In   situ   stress   testing   will   be   undertaken   in   BH3106.   As   a  representative   permeability   measure   of   the 
unit,   a  combination   of   open   standpipe   (BH3101,   BH3102   and   BH3108)   and   vibrating   wire   piezometers 
will   be   installed   (BH3104,   BH3106,   and   BH3107)   to   measure   the   groundwater   conditions   of   the   faults, 
sedimentary   units   and   overlying   creek   systems. 

Electrical   resistivity   tomography   surveys   will   be   conducted   to   obtain   information   characterisation   and 
pore   composition   (saturation)   of   the   faults   between   the   Boggy   Plain   Suite   (granites)   /  Temperance 
Formation   /  Gooandra   Volcanics.   Furthermore,   this   investigation   will   assist   with   determining   the 
weathering   profile   especially   pertaining   to   the   Volcanics.   The   traverse   length   of   this   investigation   will 
be   approximately   3km. 

3.1.7   Long   Plain   Fault   (Plateau   option   power   station   complex) 
The   4000s   series   drill   holes   are   inclined   and   in   various   locations   near   the   Snowy   Mountains   Highway 
for   definition   and   characterisation   of   the   Long   Plain   Fault.   As   with   any   fault,   understanding   the 
characteristics   enables   the   development   of   an   appropriate   tunnelling   strategy   to   overcome   the 
associated   challenges.   Selected   holes   will   utilise   vibrating   wire   piezometers   for   monitoring   of 
groundwater   conditions.  

4
  Software   for   for   the   interactive   analysis   of   orientation   based   geological   data   from   Rocscience.   See 
https://www.rocscience.com/rocscience/products/dips. 

 
©   Snowy   Hydro   Limited   2017  Page   9  of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Both   electrical   resistivity   tomography   and   seismic   refraction   surveys   will   be   conducted   in   this   series. 
The   main   purpose   of   seismic   refraction   survey   is   to   confirm   intact   structure   of   soils   and   rocks   and   the 
Long   Plain   Fault,   changes   in   lithology   including   Basalts   /  Gooandra   Volcanics   and   the   Shaw   Hill 
Gabbro.   This   investigation   will   also   assist   with   identification   of   other   possible   buried   faults   and 
localised   shearing   associated   with   these   faults   at   depth.   Transverse   length   for   this   section   will   be 
approximately   1km. 

BH4101   was   designed   to   investigate   the   geological   and   geotechnical   condition   of   the   rock   mass   for   a 
Plateau   option   power   cavern   complex.   This   drill   hole   also   provides   information   on   the   rock   mass   for 
the   HRT   for   a  Ravine   option   alignment. 

BH4101   has   recently   been   completed   at   1,176.1m   in   length   and   comprises   an   interlayered 
metamorphic   sequence   of   greenschist   and   metabasalt   units   with   some   chert   and   metamorphosed 
volcaniclastic   layers.   The   drilling   of   the   hole   encountered   drill   deviation   challenges.   As   a  result 
multiple   attempts   to   correct   the   drilling   trajectory   were   implemented   with   partial   success.   The   drill 
deviation   has   complicated   core   recovery   and   also   in   situ   stress   measurements.   A  complete   analysis 
of   this   drill   hole   along   with   televiewer   results   are   in   progress.   The   ongoing   GIP   will   utilise   the   findings 
of   this   drill   hole   and   appropriately   adjust   the   program   to   meet   the   needs   of   the   Project. 

The   composition   of   the   weathered   zone   is   typically   a  fine   grained   metamorphosed   basalt,   orange   and 
brown   in   colour,   extremely   weathered,   appearing   as   a  low   plasticity   silt   from   2.8m   to   13.9m   (residual 
soil   is   found   from   0m   to   2.8m).   From   13.9m   to   36.3m,   layers   of   metamorphosed   basalt   and 
greenschist   both   appear   as   dark   grey   and   grey   green   in   colour,   exhibiting   extremely   to   slightly 
weathered   characteristics.   Fresh   rock   commences   after   this   depth. 

The   fresh   greenschist   rock   is   typically   fine   grained,   dark   grey   to   green   grey   in   colour,   with 
well­developed   foliation   (often   with   epidote,   chert,   pyrite   and   quartz   inclusions   along   foliations). 
Typically,   the   foliation   of   the   core   has   been   measured   between   60­80°   (the   core   is   oriented   at   75°   from 
horizontal).   Therefore,   it   is   likely   that   the   foliation   of   this   unit   is   subvertical   as   it   was   observed   on   the 
surface   mapping.   Initial   logging   of   the   core   has   suggested   the   rock   strength   of   fresh   greenschist   is 
generally   high   to   extremely   high.   However,   rock   strength   of   the   greenschist   is   very   low   when   the   rock 
is   highly   to   extremely   weathered.   The   thickness   of   the   greenschist   units   vary   from   <1m   to   16.6m,   with 
an   average   thickness   of   <5m. 

The   fresh   metabasalt   rock   tends   to   be   the   more   common   lithology   and   is   typically   described   as   fine   to 
medium   grained,   dark   grey   to   pale   grey   green   in   colour   with   weak   to   indistinct   foliation.   Quartz   veining 
is   common   and   pyrite   is   typical   along   foliations.   Chlorite,   sericite   and   calcite   alteration   is   common   at 
depths   greater   than   500m.   Similar   to   the   greenschist   units,   initial   logging   of   the   core   has   suggested 
the   rock   strength   of   fresh   metabasalt   is   generally   high   to   extremely   high.   Thickness   of   the   metabasalt 
units   again,   is   similar   to   the   greenschist   varying   between   <1m   and   17.5m. 

The   geological   contact   between   the   greenschist   and   the   metabasalt   is   generally   abrupt,   producing   a 
foliation   /  contact   parting   in   the   core.   However,   in   some   sections   the   contact   has   been   observed   to   be 
through   a  fault   zone   typically   extending   no   more   than   a  few   hundred   millimetres   along   the   core   with 
angular   rock   fragments   and   clay   infill. 

Chert   bands   are   found   from   95m   to   400m   in   depth   with   an   average   thickness   of   <6m.   These   highly 
siliceous   bands   are   quartz   rich   and   display   significant   mineral   alteration   within   the   unit. 

Geotechnical   laboratory   testing   is   in   progress   with   results   expected   prior   to   FID.   Preliminary 
observations   of   the   core   in   terms   of   defects   (joint   spacing)   and   Rock   Quality   Designation   (R
  QD )  have 
been   developed   as   a  proxy   value   for   rock   fracturing   (rock   mass   permeability)   until   such   data   becomes 
available.   With   reference   to   Look   2007,5  RQD   values   vary   consistently   downhole   however   RQD 
ratings   of   ‘Excellent”   (ie.   RQD   >  90%)   become   noticeably   evident   at   depths   greater   than   700m. 

The   cavern   complex   area   as   represented   in   the   drill   hole   (1,080m   to   1,135m   depth)   comprises 
metabasalt   and   greenschist.   Both   lithologies   are   fine   to   medium   grained,   grey   green   to   dark   grey 

5
  Look,   B.,   2007.  H
  andbook   of   geotechnical   investigation   and   design   tables ,  Leiden:   Taylor   &  Francis,   Table   9.10   Correlation 
between   Rock   Quality   Designation   (RQD)   and   discontinuity   spacing. 

 
©   Snowy   Hydro   Limited   2017  Page   10   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
green,   high   to   very   high   strength   rock.   Joints   are   predominantly   clean,   planar   and   clay   lined.   Defect 
spacing   varies   within   this   location   of   the   core,   with   the   complete   analysis   in   progress.   An   example   of 
drill   core   from   this   range   of   depths   is   shown   in   Figure   3. 

 
Figure   3:   Example   drill   core   from   location   of   power   station   complex   in   Plateau   option6 

For   a  Ravine   option   HRT,   the   rock   mass   is   represented   in   the   drill   hole   between   359m   to   368m   as 
shown   in   Figure   4. 

 
7
Figure   4:   Example   drill   core   from   location   of   HRT   in   Ravine   option  

The   headrace   would   comprise   the   uppermost   6m   of   a  fine   grained   greenschist   with   high   to   very   high 
strength   and   variable   foliation   for   the   crown   and   walls.   The   lower   3m   of   the   tunnel   would   comprise 
very   fine   to   fine   grained   metabasalt   of   medium   to   high   strength   for   the   invert   and   walls. 

As   part   of   the   ongoing   testing   program   rock   will   continue   to   be   tested   for   silica   levels   and   other 
potential   substances   such   as   Naturally   Occurring   Asbestos   (N   OA )  due   to   rock   types   in   the   area.   At 
the   time   of   this   report,   no   hazardous   substances   or   concentration   levels   that   exceed   industry   normal 

6
  Drill   hole   length   1,100   to   1,104m   at   angle.  
7
  Drill   hole   length   360   to   364m   at   angle. 

 
©   Snowy   Hydro   Limited   2017  Page   11   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
levels   were   identified.   As   part   of   the   GIP,   ongoing   precautionary   monitoring   is   in   place   and   will 
continue   for   this   and   all   other   drill   holes. 

See   Figure   5  for   a  high­level   summary   log   of   the   geotechnical   conditions   along   the   full   drill   hole   length 
of   BH4101. 

 
8
Figure   5:   Summary   of   the   geotechnical   characteristics   down   hole   of   BH4101  

   

8
  Definitions:  H
  W­XW   ­  Highly   weathered­Extremely   weathered. 

 
©   Snowy   Hydro   Limited   2017  Page   12   of   60 
 
Figure 5: Summary of the geotechnical characteristics down hole of BH4101
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.1.10   Surge   pressure   shaft   and   Power   house   (Ravine   power   station   complex   option) 

The   aim   of   the   5000s   series   is   to   target   the   full   design   depth   which   covers   the   Ravine   option   for   the 
power   station   complex.   BH5102   is   currently   underway   and   BH5106   will   be   drilled   as   part   of   the 
upcoming   GIP.   The   purpose   is   to   determine   a  longitudinal   profile   which   will   inform   where   the   exact 
positions   of   BH5103   and   BH5104   (if   required)   will   be   positioned.   BH5102   is   being   drilled   directly   over 
the   surge   shaft   location   and   BH5103   for   the   pressure   shaft.   BH5106   is   designed   to   be   drilled   inclined 
to   target   towards   Yarrangobilly   River. 

In   situ   stress   testing   is   planned   for   BH5102   and   BH5104   to   determine   rock   stress   parameters   within 
the   power   station   complex.   Open   standpipes   and   vibrating   wire   piezometers   will   be   installed   to   assess 
groundwater   movement   within   the   units   and   implications   for   construction   and   rock   mass   permeability 
established. 

3.1.8   Yarrangobilly   River   Tolbar   Ridge   alignment 
These   drill   holes   will   be   located   in   the   tailrace   tunnel   (T
  RT )  portion   of   the   alignment   in   locations 
adjacent   to   Yarrangobilly   River.   All   drill   holes   in   this   series   are   vertical   with   the   exception   of   BH6102 
positioned   inclined   to   determine   variation   of   rock   material   beneath   Yarrangobilly   River.   Shallow   depth 
and   possible   structures   are   to   be   targeted   using   open   standpipes. 

Seismic   refraction   surveys   will   be   conducted   to   obtain   information   on   weathering   profile   and   intact 
soil/rock   structure   to   determine   stress   relief   in   the   valley   floor   (groundwater   recharge   zone).   The 
traverse   length   for   this   investigation   will   be   0.75km. 

3.1.9   Talbingo   Intake 
These   drill   holes   will   be   located   in   Talbingo   Reservoir   between   Yarrangobilly   River   arm   and   Middle 
Creek   arm   for   the   Talbingo   intake/outlet.   Two   open   standpipes   will   be   installed   at   BH7103   and 
BH7104. 

Seismic   refraction   surveys   and   continuous   profiling   will   be   conducted   within   the   marine   and   land 
environment   developing   a  weathering   profile   and   soil/rock   velocity   at   the   intake   location.   Furthermore, 
this   investigation   will   assist   with   dredging,   cut   off   wall   design   and   rock   levels   for   foundation   design 
purposes.   The   transverse   length   for   this   investigation   will   be   0.75km. 

The   main   purpose   of   continuous   profiling   is   a  rapid   method   of   assessing   structural   details   such   as 
shallow   alluvial,   weathering   and   bedding   structure   and   faults.   Furthermore,   this   investigation   will   help 
correlate   with   seismic   refraction.   The   traverse   length   for   this   investigation   will   be   3km. 

3.1.10   Access   tunnel   (Emergency   Cable   Ventilation   Tunnel   (EVCT)) 
These   drill   holes   will   be   located   in   Stable   Creek   area   for   the   EVCT   portion   of   the   alignment.   Drill   holes 
are   to   be   accessed   via   helicopter   making   access   difficult   for   most   rigs   hence   specialist   equipment   is 
being   sourced   for   these   holes.   Groundwater   will   be   monitored   with   open   standpipes   and   vibrating   wire 
piezometers. 

Seismic   refraction   surveys   will   be   conducted   on   land­based   holes   with   an   estimated   traverse   length   of 
approximately   0.5km.   The   main   purpose   of   this   investigation   is   to   obtain   information   on   the 
weathering   profile   and   intact   soil/rock   velocity   structure.   This   will   assist   with   excavatability   in   ground 
structures   and   retaining   wall   design   purposes. 

Table   2  shows   the   location   of   the   drill   holes   undertaken   or   in   progress   to   date.   See   the  E
  GAR   for 
preliminary   drill   hole   logs   complying   with   AS1726,9  explanatory   notes,   core   photos   and   laboratory   test 
results   received   to   date.  

   

9
  Standards   Australia,   2017.   AS   1726:2017   ­  Geotechnical   site   investigations,   Standards   Australia. 

 
©   Snowy   Hydro   Limited   2017  Page   13   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
 

Drill   Hole  Location  Easting  Northing  Surface  Inclination  Drill   Hole  Target  Status   at   at 


ID  Relative  from  Depth  Depth  31   October 
Level  horizontal  (m)  (m)  2017 
( RL )  (m)  (degrees) 

BH1114  Tantangara   Reservoir  649605.9  6038179.9  1212  90  30.28  30  Completed 

BH1115  Tantangara   Intake  649431.3  6038166.0  1234  90  55.0  55  Completed 

BH1116  Tantangara   Intake  649225.4  6038173.0  1231  90  93.10  93  Completed 

BH1117  Tantangara   HRT  648948.8  6038110.0  1241  90  65.0  65  Completed 

BH4101  Gooandra   Hill   (Plateau  636218.7  6038499.0  1479  65   to   75  1,176.0  1,176  Completed 


Site) 

BH5102  Marica   track   (Ravine   Site)  632527.0  6038535.0  1331  90  47.110  952  In   progress 


 
Table   2:   Geotechnical   investigation   at   the   time   of   reporting11 

3.2   Ground   characterisation 
This   section   presents   the   geotechnical   description   of   the   properties,   distribution   of   and   relationships 
between   the   main   soil   and   rock   materials.   The   information   is   synthesised   into   a  simple   assessment   of 
likely   conditions   along   the   Project   alignment.  

3.2.1   Soil   materials 
When   considering   the   engineering   properties   of   soils   (weathering   and   erodibility),   coarser   grained 
soils   such   as   mafic   rocks   typically   produce   thicker   soils   while   siliceous   parent   rocks   (granites   and 
rhyolites)   tend   to   have   shallower   soil   profiles   that   are   likely   to   be   sandy   and   weakly   structured.12 

Moye   suggests   alluvium   within   the   Snowy   Mountains   is   quite   restricted   due   to   steep   and   narrow 
valleys.13  This   is   particularly   evident   in   the   Ravine   and   Yarrangobilly   areas   where   alluvium   is   replaced 
with   boulder   lag   deposits   of   mixed   (volcanic   and   sedimentary)   origin.   It   is   common   that   fresh   outcrop 
will   occur   on   lower   slopes   with   active   streams   and   rivers. 

The   open   wide   plains   around   Tantangara   and   Nungar   Creeks   tend   to   have   typical   alluvial   style 
deposits.14  The   residual   and   extremely   weathered   soils   cover   the   majority   of   the   Project   Area,   due   to 
weathering   of   parent   rock.15  The   residual   soils   are   likely   to   comprise   mainly   cohesive   materials   such 
as   silty   clays,   sandy   clay   and   gravelly   clays   with   likely   high   plasticity.   Residual   soils   make   for   suitable 
material   to   be   used   in   earth   dams,   embankments   and   road   base.16  

Two   soil   units   have   been   inferred   at   the   intakes   at   Tantangara   and   Talbingo   Reservoirs.   The   fill 
materials   are   likely   to   be   derived   from   the   excavations   from   material   around   the   intakes   similar   to   the 
residual   and   extremely   weathered   rock   soils.   The   strength   of   these   soils   is   likely   to   have   high 
variability. 

While   granites   are   known   to   be   the   most   prolific   source   of   (chemically)   weathered   soil   material   in   the 
Snowy   Mountains,17  there   is   little   outcrop   seen   in   the   Project   Area.   Quartzites,   acidic   lavas   and 

10
  As   at   31   Oct   2017. 
11
  See  E   GAR . 
12
  Gray,   J.   &  Murphy,   B.W.,   1999.  P
  arent   Material   and   Soils:   a  guide   to   the   influence   of   parent   material   on   soil   distribution   in 
eastern   Australia . 
13
  Moye,   D.G.,   1955.   Engineering   geology   for   the   Snowy   Mountain   schema.  C   ivil   Engineering   Transaction   Journal,   Institution   of 
Engineers,   Australia ,  27,   pp.281–299. 
14
  Ibid. 
15
  Ibid. 
16
  Ibid. 
17
  Ibid. 

 
©   Snowy   Hydro   Limited   2017  Page   14   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
porphyritic   rocks   tend   to   weather   based   on   mechanical   processes   such   as   weakening   along   joints   and 
fault   zones   predominantly   represented   as   crushed   zones.18 

Often   thick   vegetation   cover   precludes   visualising   the   soil   condition.   Without   excavation   (e.g. 
trenching),   Table   3  displays   the   geotechnical   characteristics   of   the   soil   as   assumed   per   geological   unit 
along   the   Project   alignment   based   on   literature   and   field   mapping   observations.   The   value   of 
appreciating   the   various   soils   types   will   contribute   to   planning   the   further   ground   investigation   program 
with   particular   reference   to   proposed   surface   facilities   such   as   portals,   shaft   heads,   access   roads   and 
construction   work   areas. 

  Geotechnical  Susceptibility   to 
Soil   type  Depth 
characteristics  weathering/   erosion 

Kellys   Plain   Volcanics  Topsoil/   Residual  Shallow  Generally   granular  Moderate   to   high 

Peppercorn   Formation  Residual  Shallow   to   moderate  N/A  Moderate 

Tantangara   Formation  Topsoil/   Residual  Moderate  Moderate   potential   for  Low 


shrink/swell 

Temperance   Formation  Topsoil/   alluvial  Moderate  N/A  Low   to   moderate 

Boggy   Plain   Suite  Topsoil/   Residual  Moderate  potential   for   shrink/swell  Low 

Gooandra   Volcanics  Topsoil/   Colluvium  Shallow   to   moderate  High   potential   for  Moderate 


shrink/swell 

Tertiary   Basalts  Topsoil/   Colluvium  Shallow   to   moderate  High   potential   for  Low 


shrink/swell 

Shaw   Hill   Gabbro  Topsoil/   Residual  Shallow  N/A  Low 

Ravine   Beds  Topsoil/   Residual/  Shallow  Moderate   potential   for  Moderate   to   high 


Colluvium  shrink/swell 

Boraig   Group  Residual/  Shallow   to   moderate  N/A  Moderate 


Colluvium 

Bryon   Range   Group  Residual  Shallow  N/A  Low 


19
Table   3:   Geotechnical   soil   characteristics   assumed   from   field   mapping   and   literature   

3.2.2   Engineering   geology   of   the   rock   materials 
Weathering 

The   Project   area   has   two   main   terrains   where   weathering   processes   have   taken   place   (See   Figure   6). 
On   the   east   side   of   the   escarpment   is   undulating   plateau   country,   with   broad   mature   valleys   where 
deep   weathering   has   produced   a  deep   mantle   of   residual   soil   over   the   various   rock   types.   The   depth 
of   weathering   is   likely   to   be   30m   to   40m   with   further   penetration   along   joints.   The   western   side   of   the 
Project   area   (west   of   the   Long   Plain   Fault   escarpment)   has   incised   valleys   with   a  generally   shallower 
weathering   profile   on   the   steep   slopes   and   exposed   competent   rock   on   the   steepest   gradients   and 
commonly   along   the   stream   channels. 

