Temporary Expansion Joints For Large Buildings: Number U425B April 2002
Temporary Expansion Joints For Large Buildings: Number U425B April 2002
T E C H N I C A L N O T E
Temporary Expansion
Joints For Large Buildings
Number U425B be net overall expansion of floor or roof typically would not be noticeable.
April 2002 decks that reflects the combined effects of However, if the building is 160 feet or
panel expansion as absorbed by the spac- 240 feet long, the overall expansion
If wood structural panels are exposed to
ing at panel edges and ends, and restraint could be two or three times as much,
moisture or humidity during construc-
afforded by panel fasteners and framing. and out-of-plumb rim joists or end (and
tion of buildings with large, continuous
interior) walls would be noticeable. In
floor or roof decks, panel expansion may
Floors multi-story buildings, walls would be
accumulate through the framing.
plumb at the building’s mid-length or
All wood products absorb moisture from Floor panels are interconnected by
mid-width, but wall displacement (out-
or give up moisture to the environment bottom plates of exterior and interior
of-plumb) would gradually increase to a
until they reach a moisture content in walls which typically are nailed to the
maximum at the exterior walls. The
equilibrium with their surroundings. floor, or through the floor to the floor
squareness of door or window openings
Wood structural panels have good dimen- framing. Also, floor panels are often
also might be affected, both in interior
sional stability because the tendency of nail-glued to floor framing for added floor
and exterior walls.
individual veneers or strands to swell or stiffness, and to minimize or eliminate
floor squeaks. Either or both of these Designers and contractors can minimize
shrink is greatly restricted by the adjacent
situations may partially offset the effec- displacement by incorporating temporary
veneers or strands in the panel.
tiveness of the recommended spacing at expansion joints in floors of buildings
In typical sheathing applications, relative with wood- or steel-framed walls, when
panel edges and ends, resulting in accu-
humidity might vary between 40% and the building plan dimension (length or
mulation of panel expansion along the
80%, with corresponding equilibrium width) exceeds 80 feet. Such joints for
length or width of the building.
moisture content of wood structural floors might consist of an extra wide
panels ranging between 6% and 14%. For example, in an 80-foot long building,
spacing gap (such as 3/4 inch) between
Total dimensional change of an if net overall expansion of 0.05% occurs
panel ends at the desired expansion joint
unrestrained 48-inch x 96-inch panel in the floor deck during construction, an
intervals. Panel ends can be supported on
exposed to this range of conditions typi- increase in building length of 1/2 inch, or
adjacent doubled floor joists and not
cally averages 1/8 inch in length and 1/4 inch at each end may result. If this
nailed to them until later, to allow for
width. If the panel gets wet during con- expansion occurs on the first floor with a
floor expansion. Also, it is important to
struction, dimensional change could be concrete or masonry foundation below,
insure that wall bottom plates do not
slightly greater. Recommended spacing of the rim or band joists might be displaced
extend across the expansion joint. After
1/8 inch at ends and edges of floor and out-of-plumb by 1/4 inch, which typi-
the building is “closed in,” fastening of
roof deck panels will “absorb” some or cally could be accommodated without
the floor panels can be completed, and a
most of this expansion. problem. If this expansion occurs on the
filler piece or non-shrink grout can be
second floor of a multi-story building
However, such dimensional change in installed to fill the gap between panels,
(assuming an on-grade concrete slab for
installed panels typically is reduced due to where necessary. For shear walls or braced
the first floor), the top end of the first
partial restraint by fasteners and framing. wall panels, a short lumber bottom plate
story walls theoretically might be dis-
Field experience indicates that there can filler block and “doubler” could be added
placed out-of-plumb by 1/4 inch, which
A PA
THE ENGINEERED
WOOD ASSOCIATION
© 2002 APA - The Engineered Wood Association
TN,U425,ExpJoints.0 5/17/02 11:26 AM Page 2
©2002 APA – THE ENGINEERED WOOD ASSOCIATION • ALL RIGHTS RESERVED. • ANY COPYING, MODIFICATION, DISTRIBUTION OR OTHER USE OF THIS PUBLICATION OTHER THAN AS EXPRESSLY AUTHORIZED BY APA IS PROHIBITED BY THE U.S. COPYRIGHT LAWS.
FIGURE 1
(1) Install bottom plate filler block and doubler to splice bottom plate, after nailing floor deck when building is “closed in.”
FIGURE 2
later between studs, to splice the bottom Designers or contractors may choose to joints are not incorporated in the design
plate of walls over the expansion joint. omit temporary expansion joints in large or construction of large buildings, it is
See Figure 1 for a possible construction buildings, based on their individual expe- done with the understanding that the
detail for incorporating an expansion joint rience as affected by materials they designer or contractor may face the
in floors; other effective expansion joint choose and the environment and tech- potential risk of structural modifications
details also may be used. niques of construction. For example, or repairs if problems occur later.
Expansion of floor panels can be when large buildings are constructed in Although problems are relatively few,
reduced by minimizing exposure to warm, dry regions or in summer months incorporating temporary expansion joints
moisture during construction. If rain (or where moisture is not likely to occur in such large buildings is recommended
snow) occurs during construction and during construction, the need for expan- as good construction practice.
there are areas of the floor that are sub- sion joints is less. However, if expansion
ject to water ponding, such as when
water is trapped by bottom plates of
walls, drill drainage holes through the FIGURE 3.
floor to allow the water to escape. These TEMPORARY EXPANSION JOINT DETAIL FOR ROOFS
holes can be patched later with glued Temporary expansion
wood dowels or grout and backer plates joint at 80' intervals
Roofs
In the construction of large roof decks
with wood structural panels fastened to
trusses or rafters, sheath 80-foot sections,
omitting a roof sheathing panel (in each
course of sheathing) between sections.
This provides effective temporary expan-
sion joints. (See Figure 3.) Then, the
installation can be completed with “fill-
in” panels, cut to size as necessary. The
roof deck should be covered with roofing Omit roof sheathing panel in each course.
underlayment as soon as possible for Roof framing (typical) Install “fill-in” panel as roofing is applied.
protection against excessive moisture (Laterally brace roof framing.)
(International Offices:
Bournemouth, United Kingdom;
Mexico City, Mexico; Tokyo, Japan.)
Addres
eb s
W
@
www.apawood.org :
A PA
THE ENGINEERED
WOOD ASSOCIATION