Saep 37
Saep 37
1 Scope............................................................ 2
2 Conflicts and Deviations................................ 2
3 Applicable Documents................................... 2
4 Definitions and Acronyms.............................. 3
5 Sources of Magnetism................................... 3
6 Magnetism Verification.................................. 3
7 Residual Magnetism Levels.......................... 3
8 Magnetism Removal Methods....................... 4
1 Scope
1.1 This procedure specifies the various methods to remove residual magnetism
from pipelines (mostly underground). Residual magnetism causes “Arc Blow”
to the welding arc during welding and this result in shifting the arc from the
weld area. Arc blow can cause excessive spatter, incomplete fusion, and
porosity.
1.2 Additional requirements may be provided at the time when residual magnetism
is encountered during pipelines welding.
Conflicts between this Engineering Procedure and any other Saudi Aramco Standard
shall be resolved by the Consulting Services Department in writing.
3 Applicable Documents
Unless stated otherwise, all Standards, Specifications, and Codes referenced in this
procedure shall be of the latest issue (including revisions, addenda, and supplements)
and are considered a part of this procedure.
Page 2 of 9
Document Responsibility: Welding Standards Committee SAEP-37
Issue Date: 22 October 2011
Next Planned Update: 22 October 2016 Pipelines Residual Magnetism Removal
Arc Blow: A condition that occurs when the arc does not follow its intended path from
the electrode to the work piece due to presence of magnetic field.
5 Sources of Magnetism
6 Magnetism Verification
6.1 Qualitative
This can be done by moving small piece of steel (approximate weight 10 gram)
or 2.6 mm bare electrode (coating or flux is removed) towards the underside of
the pipe and if the pieces get hung then magnetism is exiting on the pipe.
6.2 Quantitative
Magnetism can checked and measured using an instrument called gauss meter.
The gauss meter reading will help to determine in advance what would be the
most suitable method to remove the magnetism during welding.
There are generally three ranges of magnetism that require specific actions for each range:
Only the welder can notice slight disruptive in the welding arc at such low level
of magnetism. If the welder encounters difficulties during welding, then, the
Page 3 of 9
Document Responsibility: Welding Standards Committee SAEP-37
Issue Date: 22 October 2011
Next Planned Update: 22 October 2016 Pipelines Residual Magnetism Removal
quick solution is to reduce the welding current to the minimum possible range
for the subject electrode size and to reduce the welding arc length to the
minimum.
Arc blow will be noticeable and detrimental to the welding operation when the
magnetism strength is higher than 20 Oe. At this range of magnetism welding
must be done with AC power source in order to counter attack the residual
magnetic field. Weldability can be enhanced by applying simple demagnetizing
procedures Method I and II in Section 8.
All of the impressed current of the Cathodic Protection System upstream and
downstream of the welding location must be disconnected before any welding
operations. Also, remove cables with direct current away from the welding area to
reduce magnetism produced by the direct current power.
It is not possible to demagnetize the whole pipe; however, there are various methods to
temporarily remove the magnetism or disrupt the magnetic field at the weld location to
perform the welding operation. It cannot be decided that once one method is applied
then the magnetism will be eliminated, it is trial process where people must start with
the simplest procedure (Method I) and proceed to the more complicated procedure
(Method IV).
This method requires single AC welding generator and welding cables (they
must suit the current range of the applicable electrode). It is more likely that
once the root pass is completed then the demagnetization can be terminated and
the welding operation can be continued.
1) Wrap the AC earthling cable around the pipe to form a tight coil (not less
than turns).
2) Set 100 mm space between the edge of the coil and the weld joint being
demagnetized.
Page 4 of 9
Document Responsibility: Welding Standards Committee SAEP-37
Issue Date: 22 October 2011
Next Planned Update: 22 October 2016 Pipelines Residual Magnetism Removal
3) Turn the generator on and gradually increase the current to the specified
setting of the applicable electrode size. The initial setting of the current
should be 0 amps.
4) Commence welding and if arc blow is observed then increase the current
or increase the number of turns or use larger size electrode (it is possible to
try combination of actions). If the magnetic field is still causing arc blow
then use methods III or IV below
This method requires single AC welding generator, welding cables (they must
suit the current range of the applicable electrode). It is more likely that once the
root pass is completed then the demagnetization can be terminated and the
welding operation can be continued.
1) Connect the AC earth cable to a splitter (steel bar). Four earth cables
should be connected to the pipe, two on each side and they can be 300 mm
apart.
2) Turn the generator on and gradually increase the current to the specified
setting of the applicable electrode size. The initial setting of the current
should be 0 amps.
3) Commence welding and if arc blow is still observed then increase the
current to the maximum range of the applicable electrode size.
4) If arc blow does not go away then move the earth cables connections
closer together (on each pipe side) or use larger size electrode (it is
possible to try combination of actions). If the magnetic field still affecting
the welding then use Method III or IV.