Moye   describes   the   weathering   processes   and   implications   for   the   Project   Area.20  Moye   notes   that 
weathering   is   by   no   means   evenly   developed   throughout   the   Snowy   Mountains   area.   The   important 
factors   influencing   its   development   are   the   rock   type,   local   geological   structure   and   the   erosional 
history   of   each   particular   locality. 

The   weathering   classification   developed   by   Moye   was   a  pioneering   aspect   of   engineering   geology   in 
the   Snowy   Mountains   Scheme   and   has   gone   through   various   modifications   and   standards.21  The 
system   adopted   is   according   to  A
  S   1726  a
  nd   is   presented   in   the  E
  GAR . 

18
  Ibid. 
19
  See  E  GAR .  Some   geotechnical   properties   are   N/A   where   project   requirements   exclude   that   material. 
20
  Moye   1955. 
21
  Ibid. 

 
©   Snowy   Hydro   Limited   2017  Page   15   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
It   is   anticipated   that   in   most   of   the   underground   works,   the   rock   will   be   fresh   or   slightly   weathered.   It   is 
only   in   the   surface   openings   (including   the   intakes,   portals   and   excavation   for   the   surge   shaft   collar) 
that   weathered   rock   is   expected   to   be   encountered.   Results   from   the   ongoing   GIP   are   expected   to 
clearly   define   the   extent   of   the   various   grades   of   weathered   rock   and   inform   how   to   address 
respective   conditions   in   design   and   execution   of   the   rock   excavation. 
Rock   strength 

Rock   strength   (defined   as   UCS)   excludes   discontinuities   within   the   sample.22  A  rock   mass   strength 
can   be   obtained   by   considering   the   pattern   and   nature   of   discontinuities,   their   spacing,   planarity, 
surface   condition   and   aperture.   This   property   is   utilised   in   the   analyses   for   rock   mass   strength   and 
likely   ground   behaviour.  

An   indication   of   the   rock   UCS   can   be   obtained   from   a  tactile   assessment   of   surface   outcrops   or   from 
drill   cores   with   a  classification   made   according   to   AS1726.23  Rock   units   for   the   Project   Area   having   the 
highest   strengths   appear   to   be   igneous   rock   (volcanics)   from   the   Kellys   Plain   Volcanics,   Temperance 
Formation,   Gooandra   Volcanic   and   some   of   the   granites.   The   sedimentary   rocks   of   the   Tantangara 
Formation   and   Ravine   Beds   tend   to   have   more   variable   strengths   due   to   the   layering   of   both   high   and 
low­strength   rocks.   All   of   these   assumptions   will   be   updated   based   on   results   from   the   ongoing   GIP. 
Assessment   of   rock   mass   behaviour 

The   assessment   of   a  rock   mass   is   dependent   on   the   intrinsic   properties   of   weathering   and   strength, 
the   pattern   and   nature   of   discontinuities   and   by   consideration   of   the   actual   failure   mechanism   of   an 
excavated   rock   mass.24  The   approach   to   assess   the   likely   rock   mass   behaviour   has   been   obtained 
from   documented   work   by   Hoek   and   Brown   (1980),25  and   further   described   and   discussed   by   Hoek 
and   Marinos   (2000),26  Hoek   et   al   (2005),27  and   Marinos   et   al   (2005).28 

Referring   to   the   Snowy   Mountains   Hydro­Electric   Authority   (S   MHEA )  engineering   geology 
assessment   for   the   Scheme,29  a  simple   rock   class   classification   (S   nowy   Rock   Class )  was   adopted 
based   on   rock   hardness   (strength)   and   the   nature   of   joints,   seams,   and   shears   plus   the   typical 
support   adopted   in   Table   4.   The   best   rock   is   assigned   an   index   of  5
  ,   and   worst   assigned  1
  .   This   has 
worked   well   in   the   past,   and   experience   with   construction   has   indicated   this,30  but   since   this   system 
was   prepared   in   the   1950s   there   has   been   extensive   development   of   rock   mass   classification   systems 
such   as   the   Rock   Mass   Rating  (  RMR ),31  and   the   Q­System.32 

The   RMR   and   Q­systems   depend   on   reliable   data   and   assigned   values   from   careful   observation   of 
rock   exposures,   in   outcrop,   excavations,   tunnels,   caverns   or   drill   cores.   It   is   premature   to   assign   RMR 
and   Q­system   ratings   at   this   stage   of   the   Project   as   observations   can   only   be   made   on   outcrops   with   a 
22
  UCS   is   used   for   unconfined   compression   test   data   on   intact   rock   and   σci 
   is 
    used   to   define   the   unconfined   compressive 
strength   of   intact   rock   by   back­projection   from   triaxial   tests. 
23
  See   the  E  GAR . 
24
  Marinos,   V.P.,   2012.   Assessing   rock   mass   behaviour   for   tunnelling.  E   nvironmental   &  Engineering   Geoscience ,  18(4), 
pp.327–341;   V.   P.   Marinos,   “Assessing   rock   mass   behaviour   for   tunnelling,”  E   nviron.   Eng.   Geosci .,   vol.   18,   no.   4,   pp. 
327­341,   2012;   Marinos,   V.,   Fortsakis,   P.   &  Stoumpos,   G.,   2015.   Classification   of   Weak   Rock   Masses   in   Dam   Foundation   and 
Tunnel   Excavation.   In  E   ngineering   Geology   for   Society   and   Territory­Volume   6:   Applied   Geology   for   Major   Engineering 
Projects .  Springer,   pp.   859–863. 
25
  Hoek,   E.   &  Brown,   E.T.,   1980.  U   nderground   excavations   in   rock ,  London :   The   Institution   of   Mining   and   Metallurgy. 
26
  Hoek,   E.   &  Marinos,   P.,   2000.   Predicting   tunnel   squeezing   problems   in   weak   heterogeneous   rock   masses.  T   unnels   and 
Tunnelling   International ,  Part   1­2(November),   pp.1–20.   Available   at: 
https://www.rocscience.com/documents/hoek/references/H2000d.pdf   [Accessed   November   16,   2017]. 
27
  E.   Hoek,   P.   G.   Marinos,   and   V.   P.   Marinos,   “Characterisation   and   engineering   properties   of   tectonically   undisturbed   but 
lithologically   varied   sedimentary   rock   masses,”  I nt.   J.   Rock   Mech.   Min.   Sci. ,  vol.   42,   no.   2,   pp.   277­285,   2005. 
28
  Marinos,   V.,   Marinos,   P.   &  Hoek,   E.,   2005.   The   geological   strength   index:   applications   and   limitations.  B   ulletin   of   Engineering 
Geology   and   the   Environment ,  64(1),   pp.55–65. 
29
  Moye   1955;   Moye,   D.G.   &  Price,   D.,   1966.   Geology   and   Tunnelling   in   the   Snowy   Mountains   Scheme. 
30
  See,   eg   Moye,   D.G.,   1959.   Rock   mechanics   in   the   investigation   and   construction   of   T1   underground   power   station,   Snowy 
Mountains,   Australia.  G   eological   Society   of   America   Engineering   Geology   Case   Histories ,  3,   pp.13–44;   Pinkerton,   I.L.   & 
Gibson,   E.J.,   1964.   Tumut   2  Underground   Power   Plant.   Journal   of   the   Power   Division,   90(1),   pp.33–108. 
31
  Bieniawski,   Z.T.,   1993.   Classification   of   rock   masses   for   engineering:   the   RMR   system   and   future   trends.   Comprehensive 
rock   engineering,   3,   pp.553–573. 
32
  Barton,   N.,   Lien,   R.   &  Lunde,   J.,   1974.   Engineering   classification   of   rock   masses   for   the   design   of   tunnel   support.   Rock 
Mechanics,   6(4),   pp.189–236. 

 
©   Snowy   Hydro   Limited   2017  Page   16   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
range   of   weathering   conditions.   However,   there   can   be   a  preliminary   assessment   based   on   assigning 
a   geotechnical   strength   index   (G
  SI ),   based   on   results   from   mapped   rock   structure,   lithology   and 
making   a  judgement   on   likely   rock   mass   behaviour   in   the   proposed   tunnels   and   other   underground 
openings. 

Marinos   proposed   a  useful   system,33  with   charts   for   tunnel   behaviour   types   and   a  combined   GSI 
chart,   obtaining   tunnel   behaviour   type   due   the   nature   of   the   rock   mass   structure,   intact   strength   and 
thickness   of   overburden.   Failures   can   be   grouped   as   either   structural   (gravity)­controlled   failures, 
such   as   wedge   and   chimney   type   failures   (ravelling   and   flowing   ground)   and   stress­controlled   failures 
(shear   failures,   squeezing   and   swelling,   anisotropic   deformations   and   brittle   failures).   Table   5  and 
Table   6  present   the   charts   from   Marinos   (2012)   as   Tunnel   Behaviour   Types   and   the   Tunnel   Behaviour 
Chart   for   rock   masses   respectively. 

Rock   mass  Rock   condition  Summary   characteristics  Technical   support   used   on   works   of   the 


classification        SMHEA 

5  Excellent  Sound,   compact,   usually   dry   rock,   either  No   support,   except   in   large   excavations 


unjointed   with   tightly   closed   strongly   cemented  such   as   power   stations. 
joints. 

5S  Excellent   (but  As   above,   but   ‘spalling’   or   ‘popping’   occurs.  Generally   rock   bolting   if   appropriate. 


highly 
stressed) 

4  Good    Hard   rock   generally   dry   with   tightly   closed,  Mainly   unsupported   or   with   few   rock   bolts 


weakly   cement   joints,   some   slightly   open   joints  to   pin   shoulders,   if   orientation   of 
with   water   seepages   or   flows   may   occur.   May  excavation   is   adverse   in   relation   to   main 
contain   some   narrow   sheared   or   crush   zones  jointing.   Generally   less   than   one   bolt   per 
linear   fit   for   a  20ft   (6.1m)   diameter   tunnel. 

3  Very   fair  Mainly   hard   rock,   but   considerably   loosened   by  Light   steel   set   or   “completely”   supported   in 


the   opening   up   of   weakly   cement   joints   on  rock   bolts,   occasionally   supplemented   by 
excavation   or   due   to   the   presence   of   slightly  steel   channels   and   wire   mesh.   Usually   2  to 
open   joints,   or   narrow   sheared   or   crushed  3   bolts   per   linear   fit   for   a  20ft   (6.1m) 
zones.   May   be   dry   but   usually   wet.   Tends   to  diameter   tunnel. 
break   entirely   along   joint   planes   on   excavation, 
regardless   of   the   orientation   of   excavation 
surfaces   in   relation   to   the   joint   planes. 

2  Fair  Partly   hard   rock   but   usually   containing   more  Generally   heavy   steel   sets   in   tunnels   and 


than   20%   of   soft   material   classifiable   as   soil,   i.e.,  light   steel   sets,   or   rock   bolts   with   mesh   in 
crushed   zones,   loosely   jointed   sheared   zones   or  shafts. 
highly   to   completely   altered   zones. 

1    Poor  Consists   of   more   than   50%   soft   material  Generally   heavy   steel   sets   with   close 


classifiable   as   soil,   i.e.,   crushed   zones,   loosely  timbering   in   both   tunnels   and   shafts.   Invert 
jointed   sheared   zones   or   highly   to   completely  struts   occasionally   required   in   tunnels 
altered   zones.   Can   be   excavated   without   the   use 
of   explosives.   Exerts   pressure   on   supports. 

0    Very   poor  Consists   entirely   of   soft   material   classifiable   as  Heavy   steel   sets   at   close   spacing   in   both 


rock,   usually   crushed   or   completely   altered   rock.  tunnels   and   shafts.   Invert   struts   required   in 
Exerts   pressure   on   top   and   sides   of   supports.  tunnel.   Timber   or   steel   spilling   required. 
Includes   squeezing   and   swelling   ground  Pilot   drifts   and   other   special   tunnelling 
techniques   possibly   required. 
Table   4:   SMHEA   rock   mass   classification   and   support   practice 

33
  Marinos,   V.P.,   2012.   Assessing   rock   mass   behaviour   for   tunnelling.  E
  nvironmental   &  Engineering   Geoscience ,  18(4), 
pp.327–341. 

 
©   Snowy   Hydro   Limited   2017  Page   17   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Table   5:   Brief   description   and   schematic   presentation   of   tunnel   behaviour   types34 

34
  Marinos   2012. 

 
©   Snowy   Hydro   Limited   2017  Page   18   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Table   6:   Tunnel   behaviour   chart   for   rock   masses35 

35
  Marinos   2012. 

 
©   Snowy   Hydro   Limited   2017  Page   19   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.3   Geological   model 
3.3.1   General 
The   purpose   of   developing   a  geological   model   of   the   Project   area   is   to   synthesise   all   available   data 
into   a  comprehensible   explanation   of   the   ground   conditions   relevant   to   the   Project   elements.   The 
approach   is   to   treat   the   model   as   a  Total   Geological   Model   (T  GM ),36  with   the   understanding   that 
further   updates   will   be   linked   to   results   from   the   ongoing   GIP. 

The   geological   model   approach   assists   with   the   confidence   level.   The   International   Association   of 
Engineering   Geology   and   the   Environment   (I AEG )  set   up   a  commission   in   2005   to   advise   on   the   use 
of   engineering   geological   models.37  A  more   recent   paper   by   Parry   et   al   (2014)   provides   a  useful 
approach   for   preparing   a  geological   model.38  It   describes   a  process   whereby   a  conceptual   model   is 
initially   set   up,   followed   by   an   observational   model,   which   can   then   lead   to   an   analytical   model, 
provided   there   is   sufficient   information. 

3.3.2   Assumptions 
Based   on   literature,   published   maps   and   field   mapping,   the   regional   geological   setting   of   the   Project   is 
very   complex   and   has   been   affected   by   several   cycles   of   deformation,   metamorphism,   uplifting, 
erosion,   deposition   and   volcanism.   In   addition,   assumptions   have   been   made   with   inferring   geological 
boundaries   as   per   published   maps   and   geological   contacts   and   structures   vertically   propagated   in   the 
absence   of   factual   data.39 

3.3.3   Summary   of   site   conditions 
The   Project   site   is   in   southeastern   NSW   within   the   Lachlan   Orogen   (Fold   Belt),   a  geological   province 
of   old   volcanic   belts,   sedimentary   basins   and   intrusive   rocks   that   have   been   affected   by   several 
episodes   of   orogenesis   and   metamorphism.40  The   juxtaposed   geological   units   appear   to   be   mostly 
aligned   in   a  general   north­south   direction.   The   relative   ages   are   not   sequential   due   to   a  range   of 
structural   movements   along   faults,   and   folding. 

These   two   distinct   terrains   are   separated   by   a  major   crustal   suture   and   escarpment   caused   by 
movement   on   the   Long   Plain   Fault. 

This   geological   setting,   presented   in   simple   form   in  F   igure   5,   has   implications   for   the   engineering 
geology   of   the   Project.   This   is   due   to   a  wide   range   of   rock   types   and   geological   structures,   a 
hydrogeological   situation   with   potential   impacts   due   to   the   planned   underground   openings   and   the 
geomorphological   setting.   In   addition,   the   past   tectonic   setting   and   present­day   crustal   setting 
produce   an   in   situ   stress   that   affects   the   behaviour   of   the   rock   mass   at   various   depths   when   subject   to 
underground   excavation. 

 
Figure   6:   Geomorphological   features   of   Project   area41   

36
Fookes,   P.G.,   Baynes,   F.J.   &  Hutchinson,   J.N.,   2000.   Total   Geological   History:   A  Model   Approach   To   The   Anticipation, 
Observation   And   Understanding   Of   Site   Conditions.   In  I nternational   Conference   on   Geotechnical   and   Engineering   Geology ; 
GeoEng   2000.   International   Society   for   Rock   Mechanics,   pp.   370–421. 
37
  IAEG   COMMISSION   25:   USE   OF   ENGINEERING   GEOLOGICAL   MODELS. 
38
  Parry,   S.;   Baynes,   F.J.;   Culshaw,   M.G.;   Eggers,   M.;   Keaton,   J.F.;   Lentfer,   K.;   Novotny,   J.;   Paul,   D..   2014   Engineering 
geological   models:   an   introduction:   IAEG   commission   25.  B   ulletin   of   Engineering   Geology   and   the   Environment ,  73   (3). 
689­706.   Available   at   http://doi.org/10.1007/s10064­014­0576­x. 
39
  See  E  GAR . 
40
  See   the   section   on   the   Lachlan   Orogen   in  C
  hapter   Six   ­  Geology   and   terrain . 
41
  See  E  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   20   of   60 
 
Long Plain Fault Zone Limestone
N
VV Cenozoic basalt Section A-A’ on Figure 8-2
5 km

KIANDRA FAULT
Tantangara Plain

INCISED RAVINE AREA

PLATEAU AREA

Boggy Plain

Figure 6: Geomorphological features of Project area


 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Table   7  presents   a  summary   of   the   main   rock   units,   location   with   respect   to   Project   features,   and   the 
likely   issues   that   may   affect   design   and   construction.   For   additional   geological   details   please   refer   to 
Chapter   Six   ­  Geology   and   terrain .  The   right   side   column   of   the   table   covers   the   geological   and 
geotechnical   issues   for   each   rock   unit.   This   is   a  general   summary   that   will   be   further   updated   based 
on   GIP   results   that   are   focused   on   risk   mitigation   and   refinement   of   predictions.  

Table   7:   Summary   of   main   rock   units   in   geological   model   with   respect   to   their   position   along   Project 
alignment.42 

42
  See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   21   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.3.4   Modelling   issues 
The   two   distinct   terrains   described   above   are   a  consequence   of   geological   evolution   and   the 
present­day   geomorphological   processes: 

1. Plateau   Area   ­  this   area   has   been   subject   to   uplift   that   occurred   about   20­25Ma   (Cenozoic 
Era)   with   differential   movements   causing   both   direct   uplift   and   tilting.   It   includes   all   geological 
units   in   Table   7  between   the   Kellys   Plain   Volcanics   and   the   Gooandra   Volcanics   and   in 
addition   to   the   older   Palaeozoic   Age   orogenic   events   that   extended   between   the   Ordovician 
and   Devonian   Periods.   It   is   most   likely   that   the   Long   Plain   Fault   was   reactivated   at   some   time 
during   the   Cenozoic   Era,   as   an   oblique   thrust   with   a  lateral   slip   component,   in   addition   to 
some   of   the   faults   across   the   plateau,   including   the   Boggy   Plain   Fault   and   Kiandra   Fault. 
These   faults,   formed   in   tension   could   have   opened   or   closed   crushed   zones   that   extend   to 
tunnel   level.   As   part   of   the   ongoing   4000s   series   drill   holes   in   the   GIP,   this   issue   will   be 
clarified; 
2. Incised   Ravine   Area   ­ t he   west   of   the   Long   Plain   Fault   Zone   is   considered   to   have   been 
initially   active   during   the   Palaeozoic   and   reactivated   in   the   Cenozoic.   This   area   was   not 
affected   by   the   Cenozoic   uplift   to   the   same   extent   as   the   Plateau   area,   but   there   must   have 
been   some   uplift   as   the   current   terrain   is   an   incised   ridge   and   ravine   landscape,   with   the 
Tumut   River   base   level   having   been   the   control   elevation.   Thus,   streams   and   gullies   have   cut 
into   the   escarpment   of   the   Long   Plain   Fault   exposing   the   profiles   of   the   Ravine   Beds,   Boraig 
Group   and   Byron   Range   Group,   and   their   unconformity   contacts.   As   a  consequence   of   the 
down   cutting   process,   slopes   are   much   steeper   than   in   the   Plateau   area. 

