NL Master Specification Guide For Public Funded Buildings: Revised 2010/09/02
NL Master Specification Guide For Public Funded Buildings: Revised 2010/09/02
PART 1 GENERAL
1.4 REFERENCES
.1 Canadian Standards Association (CSA)
.1 CAN/CSA-B139, Installation Code for Oil-Burning Equipment.
.2 Transport Canada - Marine Safety (TCMS)
.1 Approved Products Catalogue Index (APCI) - Structural Fire Prevention Item.
.1 Non-Combustible Material - Cloth and Paper.
.3 Underwriters' Laboratories of Canada (ULC)
1.5 QUALIFICATIONS
.1 Provide proof of diesel electric technician qualification to Owner’s Representative.
.12 Check phase sequence of normal power supply and ensure emergency power
supply are in same sequence.
.13 Check operation of electronic controller protection, transfer, timing, metering, and
annunciator functions and adjust as necessary.
.14 Check operation and calibration of analog metering and adjust as necessary.
.15 Apply electrical load, read the metres, and correlate these readings.
.16 Demonstrate:
.1 Unit start, transfer to load, retransfer to normal power, unit shutdown, on
"automatic" control.
.2 Unit start, transfer to load, retransfer to normal power, unit shutdown, on
"full load test" control. Unit start and shutdown, on "no load test" control.
.3 Unit cranking, start, and shutdown by means of engine-mounted key
switch.
.4 Run unit on load for minimum period of 8 hours to show load-carrying
capability, stability of voltage and frequency, and satisfactory
performance of engine ventilating system to provide adequate cooling.
.5 Every 1/2 hour carry out and record readings on Test Chart.
.17 Perform additional tests as required by Owner’s Representative to ensure unit is
operating satisfactorily.
1.8 COMMISSIONING
.1 Do site commissioning of the diesel electric generator unit by qualified diesel electric
technician in accordance with Section 01 91 13 – General Commissioning (Cx)
Requirements.
.2 Provide commissioning report including time delay settings, operational set points and
adjustment ranges.
PART 2 PRODUCTS
2.1 MATERIALS
.1 Provide following materials:
.1 Conduits and boxes as required.
.2 Fuel lines and fittings as required.
.3 ULC automatic fire shut-off valve.
.4 Primary fuel filter/water separator.
.5 Insulation for exhaust system.
.6 Electrical components as indicated.
NL Master Specification Guide
for Public Funded Buildings
Revised 2010/09/02 Section 26 32 13.03 – Installation of Electric Power Generating Equipment Page 4 of 7
.7 Wiring material.
.8 Antifreeze, ethylene glycol.
.9 Diesel fuel; storage and day tank initial fill, plus top-up after testing.
.10 Manual IPU bypass switch.
.11 All wiring and materials, including necessary rigid steel conduits and fittings for
making connections.
.12 The power circuit cables will be, RW90 (-40 degrees C) cross link polyethylene,
single or multiple conductors, PVC jacketed, size as indicated.
.13 The control circuit cables will not be less than No. 14, RW90, conductors, colour
or number coded.
.14 Electronic governor control cable shall be minimum size No. 18 stranded copper
conductor, shielded complete with drain wire and overall PVC jacket.
.15 Battery cable shall be welding cable type, extra flexible, rope stranded copper
conductor with neoprene oil-resistant insulation, sized to limit voltage drop to 5%
at time of peak load.
PART 3 EXECUTION
.2 Fit and adjust isolators in accordance with manufacturer's installation and adjustment
instruction bulletin contained in unit manual.
.3 Do not bolt housings to foundation if isolator housing feet are equipped with 6 mm rubber
sound pads.
.2 Where engine and generator housings are close coupled and instruments at hand are not
suitable for measuring alignment within confines of housings, just loosen engine and
generator hold down bolts and ensure that each foot is carrying proportionate amount of
weight and feet are level on base plate.
.2 Inspect thoroughly fuel tank and lines to ensure they are clean and free of foreign material
before connecting fuel system.
NL Master Specification Guide
for Public Funded Buildings
Revised 2010/09/02 Section 26 32 13.03 – Installation of Electric Power Generating Equipment Page 5 of 7
.3 Install primary fuel filter/water separator and servicing shut-off valves as indicated.
Provide 3 spare filter elements.
.4 Install ULC automatic fire shut-off valve. Locate upstream of any combustible fuel system
component.
.5 Install supply and return fuel lines between engine and fuel day tank. Install flexible
sections between the engine and fixed end of fuel lines from fuel tank, using materials
supplied with unit.
.8 Neatly install fuel lines parallel or perpendicular to building lines with no kinks or dents.
.9 Install soft drawn copper fuel lines using brass 45 degrees flare and pipe fittings as
required and bend with correct size lever type bending tool. Entirely replace leaking fuel
lines.
.2 For wet batteries, inspect individually each battery cell and check electrolyte level. Check
charge condition by measuring temperature and specific gravity of electrolyte. Consult
manufacturer's instructions for recommended readings. If readings are lower, give batteries
freshening charge until reading are reached.
.3 Locate batteries as indicated and ensure that batteries are accessible for service. Run and
protect cables to starting motor using cables supplied with unit.
.4 Install battery charger on wall, adjacent to batteries and make connection to batteries.
.2 Arrange silencer above and approximately in line with engine exhaust manifold with
exhaust tail pipe protruding through thimble in wall.
NL Master Specification Guide
for Public Funded Buildings
Revised 2010/09/02 Section 26 32 13.03 – Installation of Electric Power Generating Equipment Page 6 of 7
.3 Extend tail pipe not less than one metre beyond outside wall.
.4 Support silencer with hangers so no weight or stress is applied to engine exhaust manifold
or turbocharger.
.2 Division 25 to provide and install louvre motors and linkages, adjust to ensure louvres are
tight in closed position and give free damper movements from fully closed to fully open.
Coordinate with Division 25 – Integrated Automation.
.3 Where canvas boot is not provided, maintain 13 mm clearance between radiator and air
outlet duct.
.5 Install conduits and junction boxes and make connections from louvre motors to thermostat
and to 120/24 V AC transformer in panel.
.6 Fill engine radiator with water/ethylene glycol antifreeze mix good for -40 degrees C.
.7 Install remote radiator including piping, valves, fittings and pumps as indicated.
.4 Tag with slip-on wire maker, each wire end with number corresponding to number in
panel.
.3 Provide these services for such period, and for as many visits as necessary to put
equipment in operation, and ensure that operating personnel are conversant with aspects of
its care and operation.
.4 Provide fuel required for performing diesel-generator site test and top-up after acceptance
test completion.
END OF SECTION