Induction Training
Induction Training
5104
SPECIFICATION
DESIGN FOR Rev. No. 1
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 1 of 26
HSE REQUIREMENT
PREPARED/ REVISED
REVIEWED BY APPROVED BY TOTAL No.
BY DATE REV. No.
OF PAGES
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004A ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 2 of 26
CONTENTS
1. INTRODUCTION
1.1 Scope
1.2 Application of this Document
1.3 Purpose of this Document
2. DEFINITIONS / LANGUAGES
3. COMPLIANCE
3.1 Company Policy and Standards
3.2 Mandatory Indian Statutory Requirements
3.3 International Standards
4. HSE TARGETS AND GOALS
5. AUTHORITIES, ROLES AND RESPONSIBILITIES
5.1 Company Representatives
1.2 Key Roles and Responsibilities
5.2.1 Contractor’s Representative
5.3 Contractor’s Personnel
5.4 Company Site Representative
6. CONTRACTOR HSE MANAGEMENT
7. TRAINING AND COMPETENCY
7.1 Site Induction
7.2 Competency Requirements
8. HAZARD IDENTIFICATION, ASSESSMENT AND MANAGEMENT OF HSE
RISK
8.1 Operational Procedures
8.2 Job Hazard Analysis
8.3 Hazard Identification and Risk Management During Site Work
9. COMMUNICATION
9.1 Site Meetings
9.2 Daily Log and Reports
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 3 of 26
APPENDICES
APPENDIX 1 ITEMS TO BE INCLUDED IN CONTRACTOR’S HSE PLAN
APPENDIX 2 MONTHLY HSE REPORT
APPENDIX 3 MONTHLY INCIDENT FILE
APPENDIX 4 ENVIRONMENTAL ACCOUNTING FORM
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 4 of 26
1. INTRODUCTION
1.1 Scope
This document defines the health, safety and environmental (HSE) requirements
associated with the conduct of the Contractor’s scope of work for Well/Process
Platform Project.
This documents applies to all aspects of the Contractor’s scope of work, including all
aspects conducted by sub-contractors.
This document defines principal requirements for Health, Safety and Environment
(HSE) matters during the conduct of the Works.
The objective is to ensure that adequate precautions are taken to avoid accidents,
occupational illness and harmful effects on the environment during construction. Also
to assure that satisfactory emergency planning is undertaken and adequate means are
taken to secure contract objects.
This document:
2. DEFINITIONS / LANGUAGES
In this documents
3. COMPLIANCE
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 5 of 26
The works shall be undertaken in accordance with the Company’s HSE Policy and
Management System
The Works shall be undertaken in accordance with all applicable legislation and
mandatory Indian Statutory requirements.
The works shall be undertaken in with the standards and specifications listed below,
except where varied by agreement.
The HSE targets, goals and aims for the Works are to achieve :
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 6 of 26
This activities carried out by the Contractor shall completely fulfill the requirements of
the contractor himself, as well as the authorities, related to avoidance of loss of human
life or health, economic assets, the environment and the contract object.
This implies that the Contractor shall systematically work to HSE requirements in
accordance with established principles of quality assurance. Contractor shall ensure
management commitment and attention to HSE matters in all phases of the work.
Contractor’s organization shall reflect the implementation of HSE matters as a line
responsibility at all levels.
The Contractor shall comply with applicable legislation and ensure that employer
working on the contract object complies with the legislation. If the requirements stated
in this document are less stringent than or in conflict with the country’s legislation the
latter shall apply.
The Contractor has the overall responsibility for ensuring that the works are planned,
organized, performed and documented in compliance with the Contractor’s HSE
programme. The Contractor is also fully responsible for coordinating the HSE
activities of each employer (the contractor group and company) engaged on the works.
The contractor shall use ensure fitness of construction spread (man, material and
machine) valid for entire period of construction including :
a) Sea Survival certificate and fire fighting competency certificate for personnel
The Contractor shall ensure that each employer at the site plans, organizes, performs
and documents their own activities so that (his and other employer’s) personnel, the
environment and property are protected in accordance with the HSE plan.
The same responsibilities apply to the Contractor’s sub-contractors.
5.1 Company Representatives
The Contractor’s primary point of contact for HSE matters will be with the Company
Representative or designate.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 7 of 26
For HSE matters, at any site, the Contractor’s point of contact will be with the
Company Site Representative, who will report to the Company project manager.
The Contractor shall define the roles and responsibilities of the Contractor’s Personnel
to include following descriptions.
The Contractor shall ensure that its personnel are required to: -
• Be aware of the Works HSE goals and targets understand their HSE obligations
and take responsibility for their own HSE performance.
• Adopt a philosophy for all tasks of ‘think it through, before you do’.
• Work in compliance to procedures applicable to their work tasks.
• Stop work and advise their supervisor should circumstances arise which could
compromise the HSE integrity of the existing procedures.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 8 of 26
The Contractor HSE Plan and related documents which affect HSE performance,
including procedures and engineering calculations, shall be submitted for Company
review a minimum of twenty one (21) days prior to commencement of any work on site
to allow for document review by company.
Appendix 1 indicates the required contents of the HSE Plan for the works.
Prior to commencing work, the Contractor shall ensure that all personnel proposed for
the work have been given the necessary HSE and job related training required by law as
well as training in the applicable safety policies and procedures.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 9 of 26
The Contractor shall maintain all records of safety and environmental training and of
personnel job competency for the period of the Contract.
