The document provides a breakdown of costs for building a mosque, including costs for excavation, foundation work, blockwork, concrete, reinforcement, roof structure, tiles and finishing. It lists 11 sections with multiple sub-sections detailing materials, quantities, and costs for constructing the various parts of the mosque.

Uploaded by

greatgenius
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
147 views3 pages

Forex Trading For Beginners

The document provides a breakdown of costs for building a mosque, including costs for excavation, foundation work, blockwork, concrete, reinforcement, roof structure, tiles and finishing. It lists 11 sections with multiple sub-sections detailing materials, quantities, and costs for constructing the various parts of the mosque.

Uploaded by

greatgenius
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

THE MOSQUE

1. Foundation Trench
a) Excavation of trench not more than 1m depth - N15,000
b) Excavation of Column Bases. - N6,000
N21,000

2. Twisted Iron ReBars in Columns and Column Bases


a) 10 Lengths of 12mm bars at 2500/1 - N25,000
b) 3 Lengths of 10mm bars at 1500/1 - N4,500
e) Iron Bender - N8,000
N37,500

3. Concrete In Foundation Footing


a) 20 Tonnes of Stone Dust - N68,000
b) 20 Tonnes of ¾ Gravels - N68,000
c) 8 Bags of Cement at 2550/1 - N20,400
d) Labourers - N16,000
N172,400

4. Block work In Foundation up to DPC


a) Approximately 150 pcs of 9’’ Hollow Blocks at 180/1 - N27,000
b) 5 Bags of Cement at 2550/1 - N12,750
c) Bricklayers - N13,000
N52,750

5. Laterite and Hardcore Filling


Allow for - N15,000

6. Concrete In Ground Floor Slab


a) Sawn Formwork to Edges of Blocks - N10,000
b) Concrete
i) 10 Bags of Cement at 2550/1 - N25,500
ii) Labourers - N16,000
N51,500

7. Blocks Work on Ground Floor Slab


a) 350 no of 9” blocks at 180/1 - N 63, 000
b) 8 Bags of cement at 2550/1 - N 20, 400
c) Bricklayers - N 17, 000
N100,400
8. Lintels and Columns
a) Carpenters and Nails - N 15, 000
b) Twisted Iron Bars in Lintels and Columns
i. 10 lengths of y12 mm at 2500/1 - N 25, 000
ii. 3 lengths of y10 mm at N1500/1 - N 4,500
iii. Iron Benders - N 10, 000
c) Concrete in Lintels and Columns
i. 6 bags of cement at N2550/bag - N 15,300
ii. Labourers - N 8, 000
N 77,800

9. Parapet Headcourse
a) Twisted Iron Bars in Headcourse
i. 4 lengths of y12 mm at 2500/1 - N 10,000
ii. 2 lengths of y10 mm at 1500/1 - N 3, 000
iii. Iron Benders - N 6, 000
b) Carpenters - N10,000
c) Concrete in Headcourse
i. 4 bags of cement at 2550/1 - N10,200
ii. Labourers - N 8, 000
d) 12m of Polysterine Fascia at 4400/m - N52,800
N100,000

10. Rafter and Noggins


a) 15 No of 2x6x12 hardwood at 650/1 - N 9,750
b) 40 no of 2x4x12 at 450/1 - N18,000
c) 40 NO of 2x3x12 at 300/1 - N 12,000
d) 4 “ Nails - N 10, 000
e) Carpenters - N 15, 000
N 64,750

11. Stone Coated Roof Tiles


a) Approximately 40 m2 of Roof panels at 4200/m2 - N 168, 000
b) About 10m of ridge cap at 2800/m - N 28, 000
c) 5kg of screw Nails at 3000/kg - N 15, 000
e) Finishing kits at 4000/1 - N 4, 000
f) Installation and transportation - N 8, 000
N 223, 000