Tracking - Week 06: Pt. Epson Indonesia CIBIS Tower 9 JL - TB Simatupang, Jakarta Selatan
Tracking - Week 06: Pt. Epson Indonesia CIBIS Tower 9 JL - TB Simatupang, Jakarta Selatan
EPSON INDONESIA
CIBIS Tower 9
Report Date : 13/07/2016
Jl.TB Simatupang, Jakarta Selatan
Project Information
Role Lead Team Project Name Project Milestone Wks
Design & Build Contractor Vetira Pribadi Kreasi Budget Cap (IDR) Place Long Lead Items 7 A
TBC Screeding 7 A
Project Timeline Task On Program Task In Potential delay Task Delayed Task Done
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Shortlisted Clarification I
e
Final Submission BoQ d
Week Look Program Ownership Deliverable Mon Tue Wed Thu Fri RAG
BoQ Submission and LoA All PDF & MoM Not Yet Start
Key Project Agenda Project Mitigation Decision Required Priority Due Date
Colliers needs to submit bidders
To secure the design & Build assessment to EIN followed by a Important
LoA Design & Build Contractor 14/7/2016
contractor for EIN Project decision from EIN to appoint the & Urgent
contactor