The   Yarrangobilly   Caves   formed   in   the   upper   reaches   of   the   Yarrangobilly   River   during   the 
development   of   the   limestone   beds   of   the   Ravine   Area   terrain.   This   karstic   limestone   appears   to   be 
limited   to   an   area   6km   north   of   the   Project   alignment.   However,   a  hole   drilled   at   Ravine   in   the   lower 
Yarrangobilly   valley   in   1918   for   mining   exploration   encountered   limestone   at   the   base   of   sedimentary 
rocks   that   are   likely   Ravine   Beds,   at   a  depth   of   ~230m..  

Given   that   the   limestone   at   the   Yarrangobilly   Caves   is   stratigraphically   at   the   base   of   the   Ravine   Beds 
and   in   the   eastern   limb   of   a  large   synclinal   basin,43  it   is   prudent   to   check   if   there   is   a  connection 
between   both   limestone   occurrences,   and   if   there   is   any   likelihood   of   further   intersection   by   the 
Project   alignment.   Figure   6  is   an   interpretative   geological   section   showing   the   limestone   distribution. 
This   indicates   it   is   unlikely   limestone   will   be   encountered   along   the   tunnel   alignment   but   cannot   be 
ruled   out   until   GIP   drilling   and   analysis   is   completed.   If   it   is   encountered,   the   limestone   is   likely   to   be 
below   the   limit   of   karstic   features,   subject   to   a  range   of   conditions,   and   may   provide   favourable 
tunnelling   conditions.   The   planned   GIP   includes   drilling   to   tunnel   levels   along   the   TRT   alignment   that 
can   confirm   if   limestone   could   be   along   the   Project   alignment.   Based   on   results   of   the   GIP,   the   tunnel 
excavation   design   will   be   adjusted   to   address   all   updated   predicted   ground   conditions. 

The   Cenozoic­age   basalt   is   noted   to   follow   an   elongated   outcrop   in   a  direction   approximately   parallel 
to   the   Long   Plain   Fault   Zone.   However,   at   this   stage   of   analysis,   there   does   not   appear   to   be   features 
of   concern   south   of   the   basalt   outcrop   area   indicating   major   faulting.   This   is   possibly   because   the 
pervasive   foliation   and   elongation   of   the   rock   mass   bodies   in   this   area   created   a  landscape   of   aligned 
valleys   (still   seen   today)   and   appreciating   that   Cenozoic   basalts   have   been   mapped   as   filling   paleo 
valleys   in   other   parts   of   the   Snowy   Mountains.44  Drilling   along   the   tunnel   alignment   will   assist   in   further 
defining   if   there   is   an   issue   for   design   of   various   components   planned   in   this   area. 

43
  Moye   et   al.   1954. 
44
  Sharp,   K.R.,   2004.   Cenozoic   volcanism,   tectonism   and   stream   derangement   in   the   Snowy   Mountains   and   northern   Monaro   of 
New   South   Wales.  A   ustralian   Journal   of   Earth   Sciences ,  51(1),   pp.67–85.   Available   at: 
http://dx.doi.org/10.1046/j.1400­0952.2003.01045.x. 

 
©   Snowy   Hydro   Limited   2017  Page   22   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   7:   Section   A­A'   (from   Figure   6)   indicating   an   interpreted   extension   of   the   Yarrangobilly   Limestone 
towards   the   west45 

3.4   Rock   mass   design   parameters 
3.4.1   Approach   to   assessment   of   rock   mass   design   parameters 
The   preliminary   rock   mass   design   parameters   are   either   assumed   (if   there   is   no   observational   basis 
for   selecting   values)   or   estimated   (if   there   is   observational   basis).   Most   of   the   decisions   for   selection 
of   values   have   been   based   on   assumptions   from   empirical   processes   combined   with   engineering 
judgement.   These   parameters   are   expected   to   be   confirmed   and   or   revised   as   a  result   of   the   ongoing 
GIP. 
Rock   mass   classification 

Rock   mass   classification   systems   constitute   an   integral   part   of   empirical   design   for   civil   design.   Prior 
to   the   publication   of   currently   accepted   systems,   SMHEA   had   its   own   system   based   on   rock 
soundness,   strength,   defects   and   water   (the   Snowy   Rock   Class   as   noted   above)   that   provided   a 
guideline   for   underground   rock   support   used   on   the   Scheme.   This   is   compared   below   with   other 
classification   systems   now   in   use   as   described   in  C
  hapter   Six . 
Groundwater 

The   groundwater   for   the   Project   Area   has   been   assessed   and   is   summarised   below.   For   additional 
details,   please   refer   to  C
  hapter   Eight   ­  Meteorology   and   hydrology  o  f   this   Report.   The   key 
hydrogeology   considerations   for   the   Project   include: 

1. Major   vertical   faults   may   act   as   potential   conduits   for   draining   of   water   sources,   however   there 
is   likely   to   be   low   hydraulic   connection   between   the   surface   and   the   rock   mass   at   depth   within 
these   fault   zones  (  due   to   an   upper   weathered   profile   and   lack   of   persistence   with   depth) ; 
2. Groundwater   inflows   will   exist   during   construction   of   underground   structures,   however   will 
significantly   decrease   with   time   (within   a  few   weeks)   to   a  steady   rate   or   even   dry   up;   and 
3. Groundwater   inflow   into   underground   structures   will   induce   localised 
dewatering/depressurisation   around   the   immediate   structure,   with   a  limited   regional 
depressurisation   extent.  

The   overall   volumetric   impact   of   the   inflow   is   considered   to   be   minor   and   highly   unlikely   to   cause 
impacts,   or   any   change,   to   sensitive   receptors.   As   part   of   the   ongoing   GIP,   information   to   further   refine 
groundwater   modelling   is   one   of   the   key   targeted   outcomes. 

3.4.2   Rock   mass   characterisation 
All   relevant   data   are   compiled   on   a  geological   unit   basis,   taking   into   consideration   the   rock   type, 
tectonic   history,   anticipated   strength,   weathering,   alteration   and   rock   mass   structure.   A  table   of   rock 

45
  See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   23   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
mass   characteristics   and   assumed   or   estimated   physical   and   mechanical   parameters   are   presented   in 
tabulated   form   (together   with   the   groundwater   and   stress   condition)   in   the  E
  GAR . 

3.4.3   Rock   mass   models 
GSI 

Marinos   et   al   (2005)   state   that   the   GSI   is  
based   on   the   assumption   that   the   rock   mass   contains   a  sufficient   number   of   ‘randomly’   oriented 
discontinuities,   such   that   it   behaves   as   an   isotropic   rock   mass.   In   other   words,   the   behaviour   of   the   rock 
mass   is   independent   of   the   direction   of   the   applied   load.  
And  
it   is   clear   that   the   GSI   system   should   not   be   applied   to   the   rock   mass   in   which   there   is   a  clearly   defined 
dominant   structural   orientation.   Undisturbed   slate   is   an   example   of   a  rock   mass   in   which   the   mechanical 
behaviour   is   highly   anisotropic   and   which   should   not   be   assigned   a  GSI   value   based   on   the   chart.  
However,   the   Hoek­Brown   criterion   (Hoek   &  Brown   1980;   Hoek   &  Diederichs   200646)   and   the   GSI 
charts   can   be   applied   with   caution   if   the   failure   of   such   rock   masses   is   not   controlled   by   the 
anisotropy. 

The   GSI   tables   are   presented   in   Figure   8  and   Figure   9,   from   Marinos,   et   al   (2005),   and   Marinos   and 
Hoek   (2000)   respectively.   The   second   table   is   for   sedimentary   rock   sequences   where   there   are 
variably   layered   rocks   ranging   from   clastic   (sandstone   and   conglomerate)   to   fine   grained   (siltstone 
and   shale)   in   an   alternating   sequence. 

46
  Hoek,   E.   &  Diederichs,   M.S.,   2006.   Empirical   estimation   of   rock   mass   modulus.  I nternational   journal   of   rock   mechanics   and 
mining   sciences ,  43(2),   pp.203–215. 

 
©   Snowy   Hydro   Limited   2017  Page   24   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   8:   Geological   Strength   Index   chart47 

Figure   9  has   not   yet   been   used   for   this   preliminary   analysis   as   the   relative   proportions   of   the 
sedimentary   strata   are   not   known   in   enough   detail   to   select   the   relevant   GSI.   This   approach   can   be 
used   once   additional   drilling   data   is   available,   particularly   for   the   Tantangara   Formation   and   Ravine 
Beds. 

47
  Marinos   et   al   2005. 

 
©   Snowy   Hydro   Limited   2017  Page   25   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   9:   GSI   for   heterogeneous   rock   masses   such   as   flysch48  

The   source   data   for   assigning   GSI   in   the   Project   area   is   at   this   stage   essentially   from   outcrops   of   rock 
and   references   to   descriptions   in   the   published   geological   maps.   Some   benefit   was   also   drawn   from 
the   tunnel   logs   of   the   Scheme   where   it   is   assessed   that   the   rocks   so   described   are   similar   to   the   units 
along   the   Project   alignments. 

To   date,   the   GIP   has   produced   drill   cores   of   the   Kellys   Plain   Volcanics   and   Gooandra   Volcanics   from 
which   GSI   values   can   be   obtained.   The   hole   in   the   Gooandra   Volcanics   has   been   briefly   reviewed   and 
the   assessed   GSI   appears   to   be   consistent   with   the   preliminary   assumptions. 

Projecting   GSI   values   taken   from   outcrops   to   depth   may   require   a  shift   to   the   left   or   left   and   upward 
on   the   charts   (Marinos   et   al.   2005).   However,   at   great   depths,   such   as   at   1,000m   or   more   in   hard   rock, 
the   rock   mass   structure   may   be   so   tight   that   the   rock   mass   behaviour   approaches   that   of   intact   rock 
and   application   of   the   GSI   is   no   longer   meaningful.   According   to   these   authors,   at   such   depths   brittle 
behaviour   dominates   with   resulting   spalling,   slabbing   and   rock   bursts.   When   tectonic   disturbance   is 
reported   and   persists   at   depth,   such   as   the   Long   Plain   Fault,   the   GSI   charts   may   be   applicable   but 
used   with   caution   and   updated   based   on   results   from   the   ongoing   drilling   as   part   of   the   GIP. 
Other   systems 

There   are   two   rock   mass   classification   systems,   independent   of   the   GSI,   that   are   commonly   used   to 
classify   rock   masses   for   the   application   of   rock   support   measures.   These   are   the   RMR   and   the 
Q­system   as   noted   above.   While   both   systems   are   planned   to   be   used   on   the   Project,   the   Q­system   is 
more   applicable   for   tunnel   support   design.   These   classifications   require   large   exposures   of   rock,   such 
as   in   a  tunnel,   or   in   a  rock   cutting   or   considerable   lengths   of   drill   core   in   order   to   obtain   meaningful 

48
  Marinos   and   Hoek   2000. 

 
©   Snowy   Hydro   Limited   2017  Page   26   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
parameters.   This   is   generally   not   yet   available   at   the   Project   area,   apart   from   correlations   with   existing 
tunnel   log   data,49  and   are   selectively   further   assessed   in   the  E  GAR .  

In   addition,   the   SMHEA   developed   its   own   rock   mass   classification   and   support   practice   system 
(Jacobs   2017).   This   system   placed   the   best   rock   at   Class   5  (excellent)   and   the   worst   at   Class   0  (very 
poor).   As   most   rock   mass   systems   in   use   today   use   Class   1  as   the   best   rock,   this   assessment   has 
inverted   the   numbering   system.50  

3.4.4   Assumptions 
To   develop   the   GSI,   charts   were   prepared   using   Figure   7  as   a  basis.51  The   GSI   estimation   given   is   a 
range   for   both   the   assumed   better   rock   in   a  formation   and   likely   poorer   rock   such   as   in   weak   or 
sheared   zones.   In   some   cases,   where   deeper   rock   cover   may   improve   the   rock   mass   condition   by 
improving   the   joint   surface   condition   and   general   tighter   rock   mass,   the   GSI   is   assumed   to   be   higher. 
It   should   be   emphasised   that   ranges   of   GSI   are   usually   recommended.52 

The   table   presenting   the   assessment   of   rock   mass   characteristics   along   the   Project   tunnel   alignments 
can   be   found   in   the  E
  GAR .  In   regard   to   this   table,   it   is   noted   that: 
Assumed   intact   UCS   is   based   on   judgement   of   typical   strengths   for   each   lithology   assuming   the   rock   is 
fresh   at   tunnel   level.   A  conservative   UCS   was   initially   adopted   and   will   be   further   assessed   as 
knowledge   of   the   Project   area   improves. 
At   fault   zones,   the   UCS,   being   of   intact   rock,   should   be   higher   than   may   generally   be   thought.   The 
characteristics   of   intact   rock   components   tend   to   be   masked   by   the   surrounding   sheared   and 
weathered   material.   Thus,   a  UCS   of   up   to   20MPa   could   be   adopted   for: 

1. The   Long   Plain   Fault   Zone,   100   to   1,000m   wide;   the   GSI   could   be   30   to   35   and   the   intact 
UCS   at   30MPa; 
2. The   shallower   faults   such   as   Boggy   Plain   Fault   and   Kiandra   Fault,   where   little   is   known   about 
their   extent,   but   10m   to   100m   widths   could   be   assumed   taking   into   account   associated 
sheared   rock.   At   depth   of   200m,   the   GSI   allowed   could   be   20   and   the   intact   UCS   at   20MPa. 

The   assumed   deformation   modulus   uses   guidelines   in   Hoek   &  Diederichs   (2006).   However,   the 
presented   values   are   based   on   an   estimated   GSI   that   also   requires   verification. 

Weathering   is   noted   in   SMHEA   papers,53  to   be   up   to   50m   deep   in   granites   due   to   the   inherent 
alteration   and   long   exposure   over   the   Kosciuszko   plateau   area.   The   pattern   of   weathering   is   different 
from   the   granite   in   sedimentary   and   metamorphic   rocks   and   there   may   be   preferential   weathering 
along   weaker   layers   such   as   in   shale   beds   and   in   sheared   zones.   However,   at   depths   of   greater   than 
100m   it   is   generally   considered   the   rocks   will   be   fresh.   Weakening   of   the   rock   mass   may   have 
occurred   due   to   hydration   from   percolating   groundwater   or   chemical   alteration   due   to   hydrothermal 
activity,   and   such   occurrence   can   only   be   confirmed   from   further   subsurface   investigations. 

The   GSI   estimation   is   based   on   descriptions   of   the   rock   mass   structure   and   surface   conditions   as 
guided   in   the  E
  GAR .  The   GSI   in   the   various   rock   masses   assessed   was   estimated   from   surface 
outcrops,   and   a  few   excavations   and   limited   drill   cores.   The   ongoing   GIP   will   produce   drill   holes   and 
associated   drill   core   testing,   and   analysis   that   will   enable   more   accurate   predictions   of   the   various 
rock   properties   at   the   depths   of   the   proposed   underground   infrastructure. 

49
  Rosin,   S.,   2017.  G   eological/geotechnical   Assessment   of   Existing   Tunnels   Report   and   Interpretation   for   New   Underground 
Structures ,  Sydney:   Jacobs   Australia   Pty   Ltd,   the   findings   of   which   have   been   considered   in   the  E
  GAR . 
50
  Inverting   the   scale   was   agreed   during   a  joint   workshop   between   SMEC   and   Snowy   Hydro   on   21   July   2017. 
51
  See  E
  GAR . 
52
  Marinos,   et   al.   2005. 
53
  See,   e.g.   Moye   1955.  

 
©   Snowy   Hydro   Limited   2017  Page   27   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.7   Geotechnical   description   for   Project   components 
3.7.1   General 
The   design   scope   for   the   power   waterway   hydraulics   involves   the   determination   of   hydraulic 
performance   of   the   water   conveyance   system   between   the   Tantangara   and   Talbingo   reservoirs.54  As 
of   the   date   of   this   Report,   two   alternative   locations   have   been   carried   forward   for   the   power   station 
complex:   the   Ravine   and   the   Plateau.  C   hapter   Nine   ­  Facilities   describes   differences   in   design 
between   the   two   locations.   This   Chapter   provides   a  geotechnical   description   of   the   Project   elements 
for   both   alignment   options.   The   descriptions,   observations   and   recommendations   are   from   the 
following   sources: 

1. Published   literature   (maps   and   reports)   summarised   in  C
  hapter   Six   ­  Geology   and   terrain   of 
the   Study   Report; 
2. Field   mapping   excursions   along   the   waterway   alignments   during   March   to   June   2017;   and 
3. Geotechnical   assessments   of   proposed   access   roads   in   September   2017. 

Figure   10   depicts   the   general   arrangement   of   the   power   station   complex   and   associated   feeder/ 
collector   infrastructure   along   with   headrace   and   tailrace   connectivity.   See  C  hapter   Nine   ­  Facilities   for 
a   more   detailed   description. 

 
55
Figure   10:   General   arrangement   of   the   power   station   complex   (relevant   to   both   options)  

 
   

54
  See  S
  2­1400­REP­014035   ­  Civil   and   Structural   Design   Report   (SMEC)   (CSDR). 
55
 S  2­1405­DRG­018613   UNDERGROUND   POWER   STATION   ­  POWER   STATION   COMPLEX   ­  GENERAL   ARRANGEMENT 
ISOMETRIC   SHEET   1  (SMEC). 

