R R PET Estimation1

This document contains an estimation of construction costs for a building project. It includes 10 line items with descriptions of materials and quantities needed. The major expenses are 28 cubic meters of M20 grade concrete for columns and piles at Rs. 140,000, 3.5 metric tons of steel works at Rs. 210,000, and various miscellaneous works like electrical, plumbing, and painting for Rs. 40,000 each. The total estimated cost for the project is Rs. 1,001,559.

Uploaded by

shahee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views1 page

R R PET Estimation1

This document contains an estimation of construction costs for a building project. It includes 10 line items with descriptions of materials and quantities needed. The major expenses are 28 cubic meters of M20 grade concrete for columns and piles at Rs. 140,000, 3.5 metric tons of steel works at Rs. 210,000, and various miscellaneous works like electrical, plumbing, and painting for Rs. 40,000 each. The total estimated cost for the project is Rs. 1,001,559.

Uploaded by

shahee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

R R PET VIJAYAWADA

CONSTRUCTION ESTIMATION

S.NO DESCRIPTION OF ITEM UNIT QUANTITY RATE AMOUNT REMARKS


1 Earthwork Excavation
Main Columns Piles Cum 28.00 250.00 7,000.00

2 Filling With Sand/Other material Cum 90.00 250.00 22,500.00

3 M20 Grade Concrete


Main Columns Piles Cum 28.00 5,000.00 140,000.00
Pile Cap Cum 5.83 5,000.00 29,150.00
Plinth Beam Cum 5.70 5,000.00 28,500.00
Columns upto Plinth Cum 1.70 5,000.00 8,500.00
Columns upto Slab Cum 3.50 5,000.00 17,500.00
Staircase Cum 0.80 5,000.00 4,000.00
Beams Cum 3.50 5,000.00 17,500.00
Slab Cum 7.00 5,000.00 35,000.00
Columns Above Slab Cum 0.85 5,000.00 4,250.00
Beams Above Plinth Cum 2.50 5,000.00 12,500.00
Concrete Below Flooring Cum 5.50 5,000.00 27,500.00

4 Steel Works MT 3.50 60,000.00 210,000.00

5 Brickwork
9" walls upto plinth Cum 50.00 650.00 32,500.00
9" Walls Cum 45.00 650.00 29,250.00
4.5" Walls Sqm 105.00 250.00 26,250.00

6 Plastering
Walls & Ceiling Sqm 320.00 180.00 57,600.00

7 Doors & Windows Sqm 21.06 1,150.00 24,219.00

8 Flooring Sqm 88.00 430.00 37,840.00

10 Miscellaneous Works
Supply and Electrical accessories with all
fittings & connections. Ls. 1.00 40,000.00 40,000.00

Supply and plumbing accessories with all


fittings & connections incl.spetic tank Ls. 1.00 40,000.00 40,000.00
complete

Water arrangements with supply & fixing


incl.water tank complete with all Ls 1.00 40,000.00 40,000.00
accessories

Staircase & gate arrangements with all


required material and labor complete Ls 1.00 35,000.00 35,000.00

Supply and fixing iron grills Ls 1.00 35,000.00 35,000.00

Supply and apply putty and paiting works


internal and external area. 1.00 40,000.00 40,000.00
Ls
1,001,559.00