= Production Part Approval Process
aaa
Fourth EditionPRODUCTION PART
APPROVAL PROCESS
(PPAP)
Production Part Approval Process (PPAP)
First Edition Issued February 1993
Second Edition, Ist Printing, February 1995; 2nd Printing, July 1995
Third Edition, September 1999; 2nd Printing, August 2000
Fourth Edition, March 2006
Copyright ©1993, ©1995, ©1997, ©1999, ©2000, ©2006
DaimlerChrysler Corporation, Ford Motor Company, General Motors CorporationFOREWORD TO THE FOURTH EDITION
Effective June 1, 2006, PPAP Fourth Edition replaces PPAP Third Edition, unless otherwise specified by
your customer.
Production Part Approval Process (PPAP) is updated to the 4 edition to incorporate the customer
focused process approach associated with ISO/TS 16949:2002 and other changes listed below to update
requirements,
PPAP?’s purpose continues to be to provide the evidence that all customer engineering design record and
specification requirements are properly understood by the organization and that the manufacturing
process has the potential to produce product consistently meeting these requirements during an actual
production run at the quoted production rate.
PPAP 4th Edition includes the following changes:
‘© Alignment of PPAP to the ISO/TS 16949:2002 process approach, including:
+ “Aligning the order of the PPAP requirements with the automotive product development and
manufacturing process
‘+ Inclusion of an example process flow for PPAP
‘* Relocation of Customer Specific Instructions to appropriate websites, (e.g. OEM and IAOB,
‘www. iaob.org) to provide current requirements
© Update of Truck OEM requirements and moved to Appendix H
‘+ Revised PSW (Part Submission Warrant) to:
‘+ Provide a more logical flow for the part / design description fields
‘+ Make the supplier address fields applicable to international locations
+ Include IMDS materials reporting to indicate reporting status
‘* Updated specific PPAP requirements, including:
+ Materials reporting and polymeric identification requirements in the design record
‘+ Process capability index usage (Cpk and Ppk)
+ The definition and approval of catalog parts and the definition of black box parts
© Modified customer notification and submission requirements to align with OEM requirements
(e-g., 1.3.3 from PPAP 3rd removed)
© Clarified and commonized Appendices C, D, and E to match the PPAP reporting requirements
© Revised Tire Appendix to allow OEM specification of applicability and to eliminate duplications
with allowances already provided in the PPAP requirements
Note: The Tire Appendia is not applicable to organizations supplying tires to Ford Motor Company
* Reorganized and updated Appendix F to stress the importance of the Bulk Materials Checklist
Note: Ford Motor Company requires all organizations supplying bulk material to Ford Motor Company to
comply with PPAP.
* Revised Glossary to be consistent with the updates in the text
PPAP refers to the following reference manuals: Advanced Product Quality Planning & Control Plan,
Potential Failure Modes and Effects Analysis, Measurement System Analysis, and Statistical
Process Control. These manuals are authored by DaimlerChrysler Corporation, Ford Motor Company,
and General Motors Corporation and are available through the Automotive Industry Action Group (AIAG)
at www.aiag.org.
The Supplier Quality Requirements Task Force gratefully acknowledges the contributions of the many
individuals and their respective companies that participated in the revision process.