 
©   Snowy   Hydro   Limited   2017  Page   28   of   60 
 
NOTES:
1. FOR DRAWING INDEX AND GENERAL NOTES REFER TO DRAWING S2-1405-DRG-018601.
HEADRACE TUNNEL

TAILRACE SURGE TANK


UPPER EXPANSION POND

HEADRACE SURGE TANK


HEADRACE SURGE TANK
LOWER EXPANSION CHAMBER

DISTRIBUTOR TUNNEL
HEADRACE VALVE CHAMBER

EXPANSION CHAMBER
CONSTRUCTION ADIT
HEADRACE VALVE CHAMBER ACCESS TUNNEL
PRESSURE SHAFTS

HEADRACE CONSTRUCTION
ADIT (DOWNSTREAM)

MAIN ACCESS TUNNEL

DRAFT TUBE VALVE GALLERY


ACCESS TUNNEL
TAILRACE SURGE TANK
ACCESS TUNNEL

MAT/ECVT
CONSTRUCTION ADIT

MACHINE HALL

TAILRACE SURGE TANK IPB GALLERIES


EXPANSION CHAMBER TRANSFORMER HALL

HIGH PRESSURE TUNNELS TAILRACE SURGE


TANK
PENSTOCK TUNNELS
150

COOLING WATER TUNNEL


140

COLLECTOR TUNNELS
130

DRAFT TUBE TUNNELS


120

TAILRACE TUNNEL
110

EMERGENCY EGRESS, CABLE


AND VENTILATION TUNNEL
100
90

GENERAL ARRANGEMENT ISOMETRIC


80
150 mm ON ORIGINAL

70
60

DRAWING FILE LOCATION / NAME PLOT DATE TIME DESIGN MODEL FILE REFERENCE
17/11/2017 12:32:59 PM FEASIBILITY
50

S2-1405-MOD-014954

EXTERNAL REFERENCE FILES REV DATE AMENDMENT / REVISION DESCRIPTION WVR No APPROVAL TITLE NAME SCALES AT A1 SIZE DRAWING DESIGNER CLIENT PROJECT TITLE SNOWY 2.0
40

0 17/11/2017 FEASIBILITY DESIGN - ISSUED FOR USE WVR0102 D.E. DRAFTER J. HUNTER UNDERGROUND POWER STATION
POWER STATION COMPLEX
30

DRAFTING CHECK J. IKONEN


DESIGNER M. YEE GENERAL ARRANGEMENT
20

DESIGN CHECK A. NEUMAIER ISOMETRIC SHEET 01


10

PROJECT MANAGER D. EVANS PHASE DRAWING No. REVISION


SMEC PROJECT NO. 30012060 FEASIBILITY S2-1405-DRG-018613 0
A1

PROJECT DIRECTOR C. CLARKE


0

Figure 10: General arrangement of the power station complex (relevant to both options)
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Figure   11   below   provides   a  long   section   view   of   the   two   power   waterway   alignment   options 
superimposed   with   interpreted   geology   along   the   Project   alignment.   Both   options   commence 
chainage   at   Tantangara   Reservoir   with   Talbingo   Reservoir   serving   as   the   second   intake   as   well   as 
representing   the   end   chainage   of   both   options. 

The   Ravine   Location   would   have   the   cavern   complex   located   in   the   Ravine   Beds   with   the   cavern 
complex   for   the   Plateau   Location   located   within   the   Gooandra   Volcanics   as   shown   below.  

 
56
Figure   11:   Power   waterway   inferred   geological   long   section  

   

56
 S
  2­171026­INF­TUNNEL­GA­091­KS_ID   ­  SNOWY   2.0   RAVINE   AND   PLATEAU   OPTION   ­  PLAN   AND   LONG   SECTION . 
Ravine   option   shown   in   blue.   Pink   represents   Plateau   option   (Plateau   option   power   station   complex   not   shown). 

 
©   Snowy   Hydro   Limited   2017  Page   29   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

   

 
©   Snowy   Hydro   Limited   2017  Page   30   of   60 
 
EXISTING SURFACE (RAVINE OPTION)

EXISTING SURFACE (PLATEAU OPTION)

NOT FOR CONSTRUCTION SNOWY 2.0 C ABN 47 065 475 149

RAVINE AND PLATEAU OPTION


S2-171026-INF-TUNNEL-GA-01-KS_[ID]
PLAN AND LONG SECTION

Figure 11: Power waterway inferred geological long section


 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.7.2   Intakes 
The   arrangement   of   the   power   waterway   incorporates   intake   structures   designed   to   suit   both 
generation   and   pumping   modes   located   at   the   end   of   the   HRT   and   TRT.   Both   intake   structures 
incorporate   an   approach   channel,   a  transition   structure   and   a  gate   structure.   The   arrangement   and 
layout   of   the   two   intake   structures   remains   consistent   for   both   the   Ravine   and   Plateau   alignment 
options. 
Tantangara   Intake 

The   Tantangara   Intake   structure   will   require   excavation   into   the   Kellys   Plain   Volcanics,   with   expected 
lithologies   based   on   drilling   results   and   published   literature   indicating   dacite   ignimbrite,   rhyodacite 
ignimbrite,   tuff,   agglomerate   (volcanic   breccia),   and   rhyolite. 

Geotechnical   drilling   at   this   location   was   undertaken   as   noted   above   and   therefore   will   not   be 
repeated   in   this   section. 
Talbingo   Intake 

The   Talbingo   intake   structure   is   located   near   the   southern   end   of   Talbingo   Reservoir   and   is   positioned 
at   the   end   of   the   TRT.   It   is   here   where   the   Yarrangobilly   River   and   Middle   Creek   flow   into   storage.   The 
Talbingo   intake   structure   is   to   be   excavated   into   Ravine   Beds   and   some   minor   sections   on   Boraig 
Group   Volcanics   depending   on   the   final   design   configuration   of   the   structure.   The   Ravine   Beds 
comprise   shale,   slate,   sandstone,   gritty   sandstone   and   conglomerate.  

Field   mapping   was   completed   both   on   foot   from   the   Lobs   Hole   Road,   and   by   boat   along   the   Talbingo 
Reservoir   shoreline.   During   the   field   mapping,   it   was   observed   that   the   intake   area   is   underlain   by 
rocks   of   the   Ravine   Beds   with   isolated   volcanic   flows   from   the   upper   Boraig   Volcanics   group.   These 
flows   resemble   fingers   of   lava   flowing   from   the   upper   parts   of   the   Boraig   Volcanics   and   towards   the 
ancient   valleys   of   the   Ravine   Beds.   These   fingers   were   observed   along   the   Talbingo   Reservoir 
shoreline   (Figure   12)   and   are   likely   to   be   less   than   3m   thick.   The   flows   predominantly   consist   of 
dacite,   rhyolite   and   some   tuff.   

At   the   intake   location,   the   Ravine   Beds   have   been   described   from   field   mapping   as   interbedded   shale, 
sandstone,   gritty   sandstone   and   conglomerate   as   an   interbedded   turbiditic   sequence.   Rock   strength 
of   the   exposed   materials   varies   from   low   to   medium   strength   on   the   more   weathered   shale   to   high   to 
very   high   strength   on   the   moderately   weathered   (or   better)   sandstone.   The   Ravine   Beds   are   typically 
folded   when   in   contact   with   dacite/rhyolite   of   the   Boraig   Group   and   are   described   as   very   high   to 
extremely   high   strength,   with   three   to   four   discontinuity   sets.  

 
Figure   12:   Photo   of   the   Talbingo   Intake   location57 

57
  Source:   SMEC   field   survey   2017. 

 
©   Snowy   Hydro   Limited   2017  Page   31   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.7.3   Headrace   tunnel 
The   HRT   alignment   would   link   the   Tantangara   intake   structure   to   the   headrace   surge   shaft.   The 
horizontal   and   vertical   alignments   would   be   predominantly   straight   with   the   length   of   the   HRT 
determined   by   the   power   cavern   complex   option   to   be   taken   forward.   As   noted   above,   drilling   is 
ongoing   with   results   from   a  majority   of   drill   holes   pending.  
Ravine   option 

For   the   Ravine   option,   it   is   envisaged   that   the   HRT   will   be   16.9km   long.   The   excavation   methods   for 
this   tunnel   include   a  tunnel­boring   machine   (T   BM )  as   the   base   case,with   drill   and   blast   (D
  &B )  as   an 
option.   The   final   decision   on   excavation   method   will   consider   many   factors   such   as   GIP   results, 
associated   excavation   ground   support   and   advance   rates,   etc.   Ground   cover   ranges   from   less   than 
40m   at   the   intake   location   to   nearly   375m   BGL   under   the   Long   Plain   Fault   at   approximately   Ch 
15,300. 

Six   ground   support   categories   are   detailed   for   both   the   TBM   and   D&B   excavated   tunnels,   depending 
on   construction   limitations.58  Table   8  shows   the   likely   rock   formations   to   be   encountered   along   the 
Ravine   option   alignment   and   the   main   geotechnical   characteristics   of   each   rock   type.  

 
Table   8:   Geotechnical   characteristics   of   likely   rock   formations   along   the   Ravine   option   alignment59 

 
   

58
  See  E
  GAR . 
59
  See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   32   of   60 
 
Snowy 2.0 Study Report - Chapter Seven - Geotechnical and seismic Commercial-in-Confidence

Chainage (m) Rock unit Estimated UCS Estimated GSI (not Groundwater condition In situ stress condition σc / σ1v Stress reduction factor
including faults)

UCS ratio to vertical


0–600 Kellys Plain Volcanics Variable high to 55 to 70 Due to shallow rock cover, of 45-65m Cover is 45 to 65m, low vertical stress, stress Based on Q system, competent rock,
(Dkv) extremely high there is expected to be groundwater possible higher horizontal stress. Allow with weak zones: could be clay in single
3
strength (ISRM); connection from the ground surface. density 0.025 MN/m weak zone
range of 80 to 200 Locally high inflows along steep joints,
MPa; likely dissipating with time. Extensive
damp and dripping zones in long term
allow 120 MPa
80-200
45m 5
50-125
65m 2.5-5
600–3,000 Tantangara Formation Variable low to high 35 to 55 Due to shallow rock cover, of 45-65m Cover is 60 to 135m, low vertical stress, Based on Q system, competent to weak
(Syn-I) strength in there is expected to be groundwater possible higher horizontal stress. Allow rock, with several weak zones; some with
3
moderately locally in weak zones at 20 connection from the ground surface. density 0.026 MN/m clay
weathered to fresh to 35 Locally high inflows along steep joints,
rock (ISRM): likely dissipating with time. Extensive
damp and dripping zones in long term
range is 20 to 100 Head (Ho) = 0.15 to 0.5 MPa 60m 12.5-65 5
MPa
No reduction at tunnel 135m 5-30 2.5-5

3,000–7,740 Tantangara Formation Variable high to 45 to 55 Locally groundwater inflows along Cover is 110m to 375m, consider rock
(Syn-I) very high strength in sheared zones, local blocky jointed cover vertical stress as greater than
fresh rock (ISRM): locally in weak zones 35 to zone would provide connections to horizontal stress. Allow density 0.026
3
40 shallow groundwater sources. In long MN/m
range is 50 to 100 term generally damp to dripping
MPa
Head (Ho) = 0.8 to 3.45 MPa 110m 17-35 2.5-5

possibly 20% reduction at tunnel 375m 5-10 1-2

500–950 2,500–2,600 Tantangara Formation Generally low to 10 to 25 Refer to unit descriptions 5-10
4,030–4,130 5,200– (Syn-II) Faulted or very low strength;
5,300 7,700–7,750 sheared material, locally 5-10 MPa locally in weak zones 5
weathered

7,740–9,850 Temperance Formation Variable high to 60 to 70 Ground conditions expected to be tight Cover is 160m to 230m, consider rock Based on Q system, competent rock with
(Oitd-I) extremely high except along contact zones with cover vertical stress as greater than local weak rock and weak zones.
strength (ISRM); locally 40 to 50 in sheared granitic intrusives and along faults. At horizontal stress. Allow density 0.027
areas these points there is expected high MN/m
3
range of 80 to 150 groundwater flows.
MPa; allow 100
MPa Head (Ho) = 1.3 to 2.0 MPa 160m 18-35 1

possibly 20% reduction at tunnel 230m 12-24 1


Refer to unit descriptions
7,750–7,800 8,800– Temperance Formation Generally low to 10 to 25 5-10
8,850 contact zones (Oitd-I) Faulted or very low strength:
50m sheared material, locally 5-10 MPa locally in weak zones 5
weathered
8,100–8,300 Intrusive rocks - Boggy Variable high to 60 to 70 Ground conditions expected to be tight, Cover is 160m to 180m, consider rock
Plains Granite I-Type extremely high except along contact zones with cover vertical stress as greater than
8,850–9,330 Suite (Dgk2-I) strength (ISRM); with locally 40 to 50 in granitic intrusives and along faults, horizontal stress. Allow density 0.026
sheared areas where high groundwater flows are MN/m
3
range of 80 to 150 expected
MPa; allow 100
MPa Head (Ho) = 1.2 to 1.5 MPa 170m 18 - 34 1

Possibly 20% reduction in tunnel

© Snowy Hydro Limited 2017


Snowy 2.0 Study Report - Chapter Seven - Geotechnical and seismic Commercial-in-Confidence

Chainage (m) Rock unit Estimated UCS Estimated GSI (not Groundwater condition In situ stress condition σc / σ1v Stress reduction factor
including faults)

8,050–8,100 8,350 – Granite unit (Dgk2-II) Generally low to 10 to 25, locally in weak Refer to unit descriptions 5-10
8,400 This allows for very low strength: zones 5
random alteration 5-10 MPa
zones
9,850–14,250 Gooandra Volcanics Expected to be high Basalt: 60 - 75 Dry with localised inflows along shears Cover is 200-400m, or up to 1,100m at
(Oigl-I) to very high (ISRM and open joints. Initial high flows likely power house cavern. General E-W
classif.); Foliated rocks: 45 - 60 to decrease with time. In low cover horizontal stress condition. Potential high
Generally 60 - 70 areas - considered moderate; in high stress condition at depth. Allow density
range is : 60 to cover areas - considered moderate to 0.027 MN/m
3
200 MPa, mostly high
>120 MPa
185m 12-40 1

275m 8-27 1-2

Head (Ho) = 1.7 to 3.7 MPa 365m 6-20 1-2.5

possibly 30% reduction in tunnel 1,100m 2-6.7 2-5

9,330–9,380 9,850– Gooandra Volcanics Generally low to 10 to 25, Refer to unit descriptions 5-10
9,900 10,700–10,800 (Oigl-I) very low strength:
5-10 MPa locally in weak zones 5
Faulted or sheared
material, locally
weathered
14,250–14,700 Shaw Hill Gabbro (Og5) Variable high to 55 to 70 Generally considered to be tight rock Cover at about 350m, consider rock
extremely high with limited groundwater effect at depth cover vertical stress as greater. Allow
locally 40 to 50 in sheared 3
strength (ISRM); density 0.027 MN/m .
areas
range of 75 to 150; Depth of cover:
allow 100 MPa.
Head (Ho) = about 3.2 MPa 350m 8-16 1-2

possibly 30% reduction in tunnel 1,100m 2.5 - 5

14,700–15,100 Long Plain Fault zone Likely low strength 10 to 15 at surface but In Eucumbene-Tumut tunnel there was Cover at about 330-360m, for base case Based on Q system: Multiple weak
at surface, but possibly 25 -35 at depth, extensive high water inflow under Project Alignment. Allow density of 0.026 zones, and possible squeezing rock
3
increasing as variable conditions pressure that dissipated with time. If MN/m . Depth of cover: under high pressure
foliation becomes depending on extent of water encountered at great depth there
tight at depth. shearing and presence of will be issues with very high pressures.
clay
Allow 30 to 60 MPa Low Cover: Head (Ho) = 3.0 to 3.3 330m 3.5-7 5-10
MPa
No reduction in tunnel
High Cover: Head (Ho) = up to 11 MPa 800m 1.4 – 2.9 2.5-50
No reduction in tunnel
15,100-16,200 Ravine Beds (Ss2-II) Outcrops low Slates: 20-30, Mixed slate Relatively low inflows, isolated sources Cover from about 200-400m. General E- Based on Q system: Multiple weak
strength, and quartz veins: 30-40, that have initial high flows likely to W horizontal stress. Medium stress zones, and possible squeezing rock
3
assume some sandstone, decrease with time. In low cover areas issues; Allow density 0.026 MN/m . under high pressure.
allow 20-60MPa overall 30-40 - considered low to moderate; in high
300m 7.7 – 26 1 – 2.5
mostly <40 MPa cover areas - considered low to high.
1,100m 2.1 - 7 5 - 100
High Cover: Head (Ho) = up to 11 MPa
No reduction in tunnel
16,200–26,300 Ravine Beds (Ss2-I) Outcrops appear to Sandstone: 50 - 70 Relatively low inflows, isolated sources Cover from about 200-400m. General E- Based on Q System: competent rock with
be high to very high that have initial high flows likely to W horizontal stress. Medium stress stress problems
Siltstone and shale: 35 - 55 decrease with time. In low cover areas

© Snowy Hydro Limited 2017


Snowy 2.0 Study Report - Chapter Seven - Geotechnical and seismic Commercial-in-Confidence

Chainage (m) Rock unit Estimated UCS Estimated GSI (not Groundwater condition In situ stress condition σc / σ1v Stress reduction factor
including faults)

3
strength (ISRM - considered low to moderate; in high issues; Allow density 0.026 MN/m .
classif.); Generally 45-60 cover areas - considered low to high Depth of cover: - Low Cover
range is : 60 to
200 MPa, mostly Head (Ho) = 3.0 to 3.3 MPa 50m 46 - 154 1
>120 MPa
possibly 10% reduction in tunnel 150m 15 - 51 1

High Cover: 800m 2.8 – 9.6 2.5 - 50


Table 8: Geotechnical conditions along the HRT - Ravine Option

© Snowy Hydro Limited 2017


 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Plateau   option 

For   the   Plateau   option,   it   is   envisaged   that   the   HRT   will   be   12.72km   long   with   excavation   either   by 
TBM   and   or   D&B.   Ground   cover   ranges   from   less   than   40m   at   the   intake   location   to   nearly   405m 
BGL. 

Table   9  shows   the   likely   rock   formations   to   be   encountered   along   the   Plateau   option   alignment   and 
the   main   geotechnical   characteristics   of   each   rock   type.   For   further   details   see   the  E
  GAR . 

