0% found this document useful (0 votes)
2K views3 pages

FAT and SAT Procedure

Professional installation performed by Vaisala ensures reliable operation, efficient data flow, and a long lifecycle for the investment. Installation includes civil works like grounding and cabling, hardware installation such as masts and towers, and configuration/testing of equipment and software. For large networks, Vaisala can provide on-site training to teach customers. Acceptance testing verifies the system meets specifications and allows customers insight into functionality. Factory acceptance testing inspects hardware and software at Vaisala according to checklists, while site acceptance testing ensures smooth startup and performance at the customer site.

Uploaded by

Soe Sintthu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views3 pages

FAT and SAT Procedure

Professional installation performed by Vaisala ensures reliable operation, efficient data flow, and a long lifecycle for the investment. Installation includes civil works like grounding and cabling, hardware installation such as masts and towers, and configuration/testing of equipment and software. For large networks, Vaisala can provide on-site training to teach customers. Acceptance testing verifies the system meets specifications and allows customers insight into functionality. Factory acceptance testing inspects hardware and software at Vaisala according to checklists, while site acceptance testing ensures smooth startup and performance at the customer site.

Uploaded by

Soe Sintthu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Installation

Professional installation performed by Vaisala reduces unexpected costs related to


maintenance and enables efficient operation, reliable data flow and long life cycle for your
investment. Installation is completed by professional and experienced personnel according
to pre-defined processes and procedures.

Installation services may consist of civil works, hardware installation and implementation.
Civil works and hardware installation entail actions such as grounding, laying concrete,
cabling, installing masts or towers and the required communications.

During implementation the equipment and software will be configured and tested to ensure
reliable and accurate data output. For large networks it may be possible for Vaisala field
service engineers to teach customer personnel by providing on-site training with one or two
installations.

Acceptance Testing
The acceptance testing allows customers to verify that their system is operational and has been built according to
the specifications. Acceptance testing is carried out according to standard protocols at the Vaisala factory and/or
the customer's site. By participating in the acceptance testing customers can gain a deeper insight into the
functionality of the equipment.

Factory acceptance test


The purpose of the FAT (Factory Acceptance Test) is to inspect the system at the Vaisala factory according to
predefined FAT protocols. During the FAT, the hardware and software of the observation system is thoroughly
inspected at the Vaisala factory according to a checklist of performance parameters. The FAT is typically
performed together with the customer.

Site acceptance test


The purpose of the SAT (Site Acceptance Test) is to inspect the system at the customer's site to ensure smooth
startup and that the equipment meets its performance requirements. The SAT is carried out together with the
customer, and may also be replaced with a less formal installation inspection.
Source #2
FAT,SAT application

FAT,SAT is an documented testing of equipment witnessed by customer at vendors site and then at users premises before
commisioning /installation. So it is applicable to all types of instruments/equipments.

FAT (Factory Acceptance Test)


The complete validation test for the equipment will be performed at Comecer ’s site. The FAT
protocol will include the following tests:

1. Test Instrument Data (Calibration Certificates of the reference instruments)

2. System Documentation Verification (documents list for the equipment qualification)

3. Construction Design Verification (“As Built drawings and schemes”)

4. Main Equipment Specification Verification (correspondence with the design)

5. Functionality/Interlocks Verification (Mechanical & Software)

6. Glove Breach Test (only where gloves provided)

7. Unidirectional Air Flow Verification (Smoke pattern test – only with Laminar flow)

8. Air Change Rate

9. Air Velocity Verification (only with Laminar flow)

10. Filter Leakage (Integrity test)

11. Leak tightness Test (only if applicable)

12. Non Viable Particle Counts (Air classification)

SAT (Site Acceptance Test)


The SAT will include the following tests:

1. Finishing Visual check


2. Main components visual check

3. Internal box pressure and ventilation setting

4. Utilities functionality and setting check

5. Functionality/Interlocks Verification (Mechanical & Software)

6. Hot test for dispensing systems (activity source supplied by Customer)

7. Dose calibrator verification (activity source supplied by Customer)

8. Safety devices and interlocks check

9. Operator’s training

10. Delivery of the performed FAT protocol and documentation package including:

o Performed FAT Protocol

o Maintenance and User’s manual

o Recommended spare parts list

o Certificate of compliance

o As built technical drawings (electrical, mechanical, pneumatic & process


schemes)

o Materials certificates/data sheets

o Main equipments data sheets

o Instruments calibration certificates

o Welding Processes qualification