Clubhouse: Description Unit Quantity $rate $value
Clubhouse: Description Unit Quantity $rate $value
Additional Items
Demolition of existing structure Item
Balconies and decks Item
External Services (More than 3m away) Item
External Works
Landscaping m2 20,000.00
HVAC m2 400 250 100,000.00
Specific Factors
Infustructure upgrades Item
Remote locality Item 1 60000 60,000.00
Subtotal for additional items 400 450.00 180,000.00
Subtotal for building works 400 3,100.00 1,240,000.00
Allowance for fluctuations % 4% 49,600.00
Allowance for contingency % 8% 99,200.00
Subtotal for fluctuations and contingency 148,800.00
Total for building works 400 3,472.00 1,388,800.00
Additional Fees
Resource and Building Consent Item 1 90000 90000
Furniture, Fitting and Equipment Item 1 10000 10000
Liasison and management of separate contracts Item 1 5000 5000
Legal Fees Item 1 5000 5000
Other Item 1
Subtotal for fees 400 275 110000
Subtotal for Project Estimate 400 3,747.00 1,498,800.00