 
60
Table   9:   Geotechnical   conditions   along   the   Plateau   option   alignment  

   

60
  See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   33   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
   

 
©   Snowy   Hydro   Limited   2017  Page   34   of   60 
 
Snowy 2.0 Study Report - Chapter Seven - Geotechnical and seismic Commercial-in-Confidence

Chainage (m) Rock unit Estimated UCS Estimated GSI (not Groundwater condition In situ stress condition σc / σ1v Stress reduction factor
including faults)
UCS ratio to
0 to 600 Kellys Plain Volcanics Variable high to extremely high 55 to 70 Due to shallow rock cover, of 45-65m there is Cover is 45 to 65m, low vertical vertical stress Based on Q system, competent
(Dkv) strength (ISRM); expected to be groundwater connection from the stress, and possible higher rock, with weak zones: could be
ground surface. Locally high inflows along steep horizontal stress. clay in single weak zone
range of 80 to 200 MPa; allow joints, likely dissipating with time. Extensive 3
120 MPa damp and dripping zones in long term. Allow density 0.025 MN/m
80-200
45m 5
50-125
65m 2.5-5
600 to 3,000 Tantangara Variable low to high strength in 35 to 55 Due to shallow rock cover, of 45-65m there is Cover is 60 to 135m, low vertical Based on Q system, competent
Formation (Syn-I) moderately weathered to fresh expected to be groundwater connection from the stress, and possible higher to weak rock, with several weak
rock (ISRM): locally in weak zones at 20 to ground surface. Locally high inflows along steep horizontal stress. zones; some with clay
35.
joints, likely dissipating with time. Extensive 3
range is 20 to 100 MPa damp and dripping zones in long term. Allow density 0.026 MN/m

Head (Ho) = 0.15 to 0.5 MPa 60m 15-65 5


no reduction at tunnel 135m 5-30 2.5-5
3,000 to 7,740 Tantangara Variable high to very high 45 to 55 Locally groundwater inflows along sheared Cover is 110m to 375m, consider
Formation (Syn-I) strength in fresh rock (ISRM) zones, local blocky jointed zone would provide rock cover vertical stress as greater
locally in weak zones 35 to 40
connections to shallow groundwater sources. In than horizontal stress. Allow density
range is 50 to 100 MPa long term generally damp to dripping 0.026 MN/m
3

Head (Ho) = 0.8 to 3.45 MPa 110m 17-35 2.5-5


possibly 20% reduction at tunnel 375m 5-10 1-2
500 - 950 2,500 - Tantangara Generally low to very low 10 to 25 Refer to unit descriptions 5-10
2,600 4,030-4,130 Formation (Syn-II) strength: 5-10 MPa
locally in weak zones 5
5,200-5,300 Faulted or sheared
7,700- 7,750 material, locally
weathered

7,740 to 9,850 Temperance Variable high to extremely high 60 to 70 Ground conditions expected to be tight except Cover is 160m to 230m, Based on Q system, competent
Formation (Oitd-I) strength (ISRM); along contact zones with granitic intrusives and consider rock cover vertical rock with local weak rock and
locally 40 to 50 in sheared along faults. At these points there is expected stress as greater than weak zones
range of 80 to 150 MPa; areas high groundwater flows horizontal stress. Allow
allow 100 MPa density 0.027 MN/m
3

Head (Ho) = 1.3 to 2.0 MPa 160m 18-35 1


possibly 20% reduction at tunnel 230m 12-24 1
Refer to unit descriptions
7,750 - 7,800 Temperance Generally low to very low 10 to 25 5-10
8,800 - 8,850 Formation (Oitd-I) strength: 5-10 MPa
contact zones Faulted or sheared locally in weak zones 5
50m material, locally
weathered
8,100 to 8,300 Intrusive Rocks - Variable high to extremely high 60 to 70 Ground conditions expected to be tight except Cover is 160m to 180m,
Boggy Plains Granite strength (ISRM); along contact zones with granitic intrusives and consider rock cover vertical
8,850 to 9,330 I-Type Suite (Dgk2-I) locally 40 to 50 in sheared along faults. At these points there is expected stress as greater than
range of 80 to 150 MPa; areas
high groundwater flows horizontal stress. Allow
allow 100 MPa density 0.026 MN/m
3

Head (Ho) = 1.2 to 1.5 MPa 170m 18-34 1


possibly 20% reduction in tunnel

8,050 - 8,100 Granite unit (Dgk2-II) Generally low to very low 10 to 25 Refer to unit descriptions 5-10
8,350 - 8,400 this strength: 5-10 MPa
allows for locally in weak zones 5
random
alteration zones

© Snowy Hydro Limited 2017


Snowy 2.0 Study Report - Chapter Seven - Geotechnical and seismic Commercial-in-Confidence

Chainage (m) Rock unit Estimated UCS Estimated GSI (not Groundwater condition In situ stress condition σc / σ1v Stress reduction factor
including faults)
9,850 to 14,250 Gooandra Volcanics Expected to be high to very Basalt: 60-75 Dry with localised inflows along shears and open Cover is 200-400m, or up to
(Oigl-I) high (ISRM classif.); joints. Initial high flows likely to decrease with 1,100m at power house
Foliated rocks: 45-60 time. In low cover areas - considered moderate; cavern. General E-W
range is 60 to 200 MPa, mostly in high cover areas - considered moderate to horizontal stress condition.
>120 MPa Generally 60-70
high Potential high stress
condition at depth. Allow
3
density 0.027 MN/m
185m 12-40 1
275m 8-27 1-2
Head (Ho) = 1.7 to 3.7 MPa 365m 6-20 1-2.5
1100m 2-6.7 2 -5

9,330 - 9,380 Gooandra Volcanics Generally low to very low 10 to 25, locally in weak Refer to unit descriptions 5-10
9,850 - 9,900 (Oigl-I) strength: 5-10 MPa zones 5
10,700 - 10,800
Faulted or sheared
material, locally
weathered
13,321 to 14,250 Gooandra Volcanics Expected to be high to very Basalt: 60 - 75 Dry with localised inflows along shears and open
high (ISRM classif.); joints. Initial high flows likely to decrease with
Foliated rocks: 45 - 60 time. In low cover areas - considered moderate;
range is : 60 to 200 MPa, in high cover areas - considered moderate to
Generally 60 - 70
mostly >120 MPa high
possibly 30% reduction in tunnel 1,100m 2 - 6.7 2-5
14,250 to 14,600 Shaw Hill Gabbro Variable high to extremely high 55 to 70, Generally considered to be tight rock with limited Cover at about 350m,
strength (ISRM); groundwater effect at depth consider rock cover vertical
locally 40 to 50 in sheared
stress as greater.
range of 75 to 150; allow 100 areas
3
MPa. Allow density 0.027 MN/m .
Depth of cover:
Head (Ho) = about 3.2MPa 350 8-16 1-2

possibly 30% reduction in tunnel 1100 2.5 - 5 2-5

14,600 to 15,100 Long Plain Fault Zone Likely low strength at surface, 10 to 15 at surface but In Eucumbene-Tumut tunnel there was Cover at about 330-360m, Bases on Q system: Multiple
but increasing as foliation possibly 25 -35 at depth, extensive high water inflow under pressure that for option 1 Project weak zones, and possible
becomes tight at depth. variable conditions depending dissipated with time. Alignment. Allow density of squeezing rock under high
3
on extent of shearing and 0.026 MN/m . pressure
Allow 30 to 60 MPa presence of clay If water encountered at great depth, there will be Depth of cover:
issues with very high pressures.
High Cover: 1,100 1.0 – 2.1 5 - 100
Head (Ho) = up to 11MPa
No reduction in tunnel
15,100 to 26,400 Ravine Beds Outcrops appear to be high to Sandstone: 50 - 70 Relatively low inflows, isolated sources that have Cover from about 200-400m. Based on Q System: competent
very high strength (ISRM initial high flows likely to decrease with time. rock with stress problems
Siltstone and shale: 35 - 55 General E-W horizontal
classif.);
In low cover areas - considered low to moderate; stress. Medium stress
range is : 60 to 200 MPa, Generally 45-60 issues;
in high cover areas - considered low to high
3
mostly >120 MPa Allow density 0.026 MN/m .
Depth of cover:
Low cover:

Head (Ho) = 3.0 to 3.3MPa 50m 46 - 154 1

© Snowy Hydro Limited 2017


Snowy 2.0 Study Report - Chapter Seven - Geotechnical and seismic Commercial-in-Confidence

Chainage (m) Rock unit Estimated UCS Estimated GSI (not Groundwater condition In situ stress condition σc / σ1v Stress reduction factor
including faults)
possibly 10% reduction in tunnel 150m 15 - 51 1

High cover: 300m 7.7 - 26 1 - 2.5


Head (Ho) = up to 11MPa 600m 3.8 – 12.8 2.5 - 50
possibly 20% reduction in tunnel 1,100m 2.1 – 7.0 5 - 100

Table 9: Geotechnical conditions along the HRT - Plateau Option

© Snowy Hydro Limited 2017


 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.7.4   Headrace   surge   shaft   and   gate   chamber 
The   headrace   surge   shaft   is   the   surge   attenuation   facility   for   the   HRT.   It   will   connect   the   downstream 
portion   of   the   HRT   with   three   distributor   tunnels.  

The   headrace   gate   chamber   will   provide   access   to   the   upstream   isolation   valves   providing   the   facility 
to   seal   the   HRT   and   allow   dewatering   of   the   penstocks   without   dewatering   the   entire   HRT.   The 
chamber   is   expected   to   be   excavated   by   D&B.   The   chamber   will   be   supported   by   permanent   rock 
anchors   and   shotcrete.   A  permanent   shotcrete   internal   lining   will   then   be   installed. 
Ravine   option 

The   surge   shaft   is   expected   to   be   excavated   with   a  combination   of   raise   bore   and   D&B   methods   into 
the   Ravine   Beds   with   the   upper   section   likely   to   reach   the   contact   between   the   Ravine   Beds   and 
Boraig   Volcanics.   It   is   envisaged   that   rocks   from   the   Ravine   Beds   at   this   location   will   be   steeply 
bedded   due   to   proximity   to   the   Long   Plain   Fault.   The   contact   between   the   Boraig   Group   and   Ravine 
Beds   is   likely   to   be   through   discontinuities   with   relatively   poor   to   fair   rock   conditions   at   the   contact. 

Excavation   of   a  vertical   shaft   on   steeply   bedded   sandstone   and   shale   may   produce   local   instability   on 
one   side   of   the   shaft   walls   while   the   other   side   may   be   stable.   This   is   able   to   be   addressed   with 
conventional   shaft   sinking   with   or   without   the   use   of   a  raise   bore   hole   to   assist   with   muck   removal. 
The   gate   chamber   is   expected   to   be   fully   excavated   in   rocks   from   the   Ravine   Beds.   See   Table   8  for 
predicted   geotechnical   ground   conditions   at   this   location.   The   planned   drilling   program   as   part   of   the 
GIP   will   clarify   predicted   rock   properties. 
Plateau   option 

The   headrace   surge   shaft   is   expected   to   be   excavated   into   the   Gooandra   Volcanics.   The   headrace 
surge   shaft   would   be   located   at   the   same   elevation   as   the   Ravine   option   however   further   east   than 
the   Ravine   surge   shaft.   The   Gooandra   Volcanics   has   been   described   as   a  vertically   or   near   vertically 
foliated   sequence   of   metabasalt   and   greenschist,   as   observed   in   the   preliminary   drill   hole   logs   from 
BH4101.   It   is   envisaged   that   rocks   will   be   steeply   foliated   due   to   the   proximity   with   the   Long   Plain 
Fault   and   observations   made   during   the   geological   field   mapping.  

Excavation   of   a  vertical   shaft   in   such   steeply   foliated   metabasalt   and   greenschist   units   may   produce 
local   instability   on   one   side   of   the   shaft   walls   while   the   other   side   may   be   stable.   As   with   the   Ravine 
option,   this   could   result   in   asymmetrical   stresses   on   the   shaft   rock   support.   This   is   able   to   be 
addressed   with   conventional   shaft   sinking   with   or   without   the   use   of   a  raise   bore   hole   to   assist   with 
muck   removal.   The   gate   chamber   is   expected   to   be   fully   excavated   in   rocks   from   the   Gooandra 
Volcanics.   See   Table   9 f or   the   estimated   geotechnical   ground   conditions   at   this   location.   The   planned 
drilling   program   as   part   of   the   GIP   will   clarify   predicted   rock   properties. 

3.7.5   Pressure   shafts 
Three   pressure   shafts   have   been   designed   to   convey   water   vertically,   downstream   of   the   headrace 
gate   chamber,   from   the   end   of   the   distributor   tunnels   to   the   start   of   the   high­pressure   tunnels.   The   top 
of   the   shaft   is   at   EL1106.2m   and   the   bottom   of   the   shaft   is   at   EL450.0m.   The   shafts   have   an   internal 
diameter   of   5.2m   and   will   be   concrete   lined   with   the   top   of   the   shafts   having   concrete­formed   elbows 
and   the   bottom   steel­lined   elbows   which   will   enable   both   vertical   and   horizontal   redirection   of   water. 

Assessments   for   the   predicted   ground   conditions   of   the   pressure   shafts   are   based   on   field   surface 
mapping,   published   geological   maps   and   reports.   This   assessment   will   be   further   augmented   and 
updated   based   on   the   results   from   the   ongoing   GIP. 
Ravine   option 

The   pressure   shafts   would   be   excavated   in   the   Ravine   Beds.   It   is   envisaged   that   the   Ravine   Beds   will 
be   steeply   bedded   near   the   surface   and   likely   to   be   dipping   between   30°   and   50°   from   the   horizontal 
near   the   base   of   the   pressure   shafts   and   penstock   tunnels. 

Excavation   of   a  vertical   shaft   on   steeply   bedded   sandstone   and   shale   may   produce   local   instability   on 
one   side   of   the   shaft   walls   while   the   other   side   may   be   stable.   This   could   result   in   asymmetrical 
 
©   Snowy   Hydro   Limited   2017  Page   35   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
stresses   on   the   shaft   rock   support.   This   is   able   to   be   addressed   with   conventional   shaft   sinking   with   or 
without   the   use   of   a  raise   bore   hole   to   assist   with   muck   removal.   For   predicted   geotechnical 
conditions   along   the   pressure   shafts   please   refer   to   Table   8.  T   his   assessment   will   be   further 
augmented   and   updated   based   on   the   results   from   the   ongoing   GIP. 
Plateau   option 

The   pressure   shafts   will   be   excavated   in   the   Gooandra   Volcanics   similar   to   that   described   for   the 
surge   shaft.   Excavation   of   a  vertical   shaft   in   such   steeply   foliated   metabasalt   and   greenschist   units 
may   produce   local   instability   on   one   side   of   the   shaft   walls   while   the   other   side   may   be   stable.   As   with 
the   Ravine   option,   this   could   result   in   asymmetrical   stresses   on   the   shaft   rock   support.   This   is   able   to 
be   addressed   with   conventional   shaft   sinking   with   or   without   the   use   of   a  raise   bore   hole   to   assist   with 
muck   removal.   Geotechnical   conditions   predicted   along   the   pressure   shafts   can   be   found   in   Table   9. 
This   assessment   will   be   further   augmented   and   updated   based   on   the   results   from   the   ongoing   GIP. 

3.7.6   Cavern   complex 
The   power   station   cavern   complex   is   a  collective   of   structures   including   the   Machine   hall   cavern, 
Transformer   hall   cavern,   as   well   as   high­pressure   tunnels,   penstock   tunnels,   Isolated   Phase   Busduct 
( IPB )  galleries,   draft   tube   tunnels,   cooling   water   tunnels,   auxiliary   access   tunnels   and   construction 
adits.   The   Ravine   and   Plateau   options   have   the   same   design   approach   for   the   power   station   complex 
excavation   and   rock   support. 

Figure   13   shows   a  detailed   isometric   view   of   the   interconnectivity   between   the   HRT   and   the   TRT   with 
relation   to   the   machine   hall   complex. 

Drill   holes   at   these   alternative   locations   are   pending   as   part   of   the   ongoing   GIP.   The   ground 
investigation   program   is   underway   and   current   drilling   in   this   area   includes   one   drill   hole   BH4101   in 
Gooandra   Volcanics   at   Ch13,300m   at   the   Plateau   site.   Drill   hole   BH5102   in   Ravine   Beds   at 
Ch17,000m   at   the   Ravine   site   is   in   progress   at   the   time   of   this   Report. 

 
Figure   13:   General   arrangement   of   the   power   station   cavern   complex   in   detail,   relevant   to   both   options61 

   

61
  S2­1405­DRG­018614   ­  UNDERGROUND   POWER   STATION   ­  POWER   STATION   COMPLEX   ­  GENERAL 
ARRANGEMENT   ­  ISOMETRIC   SHEET   02   (SMEC) . 

 
©   Snowy   Hydro   Limited   2017  Page   36   of   60 
 
NOTES:
1. FOR DRAWING INDEX AND GENERAL NOTES REFER TO DRAWING S2-1405-DRG-018601.

MAIN ACCESS TUNNEL MACHINE HALL DRAFT TUBE VALVE GALLERY


CONSTRUCTION ADIT ACCESS TUNNEL

PRESSURE SHAFTS

TAILRACE SURGE TANK


ACCESS TUNNEL

HIGH PRESSURE TUNNELS


EMERGENCY EGRESS, CABLE
L
H AL AND VENTILATION TUNNEL
INE
PENSTOCK CONSTRUCTION CH
MA
ADIT

PENSTOCK TUNNELS LL
HA
ER TAILRACE SURGE
O RM
SF TANK EXPANSION
AN
TRANSFORMER HALL ACCESS TUNNEL TR CHAMBER

COOLING WATER TUNNEL 2 TAILRACE SURGE TANK

IPB GALLERIES

DRAFT TUBE TUNNELS

AUXILIARY EGRESS TUNNEL

DRAFT TUBE VALVE GALLERY

DRAFT TUBE TUNNELS

COLLECTOR TUNNELS COOLING WATER TUNNEL 1

COLLECTOR TUNNEL TAILRACE TUNNEL


CONSTRUCTION ADIT
150
140
130
120
110
100
90

GENERAL ARRANGEMENT ISOMETRIC


80
150 mm ON ORIGINAL

70
60

DRAWING FILE LOCATION / NAME PLOT DATE TIME DESIGN MODEL FILE REFERENCE
17/11/2017 12:33:01 PM FEASIBILITY
50

S2-1405-MOD-014954

EXTERNAL REFERENCE FILES REV DATE AMENDMENT / REVISION DESCRIPTION WVR No APPROVAL TITLE NAME SCALES AT A1 SIZE DRAWING DESIGNER CLIENT PROJECT TITLE SNOWY 2.0
40

0 17/11/2017 FEASIBILITY DESIGN - ISSUED FOR USE WVR0102 D.E. DRAFTER J. HUNTER UNDERGROUND POWER STATION
POWER STATION COMPLEX
30

DRAFTING CHECK J. IKONEN


DESIGNER M. YEE GENERAL ARRANGEMENT
20

DESIGN CHECK A. NEUMAIER ISOMETRIC SHEET 02


10

PROJECT MANAGER D. EVANS PHASE DRAWING No. REVISION


SMEC PROJECT NO. 30012060 FEASIBILITY S2-1405-DRG-018614 0
A1

PROJECT DIRECTOR C. CLARKE


0

Figure 13: General arrangement of the power station cavern complex in detail, relevant to both options
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
The   choice   of   location   and   orientation   with   respect   to   the   prevailing   geological   conditions   is   critical.   As 
the   subsurface   geotechnical   data   is   pending   GIP   drill   hole   results,   present   predictions   for   the   potential 
site   are   based   on   surface   mapping   combined   with   historical   information   for   the   area   as   outlined   in 
Chapter   Six   of   this   Report.   The   orientation   of   large   underground   openings   depends   on   a  number   of 
factors,   including   rock   mass   conditions,   lithology,   rock   strength   properties,   geological   structures, 
groundwater   condition,   and   prevailing   in   situ   stress.   Based   on   the   existing   knowledge   of   the   predicted 
geological   conditions,   it   is   prudent   to   assess   what   may   be   the   best   and   worst   conditions   at   the   cavern 
complex   sites.  

This   section   of   the   report   describes   both   options:   Ravine   option   with   the   cavern   complex   being 
downstream   from   the   surge   shaft   site   at   about   Ch17,000m   (assumed   within   the   Ravine   Beds),   and   the 
Plateau   option   as   an   alternative   site   at   Ch12,800m   (confirmed   to   be   Gooandra   Volcanics   based   on 
drill   hole   BH4101   results).   Geotechnical   conditions   predicted   to   be   encountered   along   the   cavern 
complex   and   downstream   pressure   shafts   are   outlined   in   Table   10.   This   table   presents   an   assessment 
of   the   best   predicted   best   and   worst   case   conditions   at   both   potential   power   station   complex   locations 
based   on   available   information   and   knowledge.  
Ravine   option 

The   machine   hall   cavern   would   have   a  length   of   173.5m,   width   of   32.8m   and   a  height   of   55.4m   with 
the   cavern   oriented   135°   from   north   to   minimise   kinematic   instability   and   overbreak.   The   transformer 
hall   cavern   with   the   same   orientation   as   the   machine   hall   cavern,   would   have   a  length   of   180.6m, 
width   of   23.2m   and   a  height   of   43.6m.   It   is   envisaged   that   the   cavern   complex   and   the   downstream 
surge   shaft   are   to   be   excavated   by   a  combination   of   D&B   and   raise   boring   in   the   Ravine   Beds   at 
depths   up   to   800m   BGL. 
Plateau   option 

The   machine   hall   cavern   would   have   a  length   of   173.5m,   width   of   26.5m   and   a  height   of   54.7m   with 
an   orientation   of   135°.   The   transformer   hall   cavern   would   have   a  length   of   173.5m,   width   of   19.5m 
and   a  height   of   44.5m.   It   is   envisaged   that   the   cavern   complex   and   the   downstream   surge   shaft   for 
the   Plateau   option   would   be   excavated   by   a  combination   of   D&B   combined   with   raise   boring   in   the 
Gooandra   Volcanics   at   depths   up   to   1,050   m  BGL. 

