Project Engineer & Planning Interview Questions
Project Engineer & Planning Interview Questions
Project planning depends upon level of decomposition done for any project. More the extent of
breaking down different activities, higher is the level of plan. Usually 4 levels of plan are used in an
EPCC environment. All four levels are explained below:
Level – 1 Plan
This is the most basic and contractual plan which shows start and end dates of all different phases of
project e.g. Engineering, Procurement, Construction etc.
Level – 2 Plan
Level – 1 plan is detailed further into various disciplines. Major activities are mentioned discipline
wise along with corresponding start and end dates e.g. commencement and completion of Mechanical,
Civil, Electrical etc. is shown more explicitly.
Level – 3 Plan
At this level, level- 2 plan is further broken down into Systems/Areas. Activities in level-2 plan are
further divided into smaller activities and plan for each is provided e.g. Start and end dates of
equipment, piping fabrication, piping erection etc. are included. Resource allocation is also applied for
this level.
Level- 4 Plan
In this level, level- 3 plan is further broken down into drawing level and making zones of Project.
This is prepared at start of the project after detailed study of BOQ and drawings.
1. Initiating
2. Planning
3. Executing
4. Monitoring and Controlling
5. Closing
4) Critical path method - The Critical path method is used to estimate the shortest
length of time needed to complete a project and to determine the amount of float
for activities that are not part of the critical path.
5) Forward pass - A technique used to calculate early start and finish dates by
working forwards from a point in a project schedule model.
6) Free float - The amount of time by which an activity can be postponed without
affecting the early start dates of a successor activity.
Total float - The length of time an activity can be delayed from its early start date
without affecting the project end date.
Lead/Lead time - The amount of time an activity can be brought forward with
respect to the activity it is dependent upon.
7) Backward pass - This calculates late-start and finish dates for project activities
by working backwards from the project end date.
8) Contingency reserve - An allocation of time or money (or both) set aside for
the occurrence of known possibilities that could delay a project or make it more
expensive. It is not the same as a management reserve, which is an allocation
made for unforeseeable circumstances. Use of a contingency reserve is typically
authorized upon the occurrence of a contingency.
16) Baseline - This term represent the costs and schedules approved at the start
of the project. They use baselines as a basis for monitoring and evaluating
performance
17) Data date - A data date, also called an as-of date, is a point at which a
project’s status is measured and documented. It separates actual data from
scheduled data.
19) Earned value - A concept used to gauge project schedule and cost
performance. Portions of the project budget are assigned to components of the
work breakdown structure, and successful completion of a work breakdown
structure component is understood as value earned through work.
Earned value management - A method of measuring project performance and
progress with regard to scope, time, and costs. It is based on the use of planned
value (where portions of the budget are allotted to all project tasks), and earned
value (where progress is measured in terms of the planned value that
is earned upon completion of tasks).
20) Finish-To-Start - In a finish-to-start relationship, a successor activity cannot
start until a predecessor activity has finished.
Finish-To-Finish - In a finish-to-finish relationship, a successor activity cannot
finish until a predecessor activity has finished.
21) Fixed duration - A task in which the time required for completion is fixed.
22) Initiation phase – The formal start of a new project. It involves receiving
proper authorization and creating a clear definition for the project.
23) Kickoff meeting - The first meeting between a project team and stakeholders.
It serves to review project expectations and to build enthusiasm for a project.
29) Project phase - A distinct stage in a project management life cycle. Each
phase comprises a set of project-related activities.
Project plan - A document formally approved by the project manager, sponsor,
and other stakeholders which states the approved cost, schedule, and scope
baselines. It guides project execution, control, and quality and performance
assessment. The project plan also forms the basis for communication between
parties involved in a project. Project plans can vary in their levels of detail.
30) Request for proposal - A formal invitation for expressions of interest that is
extended by an organization looking to procure goods or services. (See
also invitation for bid)
Request for quotation - Upon receipt of proposals after issuing a request for
proposal, an organization will issue a request for quotations to shortlisted
proposers, asking for detailed cost estimations for specific goods or services.
Risk - The probability of occurrence of a specific event that affects the pursuit of
objectives. Risks are not negative by definition. In project management,
opportunities are also considered risks.
Scope - The scope of a project constitutes everything it is supposed to accomplish
in order to be deemed successful.
31) Slippage - The negative variance between planned and actual activity
completion dates. Slippage may also refer to the general tendency of a project to
be delayed beyond planned completion dates.
Statement of work (SoW) - A Statement of work is a comprehensive and detailed
list of deliverables expected under a contract, with expected dates for each
deliverable.
Successor activity - In a schedule, a successor activity logically comes after and
depends on an activity immediately preceding it.
Sunk cost - A cost that cannot be recovered once spent.
31) Task - In project management, a task is a unit of work or activity needed for
progress towards project goals. Typically, a task must be completed by a set
deadline. Tasks may be further broken down into assignments or subtasks.
Work package - The work packages of a project are its lowest-level deliverables.
They are detailed in a work breakdown structure dictionary.
1. How do you define CPM scheduling ?2. What is the definition of a critical path
?3. What is the difference between crashing a schedule and fast tracking a
schedule ?4. What are the three major components of scheduling ?5. How would
you create a cash flow curve in a scheduling program ?6. How would you create a
manpower histogram and curve in a scheduling program ?7. What is float and who
owsn the float ?8. What is a constraint ?9. Do you believe that negative lags should
ever be used ? If so why ? If not why ?10. Typcially should mandatory constraints
be used ? If so why ? If not why ?11. What is the largest project schedule that you
have ever managed ? Number of activities ?12. What is the largest project
schedule that you have ever managed ? Dollar value ?
13. Have you ever incorporated change order or change notices or extra work
items into theschedule ? If so what was the format that you used ?14. When
refering to the contemporaneous schedule what schedule is that refering to ?15.
What is mean by the term EOT ?16. What is the proper way to record progress in a
schedule17. If the project that you were working on fell behind schedule what
would you ? What stepswould you take to bring it back in line ?18. What is the
forward pass and what dates are derived from the forward pass ?19. What is the
backward pass and what dates are derived from the backward pass20. Why
should we hire you ?21. What do you consider your strengths ?22. What do you
consider your weaknesses ?23. How do you handle constructive criticism ?24.
Where do you see yourself in 5 years from now ? (short term goals)
25. Where do you see yourself 10 years from now ? (long term goals)25. Do you
belong to any National Project Controls Organizations which as PMI ?26. Are you
willing to travel ?27. Why should we hire you ?Power plant specific1. Have you
ever done any outage scheduling ?2. Have you ever scheduled down to the hour
as a planing unit ?3. During an outage how many times a day you update the
schedule4. Do you have any power plant experience ?I could go on and on forever
and do not ask me for any of the answers. That is for you to find outon your own.
You should really think about the question and then research any
questionsanswers that you do not know the answer for