This method requires single DC welding generator, 300 amp capacity cable,
4 mm – 6 mm diameter electrode and gauss meter. The same generator used for
the demagnetization will also be used for welding. If it is noticed that this
method does not work then use Method IV must be applied.
After disrupting the field strength to a suitable level, the operator has about one
hour to start the root weld. On this basis, before starting, ensure that all the
requirements to complete the welding operation are ready as time is limited.
If the maintenance work requires replacement of pipe section then the total
length of the pup piece should be at least 300 mm.
Page 5 of 9
Document Responsibility: Welding Standards Committee SAEP-37
Issue Date: 22 October 2011
Next Planned Update: 22 October 2016 Pipelines Residual Magnetism Removal
Instructions:
1) Measure the magnetic field strength using gauss meter. Move the meter
around the weld/pipe end circumference and mark the location that has the
maximum magnetic field strength then record the reading and the polarity.
2) Wrap the earth cable around the pipe to form a tight coil (approximately
20 turns). Set a 100 mm space between the edge of the coil and the
weld/pipe end being demagnetized.
3) Connect the positive terminal of the generator to a welding cable.
Complete the electric circuit by connecting the weld cable and the earth
cable with 4 – 6 mm diameter electrode.
4) Turn the generator on and gradually increase the current (make sure the
current setting was at 0 amp).
5) Hold the gauss meter near the area that had maximum reading and increase
the current slowly until a change in the meter is observed. If it is noted
that the magnetic field is increasing then switch off the power source
immediately and do step 6, otherwise do step 7.
6) Change the polarity on the generator and then turn the generator on and
gradually increase the current (make sure the current setting was at 0 amp).
7) When the current reaches 80 amps quickly increase the current to
300 amps and hold for ten seconds or until electrode breaks to cause
sudden interruption in the current. The interruption of the applied power
produces the required changes.
8) Switch off the welding generator in the normal manner and measure the
magnetic field strength and direction. Compare this reading with the
original readings of step 1. The field strength should be reduced to
between -20 Oe to +20 Oe and now welding can be performed using DC
welding without further demagnetization.
9) If the reading is greater than 20 Oe but less than 100 Oe there is a choice
of either applying Method I or II and welding using AC or continuing
further demagnetization by repeating the steps 1 – 8 in this method until
the magnetic field strength is between -20 Oe to +20 Oe.
10) If the reading is greater than 100 Oe, further demagnetization is necessary.
If the polarity has reversed, then repeat steps 1 – 8 until demagnetization
ID completed.
11) If the magnetic field changes only slightly then increase the number of
turns on the coil, thereby increasing the amp turns, and, repeat the whole
Page 6 of 9
Document Responsibility: Welding Standards Committee SAEP-37
Issue Date: 22 October 2011
Next Planned Update: 22 October 2016 Pipelines Residual Magnetism Removal
8.4 METHOD IV
Instructions:
1) Measure the magnetic field strength using gauss meter. Move the meter
around the weld circumference and mark the location that has the
maximum magnetic field strength then record the reading and the polarity.
2) Wrap a continuous length of cable around one side of the joint to form a
tight coil (approximately 12 turns) then drape the cable under the weld
joint and wrap it around the other side of the joint. The coil should be
wound in the same direction on both sides
3) Verify that the edges of the coils are within 500 mm of the root gap.
4) Connect the cable ends to the DC generator and verify that the polarity is
opposing the polarity observed in step 1.
5) Set the welding generator current to 0 amps and turn it on, read the field in
the weld gap using the gauss meter while slowly increasing the current
until the gauss meter reading is in the range of -20 Oe to +20 Oe.
6) If the reading on the gauss meter is increasing then stop the operation and
reverse the polarity on the generator. Do step 5 again.
7) Maintain that the current of demagnetizing generator throughout the
welding of the root pass.
Revision Summary
22 October 2011 New Saudi Aramco Engineering Procedure.
Page 7 of 9
Document Responsibility: Welding Standards Committee SAEP-37
Issue Date: 22 October 2011
Next Planned Update: 22 October 2016 Pipelines Residual Magnetism Removal
10 turns
minimum
100 mm
Pipe
AC Welding generator
earth cable
Pipe 100 mm
Side 1 Side 2
300 mm
apart
Weld
AC Welding generator
splitter
earth cable
Page 8 of 9
Document Responsibility: Welding Standards Committee SAEP-37
Issue Date: 22 October 2011
Next Planned Update: 22 October 2016 Pipelines Residual Magnetism Removal
20 turns
minimum 300 mm
Pipe 100 mm
Side 1 Side 2
earth cable
DC Welding generator
*if the work is to replace pipe section then after damage and welding of side 1, the same procedure should be applied to side 2
*if the damage is conducted to repair existing weld then no need to damage side 2
12 turns
minimum
500 mm
Pipe
Side 1 Side 2
earth cable
DC Welding generator
Page 9 of 9