 
Figure   14:   Comparison   of   predicted   geotechnical   conditions   for   alternative   power   cavern   locations 

 
©   Snowy   Hydro   Limited   2017  Page   37   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.7.7   Tailrace   tunnel 
The   TRT   alignment   will   link   the   tailrace   surge   shaft   (located   downstream   of   the   power   station 
complex)   to   the   Talbingo   intake.   The   horizontal   and   vertical   alignments   will   be   predominantly   straight. 
The   expected   excavation   method   options   include   TBM   and   drill   &  blast.   Both   options   have   been 
considered   with   regard   to   the   predicted   ground   conditions.   Following   results   of   the   ongoing   GIP   the 
excavation   method   is   expected   to   be   refined   and   further   optimised. 
Ravine   option 

The   Ravine   option   TRT   is   anticipated   to   have   an   a  total   length   of   approximately   9.0km   and   excavated 
in   sedimentary   rocks   of   the   Ravine   Beds.   Ground   cover   ranges   from   less   than   100m   at   the   intake 
location   to   nearly   800m   BGL   at   around   Ch17,100m.   Refer   to   Table   8  for   a  summary   of   predicted 
geotechnical   conditions   at   this   location. 
Plateau   option 

The   TRT   for   the   Plateau   option   is   anticipated   to   have   total   length   of   approximately   13.1km.   Ground 
cover   ranges   from   less   than   100m   at   the   Talbingo   intake   location   to   nearly   1,063m   BGL   at 
approximately   Ch13,600m.   The   Plateau   option   TRT   is   likely   to   be   excavated   in   rocks   of   the   Gooandra 
Volcanics,   Shaw   Hill   Gabbro,   Long   Plain   Fault,   and   from   approximately   Ch13,800m   in   the   Ravine 
Beds.   Refer   to   Table   9  for   a  summary   of   predicted   geotechnical   conditions   at   this   location. 

3.7.8   Access   tunnels   to   the   cavern   complex 
Main   access   tunnel 

The   Main   Access   Tunnel   (M  AT )  alignment   will   link   the   Plateau   area   west   of   the   Snowy   Mountains 
Highway   to   the   power   station   complex.   Drill   holes   at   this   location   are   pending   as   part   of   the   ongoing 
GIP.  
Ravine   option 

The   MAT   is   an   access   tunnel   approximately   6.55km   long.   The   tunnel   portal   (1,191m   Relative   Level 
( RL )  is   located   west   of   the   Long   Plain   Fault   and   along   the   Yarrangobilly   escarpment.   The   tunnel 
ramps   down   to   the   cavern   complex   at   RL457m.   The   tunnel   portal   is   expected   to   be   excavated   in 
residual   materials   and   extremely   to   highly   weathered   rocks   from   the   Byron   Range   Group   with   these 
rocks   extending   for   about   the   first   150m   to   200m   of   the   MAT.   From   Ch200m   to   approximately 
Ch600m,   the   MAT   is   expected   to   be   excavated   in   rocks   of   the   Boraig   Group. 

At   the   MAT   location,   the   Byron   Range   Group   unconformably   lies   on   top   of   the   Boraig   Group   which   sits 
unconformably   above   the   Ravine   Beds.   The   exact   interaction   and   thicknesses   between   these   three 
rock   formations   at   this   location   is   currently   unknown,   as   are   the   ground   conditions   along   the   contacts 
between   formations,   but   will   be   investigated   as   part   of   the   ongoing   GIP.    The   basal   formation   of   the 
Byron   Range   Group   is   described   as   a  pebbly   sandstone   and   volcanic   sandstone   of   medium   to   high 
strength.   The   bedding   dips   steeply   to   the   south­southwest.  

The   Boraig   Group   west   of   the   Yarrangobilly   River   is   described   as   an   alternating   sequence   of   steeply 
inclined   shale,   conglomerates   and   volcaniclastic   rocks   with   dacite   and   rhyolite   bodies.   The   unit   is 
generally   well   jointed   with   at   least   four   joint   sets.   Outcropping   shales   and   conglomerate   are   low   to 
medium   strength,   while   tuff   and   ignimbrites   are   typically   deeply   weathered   and   very   low   strength   with 
soil­like   properties.   Dacite   and   rhyolite   outcrops   are   described   as   very   high   strength   with   very   shallow 
weathering.  
Plateau   option 

The   MAT   portal   for   the   Plateau   option   is   situated   on   Bullocks   Hill   Fire   Trail   within   the   Temperance 
Formation   to   the   east   of   the   Kiandra   Fault.   The   MAT   will   be   approximately   7.5km   in   length. 

The   initial   450m   of   the   tunnel   is   expected   to   be   in   basaltic   tuffs   and   cherts   belonging   to   the 
Temperance   Formation   to   the   east   of   Tantangara   Creek.   For   the   remaining   tunnel   length,   the   geology 

 
©   Snowy   Hydro   Limited   2017  Page   38   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
is   anticipated   to   be   all   in   Gooandra   Volcanics,   as   a  vertical   or   near   vertical   sequence   of   metabasalt 
and   greenschist.   The   exact   thickness   of   the   Tertiary   basalt   will   be   updated   based   on   GIP   results. 
Emergency,   cable   and   ventilation   tunnel   (ECVT) 

The   preliminary   design   of   the   ECVT   tunnel   alignment   links   the   power   station   complex   with   Ravine   in 
an   east­west   direction.  
Ravine   option 

The   ECVT   for   the   Ravine   option   will   be   4.55km   in   length   with   a  gradient   of   5.5%.   This   feature   will 
extend   from   Ravine   to   the   power   station   complex   with   depth   of   cover   varying   between   10m   at   the 
portal   to   740m   at   the   power   station   complex. 

The   majority   of   the   ECVT   will   be   excavated   in   the   Ravine   Beds   at   low   to   high   cover   ground   conditions. 
Geotechnical   conditions   likely   to   be   encountered   along   the   cavern   complex   and   downstream   pressure 
shafts   are   described   in   Table   8.   Data   gathered   during   the   field   mapping   indicates   that   the   tunnel   portal 
is   envisaged   to   be   excavated   in   slope   scree   /  colluvium   material.   This   material   is   expected   to   be   less 
than   10m   thick. 
Plateau   option 

The   ECVT   will   be   8.75km   in   length   with   a  grade   of   5.5%.   Commencing   in   Ravine   Beds   near 
Yarrangobilly   River,   the   ECVT   will   continue   in   an   west   ­  east   direction   intercepting   the   Long   Plain   Fault 
at   a  depth   of   500m   BGL.   The   approximate   chainages   are   Ch   6,570m   to   Ch7,000m   before   terminating 
in   the   Gooandra   Volcanics   power   cavern   with   an   invert   level   of   ~RL468m. 

Geotechnical   conditions   predicted   along   the   ECVT   are   described   in   Table   9.  
Access   roads 

Upgrades   to   existing   tracks   and   new   roads   are   required   to   provide   access   to   the   main   civil   works 
infrastructure   such   as   the   Tantangara   and   Talbingo   intake   structures   and   the   underground   power 
station   complex.   In   addition,   temporary   roads   are   required   to   provide   access   for   site   investigations, 
construction   camps,   quarries   and   spoil   disposal   sites. 

A   preliminary   geotechnical   assessment   has   been   undertaken   through   desktop   assessment   and   field 
mapping   to   evaluate   the   terrain   of   existing   tracks   for   their   applicability   for   upgrade   or   additional 
treatments.   Examples   of   items   to   assess   include: 

1. Slope   grade   for   access   by   large   vehicles; 
2.  R
  ealignment   potential   or   suitable   grades   for   cut/fill   works   to   reduce   existing   grades; 
3.  S
  mall  r  adius   horizontal   curves   required   for   widening   to   provide   access   for   oversized   vehicles; 
and 
4. Cut   and   fill   slopes   will   be   assessed   for   stability   during   further   design   development   and 
treatments   designed   where   required. 

The   following   sections   describe   the   main   geological   conditions   of   each   access   roads   depicted   in   the 
figure   below   and   any   primary   geotechnical   issues   requiring   further   assessment.   Further   site 
inspections   are   planned   for   Access   Roads   4­7.  

 
Figure   15:   Access   road   locations62 

62
  S2­1407­DRG­019005   ­  ACCESS   ROADS   OVERALL   PLAN   (SMEC) .  Shown   for   Ravine   option   only,   with   similar   completed 
for   Plateau   option   but   excluded   due   to   significant   duplication   of   information. 

 
©   Snowy   Hydro   Limited   2017  Page   39   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
   

 
©   Snowy   Hydro   Limited   2017  Page   40   of   60 
 
FEASIBILITY

SMEC PROJECT No. 30012060

Figure 15: Access road locations


 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Some   of   the   major   geotechnical   challenges   considered   include   slope   stability   for   cuts,   rippability   of   the 
less   weathered   rocks   and   managing   boggy   ground/drainage   in   the   lower   lying   areas   of   the   access 
road.   These   challenges   are   being   addressed   with   a  combination   of   GIP   and   further   refinement   of   the 
engineering.   See  C   hapter   Nine   ­  Facilities   for   detail   on   location,   access   road   assessment   and   design.  
Access   Road   1 

Access   Road   1  (6.2km)   is   planned   to   connect   Elliot   Way   to   the   Ravine   area   via   O’Hares   Track   and   by 
crossing   O’Hares   Creek.   Access   Road   1  gradually   ascends   the   northern   flank   of   the   valley   in   order   to 
gain   elevation.   The   geological   assessment   is   based   on   a  range   of   data   sources.   The   main 
geotechnical   challenges   include   slope   stability   for   cuts   and   cut/fill   sections   of   road   on   steeply   sloping 
ground,   and   rippability   of   less   weathered   rocks.   These   will   be   addressed   through   the   engineering 
process.   Drainage   and   the   potential   for   flooding   is   considered   in   the   design   since   the   access   road   will 
be   adjacent   to   O’Hares   Creek. 
Access   Road   2 

Access   Road   2  (14.7km)   is   planned   to   upgrade   the   length   between   Lobs   Hole   Ravine   Road   from   Link 
Road   to   the   Ravine   area   where   the   route   continues   north   towards   Lobs   Hole.   In   general,   the   route 
descends   680m   in   elevation   from   RL1,350m   to   RL670m. 

The   alignment   crosses   numerous   geological   units,   commencing   in   the   (poorly   exposed)   Tertiary 
basalts,   followed   by   the   very   poorly   exposed   Mountain   Creek   Volcanics   and   Byron   Range   Group.   The 
Byron   Range   Group   presents   as   low   to   medium   strength   /  splintery   shale   with   some   siltstone,   high 
strength   limestone   and   high   strength   sandstone   /  gritstone   with   minor   siltstone   and   conglomerate 
deposits. 

Steeply   sloping   basalt   boulder   fields   are   located   from   Ch7,500m   to   Ch8,850m.   The   basalt   boulders 
are   angular,   100mm   to   500mm   in   diameter,   very   high   strength,   and   estimated   to   be   2  to   4m   thick. 
From   Ch11,100m   to   Ch13,000m   ­  cut/fill   road   widening   techniques   may   be   challenging   in   this   section 
of   road   due   to   the   steeper   slopes.   The   geology   is   generally   high   strength   limestone   passing   into   high 
strength   siltstone   with   cut   slope   angles   of   45­65°   possibly   being   achieved.   Further   refinement   will 
utilise   results   from   the   ongoing   GIP. 
Access   Road   3A 

Access   Road   3A   (2.9km)   would   align   generally   west   to   east,   connecting   Access   Road   3B   to   the 
ECVT.   The   route   begins   in   Lobs   Hole   following   the   Yarrangobilly   River   upstream   to   Wallaces   Creek. 

The   alignment   of   Access   Road   3A   generally   follows   the   contact   between   the   Byron   Range   Group   and 
Ravine   Beds.   The   Byron   Range   Group   was   assessed   during   the   site   work   to   generally   be   interbedded 
conglomerate,   sandstone,   and   shale   in   nature.   Above   the   Yarrangobilly   River   a  significant   amount   of 
colluvium   was   observed. 

Drainage   was   the   primary   geotechnical   issue   observed   along   Access   Road   3A   with   wet   subgrade, 
deep   channel   incision   and   thick   colluvium   posing   less   significant   issues   to   address.  
Access   Road   3B 

Access   Road   3B   (7.3km)   connects   Talbingo   Reservoir   to   Ravine   Road.   This   road   is   planned   to   cross 
two   geological   units:   the   Byron   Range   Group   and   Ravine   Beds.   The   Byron   Range   Group   along   the 
alignment   of   Access   Road   3B   can   generally   be   classified   as   low   to   medium   strength   shale,   and 
splintery   shale   with   some   siltstone.   Cut   slope   angles   of   45­65°   should   be   achievable   with   easy   to   hard 
ripping   anticipated.   The   Ravine   Beds   along   this   road   alignment   generally   comprise   siltstone   with 
some   sandstone   which   may   be   difficult   to   excavate,   presenting   easy   to   hard   ripping.   Slope   angles   of 
45­65°   should   be   achievable. 

Thick   layers   of   colluvium,   comprising   silty   sand   with   gravel   and   cobbles,   were   observed,   along   with 
extremely   steep   terrain   where   Ravine   Beds   geological   conditions   are   considered   to   be   unfavourable. 
Wedge   and   toppling   and   planar   failures   could   be   possible.   Scouring   was   noted   on   the   steep 
downslope   (45°)   of   the   track   and   a  localised   rockfall   was   observed   in   the   Ravine   Beds   on   the   upslope 

 
©   Snowy   Hydro   Limited   2017  Page   41   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
side   of   the   existing   track.   As   the   proposed   track   passes   close   to   the   Yarrangobilly   River,   this   area   may 
be   prone   to   flooding   during   heavy   rain   events   and   is   considered   in   the   design. 
Access   Road   3C 

Access   Road   3C   (18.0km)   is   planned   to   connect   the   Snowy   Mountains   Highway   to   the   Talbingo 
Reservoir   area,   aligning   north   to   south.   In   general,   the   route   falls   485m   in   elevation,   from   RL1,095m 
to   RL610m. 

From   Ch0m   to   Ch3,850m   and   Ch17,150m   to   Ch18,800m,  t he   route   is   underlain   by   rocks   from   the 
Ravine   Beds   comprising   sandstone,   siltstone,   conglomerate   and   shale.   Between   Ch3,850m   and 
Ch17,150m   the   route   is   underlain   by   rocks   from   the   Boraig   Group   comprising   rhyodacite,   tuff,   lapilli 
tuff,   feldspathic   sandstone   and   granophyre. 

The   following   key   areas   have   been   identified   with   further   refinement   proposed   as   part   of   the   standard 
engineering   process: 

1.  L
  ava   flows   (visible   and   possibly   buried)   ­  such   material   may   prove   slow   to   excavate,   and 
require   ripping   and   localised   breaking/blasting,   but   also   prove   useful   as   high   quality   fill. 
Further   work   to   assess   excavatability   is   advised.   Batter   angles   of   65°   may   be   achievable; 
2. Volcaniclastic   material   within   the   Boraig   Group   ­  due   to   the   chaotic   nature   of   deposition, 
these   materials   are   likely   to   vary   considerably   over   small   distances,   complicating   design   and 
construction.   Safe   batter   angles   will   vary   widely   from   26°   (low   quality   tuff)   to   65°   (sandstone). 
Excavation   by   digging,   ripping   and   localised   breaking   is   possible.   Detailed   mapping   of   the 
deposit   is   advisable; 
3. Colluvium,   residual   soil   and   highly   weathered   material   of   poor   consistency   ­  in 
combination   with   steep   slopes   may   lead   to   difficulties   in   achieving   satisfactory   batter   angles 
such   as   3H:1V   to   2H:1V   and   may   involve   significant   earthworks;   and 
4. Ravine   Beds   ­  have   been   observed   as   performing   well   when   cut   at   45°,   with   a  tolerable 
amount   of   spalling/weathering.   Where   bedding   and   joints   are   well   oriented,   steeper   65°   slope 
angles   may   be   achievable. 
Other   access   roads 

Further   site   investigations   are   planned   for   Access   Roads   4,   5,   6  and   7.   It   is   expected   that   these   roads, 
will   have   similar   geotechnical   challenges   to   most   of   the   other   roads   in   this   Project.   These   challenges 
include   slope   stability   for   cuts,   rippability   of   the   less   weathered   roads   and   managing   boggy   ground. 
These   aspects   can   all   be   addressed   as   part   of   standard   and   typical   engineering   process.   Other 
similar   roads   have   been   constructed   previously   in   the   Scheme   and   learnings   from   that   experience 
combined   with   road   maintenance   since   the   construction   will   also   be   utilised. 

3.8   Seismicity 
3.8.1   Seismo­tectonics   of   southeastern   Australia 
The   Seismology   Research   Centre   (S
  RC )  Review   of   Seismicity   for   the   Snowy   Mountain   Dams   ­ 
Guthega,   Island   Bend,   Eucumbene   and   Tantangara,63  describes   the   tectonic   model   of   the   area   as 
showing  
an   area   of   high   activity   north   of   Canberra.   Other   areas   of   high   activity   include   reservoir   induced 
seismicity   at   Talbingo   Dam,   and   the   long­term   activity   between   Eucumbene   and   Jindabyne. 
The   report   also   highlights   that  
apart   from   these   clusters,   the   earthquake   distribution   in   the   Snowy   Mountains   area   does   not   show   any 
obvious   pattern.   There   does   not   appear   to   be   any   convincing   geological   evidence   to   constrain   the 
current   earthquake   activity   to   particular   faults. 

63
  Gutteridge,   Haskins   &  Davey,   (1996)   (reference   411/14296/00,   Brian   Forbes)   and   the   Hydro­electric   Commission.   Reference: 
Tony   Morse.  

 
©   Snowy   Hydro   Limited   2017  Page   42   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Most   earthquakes   in   the   Snowy   Mountains   are   very   shallow,   less   than   15km   deep   and   cause   strong 
ground   shaking   in   the   epicentral   region. 

Australia’s   tectonic   situation   is   one   of   entirely   intraplate   crustal   area   (McCue   1999).   In   the   last   100 
years   there   have   been   20   earthquakes   of   magnitude   6  or   more.   The   two   most   damaging   earthquakes 
were   in   1989   (Newcastle)   and   1954   (Adelaide).   The   magnitude   5.3   earthquake   that   occurred   at 
Berridale   on   18   May   1959   is   a  notable   event   in   the   region. 

Moye   et   al.   (1954)   commented   that   the   Snowy   Mountains   area   is   traversed   by   many   faults.   The   rock 
is   usually   crushed   in   zones   of   varying   width   along   the   fractures,   and   is   often   more   closely   jointed   than 
normal   adjacent   to   them. 

3.8.2   Seismic   hazard   classification 
Seismic   hazards   are   measured   in   Australia   by   Geoscience   Australia   which   produces   a  seismic   hazard 
classification   map   (see   Figure   16).   An   assessment   of   the   Project   Area   in   Figure   16   shows   the   peak 
ground   acceleration   (maximum   shaking   of   the   ground   at   a  location)   from   an   earthquake   with   an 
annual   exceedance   probability   of   1  in   500   (that   is,   a  return   period   of   500   years)   is   0.06­0.07g. 

 
Figure   16:   Seismic   hazard   Classification   Map64 

3.8.3   Potential   for   active   faults 
It   is   challenging   to   identify   faults   in   low   seismicity   regions   where   long­term   fault   movement   rates   could 
be   similar   to   local   erosion   and   sediment   deposition   rates.   The   length   of   the   fault   involved   in   generating 
small   magnitude   events   is   ~100m   long,   and   does   not   necessarily   have   related   surface   features.   The 
primary   faults   in   the   Project   Area   are   the   Long   Plain   Fault,   Kiandra   Fault   and   Boggy   Plain   Fault.   There 
are   also   minor   faults   intersecting   the   Project   alignment.   Figure   17   shows   earthquake   distribution 
around   the   Project   Area. 
Sharp   (2004)   indicated   some   neotectonic   features   where   a  thrust   of   older   rocks   over   alluvium   was 
observed   on   a  fault   near   Khancoban   that   may   be   part   of   the   western   margin   of   the   uplifted   Kosciusko 
block.   Given   that   the   faulting   has   displaced   alluvium   of   presumed   Quaternary   age   there   could   have 
been   fault   displacement   during   the   past   1Ma.   In   the   Project   area   there   is   likely   evidence   for 
Cenozoic­age   fault   movements   from   perhaps   20­25Ma   ago.  

