Chapter-17 Demolition and Dismantling: D:/Office Work/Website/Upload/Sor/Se-Gonda - Xlsse-Gonda

The document provides specifications for various demolition and dismantling work items including: 1. Dismantling brick work, stone work, reinforcement concrete, wooden beams, roofs, floors, iron roofs, grids, doors, windows and plaster. 2. It lists the item number, description of work, specification number, unit of measurement, labour rate and overall rate for 15 such work items. 3. The rates provided are for dismantling and stacking materials within a distance of 60 meters as directed by the Engineer-in-charge.

Uploaded by

Sandeep Solanki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
94 views2 pages

Chapter-17 Demolition and Dismantling: D:/Office Work/Website/Upload/Sor/Se-Gonda - Xlsse-Gonda

The document provides specifications for various demolition and dismantling work items including: 1. Dismantling brick work, stone work, reinforcement concrete, wooden beams, roofs, floors, iron roofs, grids, doors, windows and plaster. 2. It lists the item number, description of work, specification number, unit of measurement, labour rate and overall rate for 15 such work items. 3. The rates provided are for dismantling and stacking materials within a distance of 60 meters as directed by the Engineer-in-charge.

Uploaded by

Sandeep Solanki
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CHAPTER-17

DEMOLITION AND DISMANTLING


S.No. SCH. ITEM Description of Work P.W.D SPEC. UNIT LABOUR OVER ALL
P.W.D NO NO. RATE RATE
PWD
1 2 3 4 5 6 7 8
1 692 Dismantling brick work or stone work in
lime or cement mortar and including
stacking of materials as directed by
Engineer-in-charge with in a distance of 60
mt. (200 feet) Cu.M - 320.00
2 693 As in item (692) above but in mud mortar.
Cu.M - 155.00
3 694 Dismantling reinforcement cement concrete
or reinforcement brick work including
stacking of materials as directed by
Engineer-in-charge with in a distance of 60
mt. (200 feet) Cu.M - 715.00
4 695 Dismantling Jack arched or wooden beam
and barja roofs including beam and roof
concrete and including stracking
dismantled materials as directed.
Sqm. - 180.00
5 696 As in item (695) above but only roof
concrete. Cu.M - 250.00
6 697 Dismantling cement concrete or brick work
or granolithic floors including stacking of
dismantled materials as directed by
Engineer-in-charge with in a distance of 60
mt. (200 feet) Sqm. - 38.00
7 698 As in item (697) above but floor to be stone
flagged or tiled floor Sqm. - 50.00
8 701 Dismantling corrugated iron roofs walls or
partition including purlins battens and
vertical support and including stacking of
dismantled materials as directed by
Engineer-in-charge with in a distance of 60
mt. (200 feet) Sqm. - 32.00
9 702 Dismantling of grids, trusses and other steel
work including stacking of dismantled
materials as directed by Engineer-in-charge
with in a distance of 60 mt. (200 feet)
Qtl - 1100.00
10 703 Dismantling doors or windows including
stacking of dismantled materials as directed
by Engineer-in-charge with in a distance of
60 mt. (200 feet) Sqm. - 50.00

D:\Office Work\Website\upload\SOR\SE-Gonda.xlsSE-Gonda.xls 1
S.No. SCH. ITEM Description of Work P.W.D SPEC. UNIT LABOUR OVER ALL
P.W.D NO NO. RATE RATE
PWD
1 2 3 4 5 6 7 8
11 704 Dismantling doors or windows leaves
including stacking of dismantled materials
as directed by Engineer-in-charge with in a
distance of 60 mt. (200 feet)
Sqm. - 25.00
12 705 Dismantling doors or windows leaves
excluding chaukhat including stacking of
dismantled materials as directed by
Engineer-in-charge with in a distance of 60
mt. (200 feet) Sqm. - 48.00
13 706 Dismantling existing plaster including
disposal of refuse as directed by Engineer-
in-charge with in a distance of 60 mt. (200
feet) Sqm. - 27.00
14 707 Racking out joints of brick work in cement
or lime mortar to depth of 1 cm (3/8”)
including disposal of refuse material as
directed by Engineer-in-charge with a
distance of 60 met.(200 feet)
Sqm. - 19.00
15 708 Scraping old white or colour wash
including disposal of refuse material as
directed by Engineer-in-charge with a
distance of 60 met.(200 feet) Sqm. - 8.00