64
  See   http://ecat.ga.gov.au/geonetwork/srv/eng. 

 
©   Snowy   Hydro   Limited   2017  Page   43   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Lambeck   et   al   (1984),65  propose   that   present­day   seismicity   does   not   exhibit   any   clear   relation   with 
the   continental   topography.   In   addition,   there   is   no   clear   correlation   with   geologic   or   tectonic   structure; 
however,   some   generalisations   can   still   be   made: 
1. Seismic   events   >  Magnitude   3  are   distributed   uniformly   throughout   much   of   the   Lachlan   Fold 
Orogen; 
2. However,   there   is   a  seismically   quiet   zone   to   the   east   of   the   southern   Dividing   Range   (below 
Eucumbene   Reservoir); 
3. Seismic   events   less   than   Magnitude   3  have   a  very   similar   geographic   distribution   to   the   larger 
earthquakes.   Some   smaller   seismic   events   represent   aftershocks   following   large 
earthquakes; 
4. There   is   no   real   correlation   between   seismicity   and   known   faults   in   the   Snowy   Mountains, 
apart   from   higher   seismic   activity   correlates   with   known   higher   concentrations   of   faults   are 
mapped;   and 
5. It   is   theorised   that   much   of   the   activity   occurs   on   or   at   the   edges   of   the   abundant   granite 
intrusions   in   the   Lachlan   Fold   Belt   (Cleary   1967).66 
Figure   17   indicates   the   local   historical   earthquake   distribution. 

 
Figure   17:   Distribution   of   earthquakes   and   mapped   faults   near   the   Project   location67 

65
Lambeck,   K.   et   al.,   1984.   The   state   of   stress   within   the   Australian   continent.  A
  nnales   Geophysicae ,  2(6),   pp.723–742. 
Available   at:   http://people.rses.anu.edu.au/lambeck_k/pdf/95.pdf   [Accessed   November   17,   2017]. 
66
  Cleary,   J.R.,   1967.   The   seismicity   of   the   Gunning   and   surrounding   areas,   1958–1961.  J  ournal   of   the   Geological   Society   of 
Australia ,  14(1),   pp.23–29.   Available   at:   http://dx.doi.org/10.1080/00167616708728641. 
67
  Lambeck   et   al,   Figure   2c),   p.728. 

 
©   Snowy   Hydro   Limited   2017  Page   44   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
3.8.4   Maximum   credible   earthquake 
The   literature   reviewed   for   this   chapter   does   not   conclusively   rule   out   the   occurrence   of   seismic 
events   in   the   future,   nor   can   the   potential   size   of   future   earthquakes   be   accurately   predicted.  

The   Maximum   Credible   Earthquake   (M   CE )  is   defined   by   the   Australian   National   Committee   on   Large 
Dams   (A
  NCOLD )  guidelines   as   ‘the   largest   reasonably   conceivable   earthquake   magnitude   that   is 
considered   possible   along   a  recognised   fault   or   within   a  derived   tectonic   province’.68  The   earthquake 
hazard   in   the   Snowy   Mountains   Area   is   just   above   average   for   eastern   Australia.  

ANCOLD   guidelines   suggest   that   the   MCE   could   be   in   the   order   of   magnitude   7.5­8.0.   This   estimate 
can   be   derived   by   either   deterministic   analysis   or   by   a  risk­based   analysis.   The   risk­based   analysis 
approach   is   preferred   when   following   the   ANCOLD   guidelines. 

3.8.5   Induced   seismicity 
The   SRC   Review   of   Seismicity   for   the   Snowy   Mountains   dams   (1996),   Lambeck   et   al.   (1984)   and 
Muirhead   (1981)69  all   support   the   theory   that   the   activity   hotspot   under   Talbingo   Reservoir   is   assumed 
to   be   reservoir   induced.   As   the   reservoir   was   filled   over   20   years   ago   it   is   believed   that   stress   and 
pore   water   pressure   will   have   stabilised   and   the   probability   of   further   events   in   the   area   is   no   higher 
than   the   background   level   of   the   surrounding   area. 
3.8.6   Seismicity   monitoring 
Snowy   Hydro   presently   has   existing   seismic   monitoring   instrument   installation   in   Power   Stations   at 
Wambrook,   Murray   2  Dam,   and   Tumut   Pond   Dam.   The   system   detects   seismic   activity   that   has 
potential   to   cause   damaging   energy   within   the   Snowy   Mountains   region.   As   part   of   the   risk   mitigation 
process,   an   earthquake   monitoring   and   alarm   service   is   provided   by   the   SRC   at   Environmental 
Systems   and   Services   (E  S&S )  (a   Melbourne­based   company   who   specialise   in   earthquake   studies 
and   seismic   monitoring).  

Data   is   monitored   by   the   SRC   and   for   each   seismic   event,   the   SRC   utilises   the   information   to   estimate 
intensities.   Based   on   intensities,   response   actions   following   an   earthquake   are   identified   in   Standard 
Response   Practice   documents.   This   existing   system   would   be   augmented   to   include   the   Project   and 
for   earthquakes,   Standard   Response   Practices   would   be   augmented. 

3.9   Ground   characterisation   ­  results 
Each   of   the   main   rock   units   encountered   along   the   Project   alignment   was   assessed   based   on   the 
available   geological   data   presented   in   the  E  GAR   and   assigned   a  GSI   grouping,   intact   strength   and 
overburden   situation.   Based   on   these   predictions,   schematic   block   diagrams   were   generated   for   the 
main   tunnels   with   excavated   cross   sections   covering   both   the   D&B   profile   (horseshoe   shape)   along 
with   the   TBM   (circular   shape).  

The   main   rock   units   are   illustrated   in   general   terms   in   Figures   18   to   21.   The   general   behaviour   of   the 
rock   mass   will   not   alter   greatly   if   the   tunnel   dimensions   are   slightly   adjusted.   The   selection   of   sections 
that   would   be   tunnelled   either   by   D&B   or   TBM   or   some   combination   are   based   on   current   design 
information. 

68
  ANCOLD,   1998.  G   uidelines   on   Design   of   Dams   for   Earthquake . 
69
  Muirhead,   K.J.,   1981.   Seismicity   induced   by   the   filling   of   the   Talbingo   reservoir.  J  ournal   of   the   Geological   Society   of   Australia , 
28(3–4),   pp.291–298.   Available   at:   http://dx.doi.org/10.1080/00167618108729168. 

 
©   Snowy   Hydro   Limited   2017  Page   45   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   18:   Summary   block   diagrams   for   Kellys   Plain   Volcanics   and   Tantangara   Formation70 

70
  See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   46   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
71
Figure   19:   Summary   block   diagrams   for   Boggy   Plain   Fault   and   Gooandra   Volcanics   (east   side)  

71
   See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   47   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   20:   Summary   block   diagrams   for   Gooandra   Volcanics   (west   side)   and   Long   Plain   Fault72 

72
    See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   48   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   21:   Summary   block   diagrams   of   Ravine   Beds   (proximal   and   distal   to   Long   Plain   Fault)73 

3.10   Rock   mass   characteristics   ­  predicted 
The   results   of   the   rock   mass   characterisation   assessment   and   detailed   predicted   parameters   are 
presented   in   the  E   GAR .  At   present   the   underground   conditions   are   predicted   from   the   surface 

73
    See  E
  GAR . 

 
©   Snowy   Hydro   Limited   2017  Page   49   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
mapping   and   regional   geology   as   outlined   in  C   hapter   Six  o
  f   this   Report.   This   level   of   information   is   not 
sufficient   for   final   design   and   optimisation   of   the   project.   The   GIP   has   been   developed   to   provide   the 
confirmation   of   underground   conditions   through   a  combination   of   drilling,   testing,   and   monitoring   of 
rock   and   water   properties.   Therefore   the   following   predictions   should   be   considered   as   preliminary 
only,   with   this   information   to   be   updated   based   on   the   ongoing   results   of   the   GIP   program.   Figures   22 
to   27   illustrate   the   predicted   conditions   at   depth   along   the   tunnel   alignment   starting   at   the   Tantangara 
Intake.   This   set   of   figures   is   for   the   Ravine   base   case   option.   It   has   also   been   completed   for   the 
Plateau   option   but   excluded   in   this   summary   due   to   duplication   of   geotechnical   information. 

 
Figure   22:   Geology   and   anticipated   ground   conditions   starting   at   Tantangara   Intake   (left   side   of   dwg)   for 
the   Ravine   option74 

Figure   23:   Geology   and   anticipated   ground   conditions   along   HRT   of   Ravine   option75 

Figure   24:   Geology   and   anticipated   ground   conditions   at   power   station   complex   location   for   Ravine 
option76 

Figure   25:   Geology   and   anticipated   ground   conditions   for   TRT   of   Ravine   option77 

Figure   26:   Geology   and   anticipated   ground   conditions   for   MAT   of   Ravine   option78 

Figure   27:   Geology   and   anticipated   ground   conditions   for   ECVT   of   Ravine   option79 

   

74
 S  2­0602­DRG­012216   GEOLOGY   AND   TERRAIN   ­  POWER   WATERWAY   TUNNEL   ­  INTERPRETED   GEOLOGY   LONG 
SECTION   ­  SHEET   01   (SMEC). 
75
 S  2­0602­DRG­012217   GEOLOGY   AND   TERRAIN   ­  POWER   WATERWAY   TUNNEL   ­  INTERPRETED   GEOLOGY   LONG 
SECTION   ­  SHEET   02   (SMEC) . 
76
 S  2­0602­DRG­012218   GEOLOGY   AND   TERRAIN   ­  POWER   WATERWAY   TUNNEL   ­  INTERPRETED   GEOLOGY   LONG 
SECTION   ­  SHEET   03   (SMEC). 
77
 S  2­0602­DRG­012219   GEOLOGY   AND   TERRAIN   ­  POWER   WATERWAY   TUNNEL   ­  INTERPRETED   GEOLOGY   LONG 
SECTION   SHEET   04   (SMEC) . 
78
  S2­0602­DRG­012221   GEOLOGY   AND   TERRAIN   ­  MAT   ­  PLAN   AND   INTERPRETED   GEOLOGY   LONG   SECTION 
(SMEC). 
79
 S  2­0602­DRG­012226   GEOLOGY   AND   TERRAIN   ­  ECVT   ­  PLAN   AND   INTERPRETED   GEOLOGY   LONG   SECTION 
(SMEC) . 

 
©   Snowy   Hydro   Limited   2017  Page   50   of   60 
 
FEASIBILITY

SMEC PROJECT No. 30012060

Figure 22: Geology and anticipated ground conditions starting at Tantangara Intake (left side of dwg) for the Ravine option
FEASIBILITY

SMEC PROJECT No. 30012060

Figure 23: Geology and anticipated ground conditions along HRT of Ravine option
FEASIBILITY

SMEC PROJECT No. 30012060

Figure 24: Geology and anticipated ground conditions at power station complex location for Ravine option
FEASIBILITY

SMEC PROJECT No. 30012060

Figure 25: Geology and anticipated ground conditions for TRT of Ravine option
FEASIBILITY

SMEC PROJECT No. 30012060

Figure 26: Geology and anticipated ground conditions for MAT of Ravine option
FEASIBILITY

SMEC PROJECT No. 30012060

Figure 27: Geology and anticipated ground conditions for EVCT of Ravine option
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

4   Underground   geotechnical   investigation 

In   general,   the   underground   power   station   complex   designed   for   both   the   Ravine   and   Plateau   options 
consists   of   many   large   excavations.   Design   and   construction   of   excavations   of   this   size   and 
complexity   are   highly   dependent   on   the   rock   properties   and   structural   geology   of   the   potential 
locations.   The   existing   GIP   has   been   described   in   earlier   portions   of   this   chapter   and   is   largely   a 
surface   based   program   that   utilises   deep   drill   holes   to   access   the   depths   of   the   proposed   excavations.  

This   approach   is   appropriate   for   determining   first   stage   information   on   a  broad   level   but   does   have 
limitations.   Some   of   the   limitations   with   this   approach   include   (for   example)   when   the   targets   are   deep 
the   drilling   process   is   long   and   measurements   for   factors   such   as   in   situ   stress   are   further   complicated 
and   sometimes   not   possible.   Other   limitations   include   the   orientation   of   drill   holes   that   are   typically 
vertical   with   a  possible   variation   angle   of   ±20   degrees.   This   lack   of   horizontal   holes   limits   the   level   of 
detail   possible   when   attempting   to   define   vertical   tending   structures.   Based   on   the   complex   geology 
for   these   two   possible   power   station   complex   options   as   described   in  C   hapter   Six   of   this   Report,   it   is 
expected   that   underground   investigations   of   some   form   will   be   needed   before   final   detail   design   of   the 
selected   power   station   complex   location   is   possible. 

Until   the   drill   holes   and   testing   associated   with   the   two   possible   power   station   complex   locations   are 
completed,   it   is   not   possible   to   define   in   detail   what   would   be   appropriate   for   the   underground   phase 
of   the   GIP.   That   being   said,   there   are   many   hydro   power   stations   previously   constructed   around   the 
world   that   have   also   had   to   overcome   the   challenges   of   collecting   the   information   needed   to   enable 
the   appropriate   design   and   construction   methodology   in   deep   and   geotechnically   challenging 
locations.   Some   of   these   underground   geotechnical   investigation   programs   examples   are   described 
below   for   Dinorwic   (Wales),   and   also   Snowy   Hydro   Tumut   1  and   Tumut   2.  
 
The   site   geology   of   the   Dinorwic   Power   Station   in   Northern   Wales   as   outlined   by   Douglas,   Richards 
and   Arthur   1979,80  was   identified   as   slates   of   the   Cambrian   series   with   dolerite   intrusions.   A  surface 
investigation   program   was   conducted   with   significant   data   collection   and   analysis   through   various 
methods   such   as:   quarry   works,   surface   mapping   and   drill   holes.   The   result   of   this   work   identified   that 
a   detailed   analysis   of   the   underground   structural   geology   would   be   required   prior   to   excavation   of   the 
caverns   could   start.   This   was   further   confirmed   with   the   collapse   of   a  tunnel   portal   early   in   the   project. 
The   investigation   plan   to   clarify   the   design   factors   included   the   construction   of   an   access   tunnel   along 
with   excavation   of   a  heavily   instrumented   trial   excavation   of   a  portion   of   the   Machine   Hall   as   shown 
below.  

80
  Douglas,   T.H.,   Richards,   L.R.   &  Arthur,   L.J.,   1979.   Dinorwic   Power   Station   Rock   Support   Of   The   Underground   Caverns.   In 
Fourth   Congress   of   the   Int.   Soc.   Rock   Mechanics .  Montreux:   International   Society   for   Rock   Mechanics,   pp.   361–369. 

 
©   Snowy   Hydro   Limited   2017  Page   51   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   28:   Layout   of   the   Dinorwic   power   station   complex   with   the   Machine   Hall   trial   enlargement   shown 
(item   3)81 

A   further   enlargement   of   the   the   Machine   Hall   trial   enlargement   is   shown   below. 

 
Figure   29:   Dinorwic   power   station   complex   ­  Machine   Hall   trial   enlargement   shown   (item   3)82 

81
  Douglas   et   al.   1979,   p.362. 
82
  Ibid,   p.364. 

 
©   Snowy   Hydro   Limited   2017  Page   52   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
The   results   from   this   Machine   Hall   trial   enlargement   improved   the   design   and   construction   process. 
 
Considerable   savings   in   time   of   construction   (of   the   order   of   20%)   due   to   wider   pacing   of   anchors   than 
originally   envisaged   and   to   the   installation   of   secondary   reinforcement   in   line   with   the   excavation 
thereby   initially   eliminating   any   additional   support   which   might   have   been   nominated   by   the   contractor. 
Similarly   a  saving   in   the   cost   of   approximately   20%   was   achieved   in   comparison   with   the   basis   originally 
tendered.83 
Snowy   Hydro   (as   SMHEA)   previously   designed   and   constructed   both   Tumut   1  and   Tumut   2  power 
station   complexes.   For   both   Tumut   1  and   Tumut   2  underground   exploratory   programs   were   completed 
prior   to   the   finalisation   of   the   design   and   the   start   of   construction   as   described   by   Brown.84  It   is   also 
important   to   note   that   the   depth   of   Tumut   1  and   2  Power   Stations   is   approximately   ⅓  the   depth   of   the 
proposed   power   station.   In   addition   the   size   of   the   largest   excavations   in   the   Scheme   to   date   are 
significantly   smaller   than   for   the   Project   as   outlined   in   the   table   below. 
 
Power   station   complex   and  Length   (m)  Width   (m)  Height   (m) 
Excavation 
Tumut   1  machine   hall  93.2  18.0  33.5 
Tumut   2  machine   hall  97.4  15.6  33.5 
Project   machine   hall   (base   case)  190.0  29.4   (crown   arch)  50.4   (typical) 
32.8   (max   width)  55.4   (max) 
Table   11:    Comparison   table   of   previous   underground   excavations   within   Snowy   Hydro   and   the   Project 

Prior   to   construction   of   Tumut   1  and   Tumut   2  underground   power   stations,   detailed   underground 
geotechnical   investigations   were   completed.   These   investigations   included   detailed   in   situ   stress 
testing,   and   significant   drilling   completed   for   each   site   as   described   below. 
 
Possible   sites   for   the   underground   power   stations   were   investigated   using   air­photo   interpretations, 
surface   geological   mapping   and   diamond   drilling.   Electrical   resistivity   logging   and   seismic   refraction 
surveys   were   also   used   in   site   investigation   for   other   structures   in   the   Scheme   (Moye   1955).   In   the   case 
of   Tumut   1,   four   diamond   drill   holes   ranging   from   300   to   600m   in   length   were   first   drilled   from   the   surface 
into   the   rock   at   the   proposed   power   station   site.   As   the   surface   drilling   indicated   favourable   conditions   at 
the   proposed   site,   an   exploratory   tunnel   was   driven   to   confirm   and   augment   the   data   obtained   from   the 
surface   drill   holes   and   to   enable   direct   examination   of   the   rock   in   which   the   excavations   would   be   made. 
From   a  chamber   located   at   the   end   of   the   exploratory   tunnel   six   diamond   drill   holes   with   a  total   length   of 
420m   were   drilled   across   the   proposed   excavations   for   the   machine   and   transfer   halls   and   draft   tubes 
(Moye   1959,   Pinkerton   et   al   1961).   A  similar   process   was   followed   for   Tumut   2.   However,   as   a  result   of 
the   identification   of   a  crushed   and   shear   zone   in   the   exploratory   tunnel   and   the   the   underground 
diamond   drill   holes,   the   initially   proposed   location   of   the   power   station   and   much   of   the   associated   works 
was   moved   by   approximately   30m   along   the   longitudinal   axis   of   the   machine   hall   (Stapledon   1961, 
Pinkerton   &  Gibson   1964).85 
 
The   location   of   the   underground   exploratory   tunnel   and   associated   drill   holes   for   Tumut   2  are 
illustrated   in   Figure   30   below. 
 
 
 

83
  Ibid,   p.   368. 
84
  Brown,   E.,   1999.   Rock   mechanics   and   the   Snowy   Mountains   Scheme.   The   Spirit   of   the   Snowy   Fifty   years   On.   In 
Proceedings   of   the   1999   Invitation   Symposium .  Cooma:   Australian   Academy   of   Technology,   Science   and   Engineering,   pp. 
89–101. 
85
  Brown   1999,   pp.92­93. 

 
©   Snowy   Hydro   Limited   2017  Page   53   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

Figure   30:   Geology   and   layout   of   Tumut   2  Site   including   location   of   exploratory   underground   tunnel   and 
associated   diamond   drill   holes86 

 
 

86
  Pinkerton   &  Gibson   1964. 

 
©   Snowy   Hydro   Limited   2017  Page   54   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

 
Figure   31:   Exploratory   Tunnel   Portal   for   Tumut   2  Project87 

In   addition   to   the   Exploratory   Tunnel   for   Tumut   2,   an   Exploratory   Shaft   was   also   constructed   for 
collection   of   geotechnical   information   on   the   project   as   shown   below.  
 

 
Figure   32:   Sinking   of   Exploratory   Shaft   for   Tumut   2  Project88 

The   underground   investigations   programs   for   both   Tumut   1  and   Tumut   2  were   considered   successful 
and   appropriate.   For   example,   specific   feedback   on   the   Tumut   2  site   investigation   is   quoted   below.  
The   comprehensive   program   of   field   exploration,   rock   tests,   photoelastic   model   studies   and 
instrumentation   carried   out   of   the   Tumut   2  Power   Plant   was   probably   the   main   factor   in   enabling   the 
design   and   construction   to   be   completed   without   any   significant   amendments   being   necessary   during 
the   construction   period.   On   this   basis,   the   cost   of   the   program   was   fully   justified   and   a  similar   program 
would   certainly   be   adopted   for   any   future   underground   plant.89 

87
  SMHEA   Official   Photo   Date   25­9­56   Negative   No   8945. 
88
  SMHEA   Official   Photo   Date   29­7­55   Negative   No   6914B. 
89
  Pinkerton   &  Gibson   1964. 

 
©   Snowy   Hydro   Limited   2017  Page   55   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
Based   on   the   depth   of   the   proposed   power   station   complex   for   both   the   Ravine   and   Plateau   options, 
the   use   of   exploratory   tunnel   and   or   shaft   to   provide   access   will   be   further   considered   based   on   the 
results   from   the   ongoing   GIP   and   the   potential   requirements   for   any   UGIP.   An   illustration   is   provided 
below   as   an   example   only,   to   help   describe   the   possible   locations   of   horizontal   drill   holes   in   relation   to 
a   potential   power   station   complex   layout. 
 

 
Figure   33:   Schematic   of   potential   underground   geotechnical   investigations90 

5   Risks   and   opportunities 

As   described   in  C
  hapter   Six ,  the   likely   geological   and   geotechnical   risks   and   opportunities   for   this   can 
currently   only   be   understood   at   a  conceptual   level.   This   is   based   on   predictions   of   rock   types,   rock 
structures,   and   rock   properties   at   the   underground   depths   of   proposed   infrastructure   being   based   on 
predominantly   surface   based   information.   As   a  result,   the   underground   actual   geology   and   the 
associated   geotechnical   rock   properties   could   be   better   or   worse   than   existing   predictions.  

The   geology   forms   the   basis   of   the   geotechnical   design   and   associated   construction   methodologies 
and   resulting   project   schedules   and   costs.   While   available   subsurface   data   at   the   date   of   this   Study 
Report   is   minimal,   the   quality   of   surface   mapping   undertaken   is   considered   sound.  

One   of   the   clearest   opportunities   to   reduce   uncertainty   in   Project   outcomes   is   improve   the   accuracy   of 
predicted   underground   geological   information   at   the   depths,   location   of   proposed   excavations   and 
associated   infrastructure.   The   GIP   has   been   developed   to   mitigate   this   risk   through   detailed   surface 
drilling,   mapping,   testing,   and   analysis.   The   GIP   is   expected   to   be   substantially   if   not   wholly   complete 
before   FID.  

At   this   early   stage   of   the   GIP   it   is   most   appropriate   to   provide   examples   only   of   geology   related   factors 
and   highlight   that   once   results   of   the   GIP   have   been   received,   potential   risks   and   opportunities   will   be 
more   fully   understood,   and   appropriate   mitigations   developed. 

The   risks   and   opportunity   areas   that   will   be   clarified   through   the   GIP   include: 

1. Percentage   of   each   rock   type   along   project   alignment; 
2. Rock   properties   for   each   rock   type; 
3. In   situ   stress; 
90
  Scope   only   able   to   be   confirmed   based   on   results   from   existing   GIP. 

 
©   Snowy   Hydro   Limited   2017  Page   56   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
4. Width   and   location   of   faults; 
5. Orientation   of   rock   structures; 
6. hazardous   gas   or   substances; 
7. Rock   temperature;   and 
8. Groundwater   pressure,   temperature,   and   flow   rates. 

As   with   all   underground   tunnelling   and   hydropower   projects,   assessing   underground   geology   from 
surface   with   the   use   of   surface   geophysics   and   surface   drill   holes   is   challenging,   especially   when   the 
targeted   underground   locations   are   up   to   1,100m   below   surface.   Once   a  preferred   cavern   location   is 
identified   based   on   surface   drilling   results,   the   next   stage   of   risk   mitigation   probably   includes   an 
underground   drill   site   that   can   enable   horizontal   and   multi­directional   drilling   and   potentially   trial 
excavations.   As   outlined   above,   the   scope   for   any   underground   geotechnical   investigation   program 
can   only   be   confirmed   once   results   of   the   existing   GIP   are   available.  

6   Supporting   documents 

Multiple   sources   of   information   were   used   for   the   compilation   of   this   report,   refer   to   the  E
  GAR   for   a  full 
list.   The   primary   references   used   in   this   report   are   listed   in   Section   9. 

Reference   name  Source  Year 

S2­0600­REP­011506   Engineering   Geology  SMEC  2017 


Assessment   Report 

S2­1400­REP­014035   Civil   and   Structural   Design  SMEC  2017 


Report 

NSW   zone   55   East   Seamless   Geology   dataset,  Geological   Survey   of   NSW,   NSW  2017 


version   1  (Digital   Dataset)  Planning   and   Environment 
Resources   and   Energy 

1:250   000   Bedrock   Geology  Geological   Survey   of   NSW,   NSW  2001 


Planning   and   Environment 
Resources   and   Energy 

Geology   of   the   Kosciuszko   National   Park   1:250,   000  Bureau   of   Mineral   Resources,  1990 


Australia 

Tantangara   1:100,000   Geology   Map   First   Edition  Bureau   of   Mineral   Resources,  1979 


Australia 

Tumut   1:100,   000   Geology   Map  Geological   Survey   of   NSW,  1990 


Department   of   Mineral   Resources 

Wagga   Wagga   1:250,000   Metallogenic   Map  Geological   Survey   of   NSW,  1980 


Department   of   Mineral   Resources 

Geological/geotechnical   Assessment   of   Existing  Jacobs,   for   Snowy   Hydro   Limited;  2017 


Tunnels   Report   and   Interpretation   for   New  Report   ­  1A5066­001 
Underground   Structures 

Eucumbene­Tumut   tunnel   logs   and   reports  Snowy   Mountains   Hydro­Electric    1957 


Authority 

Murrumbidgee­Eucumbene   tunnel   logs   and   reports  Snowy   Mountains   Hydro­Electric    1960 


Authority 

 
©   Snowy   Hydro   Limited   2017  Page   57   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 

Eucumbene­Snowy   tunnel,   Eucumbene­Snowy,  Snowy   Mountains   Hydro­Electric    1966,   1972 


Snowy­Geehi   and   Murray   1  logs   and   reports  Authority 

Tantangara   Dam   Quarry   Rehabilitation   Preliminary  SMEC  2010 


Design   Report 

Earthquake   Ground   Motion   Response   Spectra   ­  AECOM  2017 


Snowy   Hydro   Phase   1  sites 

Review   of   Seismicity   ­  Snowy   Mountains   Dams   ­  SRC  1999 


Geehi,   Happy   Jacks,   Talbingo,   Jindabyne   & 
Eucumbene 

Review   of   Seismicity   ­  Snowy   Mountains   Dams   ­  SRC  1996 


Guthega,   Island   Bend,   Eucumbene   &  Tantangara 

Rock   Mechanics   in   the   investigation   and  Moye,   D.G  1959 


construction   of   Tumut   1  Underground   Power   Station, 
Snowy   Mountains 

Engineering   Geology   of   the   Snowy   Mountains  Moye,   D.G  1955 


Scheme 
Table   12:   Supporting   documents   and   appendices 

7   Further   work   required   prior   to   FID 

As   discussed   in  C
  hapter   Six   ­  Geology   and   terrain ,  further   work   required   prior   to   FID   is   heavily 
dominated   by   understanding   the   geology   within   the   Project   alignment   through   the   GIP.  

The   primary   activity   to   further   develop   understanding   of   the   geology   of   the   Project   Area   is   to   complete 
the   GIP.   It   is   recommended   that   the   results   from   the   ongoing   GIP   be   incorporated   into   the   study 
information   and   associated   design.   This   will   gain   a  clearer   understanding   of   the   subsurface   conditions 
of   the   geological   units,   in   addition   to   the   nature   of   the   faults   (particularly   the   Long   Plain   Fault), 
groundwater   and   geological   contacts   in   the   Project   Area.   Based   on   an   updated   geological   model,   and 
associated   updated   geotechnical   predictions,   the   refinement   of   power   station   complex   design, 
construction   and   final   location   selection   can   be   completed. 

Once   a  preferred   chamber   location   is   identified,   the   next   stage   of   risk   mitigation   includes   initiation   of   a 
program   to   quickly   access   an   underground   drill   site   that   can   enable   horizontal   drilling   of   the   preferred 
chamber   location.   The   timing   of   this   decision   in   relation   to   FID   depends   on   the   level   of   confidence 
from   the   results   of   surface   based   GIP   program   and   as   such   can   not   at   this   stage   determine   how   much 
if   any   of   the   underground   drilling   results   or   other   underground   tests   are   needed   before   FID. 

8   Definitions   and   Abbreviations 

Refer   to   Chapter   Two   of   the   Study   Report. 

9   Bibliography  
1. ANCOLD,   1998.   Guidelines   on   Design   of   Dams   for   Earthquake. 
2. Barton,   N.,   Lien,   R.   &  Lunde,   J.,   1974.   Engineering   classification   of   rock   masses   for   the   design   of   tunnel 
support.   Rock   Mechanics,   6(4),   pp.189–236.   Available   at: 
https://www.google.com.au/search?q=Barton%2C+N%2C+Lien%2C+R+and+Lunde%2C+J.+(1974).+E
ngineering+Classification+of+Rock+Mass+for+the+Design+of+Tunnel+Support.+NGI+Publication+106%
2C+Oslo.+Rock+Mechanics+6%3A+No.+4%3A+189­236.&rlz=1C5CHFA_enAU723AU723&oq=Ba 
[Accessed   September   4,   2017]. 
3. Bieniawski,   Z.T.,   1993.   Classification   of   rock   masses   for   engineering:   the   RMR   system   and   future 
trends.   Comprehensive   rock   engineering,   3,   pp.553–573. 
4. Brown,   E.,   1999.   Rock   mechanics   and   the   Snowy   Mountains   Scheme.   The   Spirit   of   the   Snowy   Fifty 
years   On.   In   Proceedings   of   the   1999   Invitation   Symposium.   Cooma:   Australian   Academy   of 
Technology,   Science   and   Engineering,   pp.   89–101. 

 
©   Snowy   Hydro   Limited   2017  Page   58   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
5. Cleary,   J.R.,   1967.   The   seismicity   of   the   Gunning   and   surrounding   areas,   1958–1961.   Journal   of   the 
Geological   Society   of   Australia,   14(1),   pp.23–29.   Available   at: 
http://dx.doi.org/10.1080/00167616708728641. 
6. Douglas,   T.H.,   Richards,   L.R.   &  Arthur,   L.J.,   1979.   Dinorwic   Power   Station   Rock   Support   Of   The 
Underground   Caverns.   In   Fourth   Congress   of   the   Int.   Soc.   Rock   Mechanics.   Montreux:   International 
Society   for   Rock   Mechanics,   pp.   361–369. 
7. Fookes,   P.G.,   Baynes,   F.J.   &  Hutchinson,   J.N.,   2000.   Total   Geological   History:   A  Model   Approach   To 
The   Anticipation,   Observation   And   Understanding   Of   Site   Conditions.   In   International   Conference   on 
Geotechnical   and   Engineering   Geology;   GeoEng   2000.   International   Society   for   Rock   Mechanics,   pp. 
370–421. 
8. GHD,   1996.   Review   of   Seismicity   for   the   Snowy   Mountain   Dams   ­  Guthega,   Island   Bend,   Eucumbene 
and   Tantangara, 
9. Gray,   J.   &  Murphy,   B.W.,   1999.   Parent   Material   and   Soils:   a  guide   to   the   influence   of   parent   material   on 
soil   distribution   in   eastern   Australia, 
10. Hoek,   E.,   Marinos,   P.G.   &  Marinos,   V.P.,   2005.   Characterisation   and   engineering   properties   of 
tectonically   undisturbed   but   lithologically   varied   sedimentary   rock   masses.   International   Journal   of   Rock 
Mechanics   and   Mining   Sciences,   42(2),   pp.277–285. 
11. Hoek,   E.   &  Brown,   E.T.,   1980.   Underground   excavations   in   rock,   London :   The   Institution   of   Mining   and 
Metallurgy. 
12. Hoek,   E.   &  Diederichs,   M.S.,   2006.   Empirical   estimation   of   rock   mass   modulus.   International   journal   of 
rock   mechanics   and   mining   sciences,   43(2),   pp.203–215. 
13. Hoek,   E.   &  Marinos,   P.,   2000.   Predicting   tunnel   squeezing   problems   in   weak   heterogeneous   rock 
masses.   Tunnels   and   Tunnelling   International,   Part   1­2(November),   pp.1–20.   Available   at: 
https://www.rocscience.com/documents/hoek/references/H2000d.pdf   [Accessed   November   16,   2017]. 
14. Lambeck,   K.   et   al.,   1984.   The   state   of   stress   within   the   Australian   continent.   Annales   Geophysicae,   2(6), 
pp.723–742.   Available   at:   http://people.rses.anu.edu.au/lambeck_k/pdf/95.pdf   [Accessed   November   17, 
2017]. 
15. Lambeck,   K.   et   al.,   The   state   of   stress   within   the   Australian   continent.   Available   at: 
http://people.rses.anu.edu.au/lambeck_k/pdf/95.pdf   [Accessed   November   17,   2017]. 
16. Lambeck,   K.   et   al.,   The   state   of   stress   within   the   Australian   continent.   Available   at: 
http://people.rses.anu.edu.au/lambeck_k/pdf/95.pdf   [Accessed   November   17,   2017]. 
17. Look,   B.,   2007.   Handbook   of   geotechnical   investigation   and   design   tables,   Leiden:   Taylor   &  Francis. 
18. Marinos,   P.   &  Hoek,   E.,   2000.   Estimating   the   geotechnical   properties   of   heterogeneous   rock   masses 
such   as   flysch.   Bulletin   of   Engineering   Geology   and   the   Environment,   60(2),   pp.85–92. 
19. Marinos,   V.,   Fortsakis,   P.   &  Stoumpos,   G.,   2015.   Classification   of   Weak   Rock   Masses   in   Dam 
Foundation   and   Tunnel   Excavation.   In   Engineering   Geology   for   Society   and   Territory­Volume   6:   Applied 
Geology   for   Major   Engineering   Projects.   Springer,   pp.   859–863. 
20. Marinos,   V.,   Marinos,   P.   &  Hoek,   E.,   2005.   The   geological   strength   index:   applications   and   limitations. 
Bulletin   of   Engineering   Geology   and   the   Environment,   64(1),   pp.55–65. 
21. Marinos,   V.P.,   2012.   Assessing   rock   mass   behaviour   for   tunnelling.   Environmental   &  Engineering 
Geoscience,   18(4),   pp.327–341. 
22. McCue,   K.,   1999.   Seismic   hazard   mapping   in   Australia,   the   southwest   Pacific   and   southeast   Asia. 
Annali   Di   Geofisica,   42(6),   pp.1191–1198.   Available   at: 
http://www.annalsofgeophysics.eu/index.php/annals/article/view/3776   [Accessed   November   16,   2017]. 
23. Moye,   D.G.,   1955.   Engineering   geology   for   the   Snowy   Mountain   schema.   Civil   Engineering   Transaction 
Journal,   Institution   of   Engineers,   Australia,   27,   pp.287–299. 
24. Moye,   D.,   Sharp,   K.   &  Stapledon,   D.,   1954.   Engineering   geology   of   the   Snowy   Mountains   Scheme, 
25. Moye,   D.G.,   1959.   Rock   mechanics   in   the   investigation   and   construction   of   T1   underground   power 
station,   Snowy   Mountains,   Australia.   Geological   Society   of   America   Engineering   Geology   Case 
Histories,   3,   pp.13–44. 
26. Moye,   D.G.,   1959.   Rock   mechanics   in   the   investigation   and   construction   of   T1   underground   power 
station,   Snowy   Mountains,   Australia.   In   Geological   Society   of   America   Engineering   Geology   Case 
Histories.   Geological   Society   of   America,   pp.   13–44. 
27. Moye,   D.G.   &  Price,   D.,   1966.   Geology   and   Tunnelling   in   the   Snowy   Mountains   Scheme. 
28. Muirhead,   K.J.,   1981.   Seismicity   induced   by   the   filling   of   the   Talbingo   reservoir.   Journal   of   the   Geological 
Society   of   Australia,   28(3–4),   pp.291–298.   Available   at:   http://dx.doi.org/10.1080/00167618108729168. 
29. Parry,   S.   et   al.,   2014.   Engineering   geological   models:   An   introduction:   IAEG   commission   25.   In   Bulletin 
of   Engineering   Geology   and   the   Environment.   p.   707. 
30. Pinkerton,   I.   et   al.,   1961.   The   design,   construction   and   commissioning   of   Tumut   1  Power   Station. 
Journal   of   the   Institution   of   Engineers,   33(7–8),   pp.235–252. 
31. Pinkerton,   I.L.   &  Gibson,   E.J.,   1964.   Tumut   2  Underground   Power   Plant.   Journal   of   the   Power   Division, 
90(1),   pp.33–108. 
32. Rosin,   S.,   2017.   Geological/geotechnical   Assessment   of   Existing   Tunnels   Report   and   Interpretation   for 
New   Underground   Structures,   Sydney:   Jacobs   Australia   Pty   Ltd. 

 
©   Snowy   Hydro   Limited   2017  Page   59   of   60 
 
 
 
 
 
Snowy   2.0   Study   Report   ­  Chapter   Seven   ­  Geotechnical   and   seismic  Commercial­in­Confidence 
 
33. Sharp,   K.R.,   2004.   Cenozoic   volcanism,   tectonism   and   stream   derangement   in   the   Snowy   Mountains 
and   northern   Monaro   of   New   South   Wales.   Australian   Journal   of   Earth   Sciences,   51(1),   pp.67–85. 
Available   at:   http://dx.doi.org/10.1046/j.1400­0952.2003.01045.x. 
34. Standards   Australia,   2017.   AS   1726:2017   ­  Geotechnical   site   investigations,   Standards   Australia. 
35. Stapledon,   D.,   1961.   Geological   Studies   for   the   Planning   and   Construction   of   Tumut   2  Underground 
Power   Station,   Engineering   Geology   Report   S.G.86,   SMHEA,   Cooma.   University   of   Adelaide. 

 
©   Snowy   Hydro   Limited   2017  Page   60   of   60 
 

You might also like