All Contractor personnel working offshore shall have satisfied the offshore training
requirements as specified by the Company.
Contractor shall ensure that all offshore going personnel/ work place personnel are
having following valid certified trainings: 1) Survival at Sea 2) Fire Prevention and
Fire Fighting 3) First Aid and 4) Helicopter Safety
Contractor shall also ensure that entries of undergoing of these trainings are made in
their site passport/ relevant document for site visit along with their photographs.
The Contractor shall ensure that all personnel working at the Site receive an
introductory briefing explaining the nature of the work, the hazards that may be
encountered during the Site Work and the particular hazards attached to their own
function within the operation.
All personnel shall be assessed for their understanding of the induction information and
will be required to meet a set level of understanding.
Contractor shall issue a personnel HSE handbook, which provides information on HSE
and emergency procedures that all personnel working on contract are required to know.
Contractor shall ensure that this is distributed and its content introduced to all personnel
working at the site. Visitors to the site shall be given adequate information on HSE
requirements applicable to the site.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 10 of 26
The Contractor shall ensure that all personnel are competent to perform the job
activities assigned to them. In the event that the Contractor is unable to demonstrate
the competency of any person whose activities can directly impact on the Works HSE
performance, that person shall be removed from the Site.
Where appropriate, vessels shall have appropriate procedures covering safe working
practices and vessel operations. These procedures shall be available for review by
Company and shall be submitted on request.
The Contractor shall provide equipment that is fit for purpose, complies with all
regulatory requirements and, where appropriate has current certification. Contractor
shall be able to demonstrate its adherence to these requirements.
The Contractor shall repair, remove or replace any of the Contractor’s equipment,
which in the opinion of the Company is a potential hazard.
The Contractor HSE Plan shall include procedures for performing job Hazard Analysis
(JHAs)
JHAs shall be performed in accordance with the Contractor HSE Plan for all activities,
which could affect the safety of personnel or equipment and/or affect the environment.
JHAs shall identify :
• Any safety environmental affects that have the potential to occur during Site
Work.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 11 of 26
JHAs covering all activities shall be held prior to mobilization to site at a time such that
they can be incorporated in the Approved operational procedures.
Copies of the JHA sheets shall be held on Site for as long as they remain applicable to
the activities being conducted.
During daily Site meetings the appropriate procedures associated with the impending
work activities and the JHAs relating to those procedures are to be reviewed in order:
• for them to be reviewed and updated as to that day’s activities by the personnel
performing the tasks and
• To ensure the potential hazards associated with the activities have been
understood as well as the measures to be taken to eliminate, control or mitigate
their risk.
Supervisors shall covey to their personnel (via toolbox meetings) the procedures to be
followed, including hazards and mitigation measures. Supervisors shall ask their
personnel whether they foresee any other hazards that have not been addressed and
shall address any concerns raised.
During operations, any person involved may request ‘time out’ for HSE if they consider
that HSE performance is or may be compromised. Where ‘time-out’ for HSE is
requested, action shall be taken by the supervisor to resolve the HSE concerns. This
may include conducting toolbox meetings, JHAs or other HSE techniques, prior to
restarting the operation.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 12 of 26
As a minimum, the Contractor HSE plan shall include aspects such as the operation of a
Permit to work system, procedures for isolation of equipment and the management of
change systems for updating procedures.
9. COMMUNICATION
The Contractor’s Representative shall convene daily meetings with the Company Site
Representative, Contractor’s supervisory personnel and where applicable other
applicable supervisory personnel (eg. Vessel Masters during transportation and
installation phases) to plan and coordinate the day’s activities. The meetings shall be
minuted. Where feasible, both persons occupying a position and working back-to-back
shifts shall attend these meetings. These meetings shall:
• Review progress on incidents, near misses and hazards that have been reported.
• Identity and agree implementation of any lessons, equipment or operational
changes which may arise from incident or hazard reports.
• Identify the procedures applying to the next 24 hours of work and manage any
changes required to them.
• Review the HSE hazards and associated control measures to be confronted within
the next 24 hours of work.
A daily log of all HSE activities including incidents, inductions, JHAs, toolbox meeting
and other safety initiatives shall be recorded and maintained by the Contractor. The
daily log will be available to the Company at all times. At the end of the Site Work a
copy of the log shall be submitted to Company.
Safety and environmental incidents and any other major HSE item shall be included in
the daily report from the Vessel.
HSE hand books shall be prepared and distributed by the contractor to all personnel on
board and at other work sites
The Contractor will facilitate the effective operation of a Site HSE Committee
conducted in compliance with relevant regulatory requirements.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 13 of 26
Contractor shall prepare safety plot plans for the site and for the contract object,
showing escape ways, mustering stations and the location of fire fighting and first aid
equipment. The plot plans shall be kept undated and be posted at all main entrances on
each level of the works sites.
9.5 Display boards shall be placed at a prominent location at work site indicating the total
number of hot jobs for the day.
The Contractor shall report on and investigate any incident near miss or hazard
occurring at the site in accordance with the procedure in the Contractor HSE Plan.
An Incident Report pro-forma is to be included in the Contractor HSE Plan and shall be
used on site if an incident or near miss occurs.
The Contractor’s incident reporting procedure shall include the following notifications:
• The Company site Representative will verbally notify the Company project
manager of an incident necessitating medical treatment (i.e. treatment extending
beyond first aid) or an environmental incident as soon as possible but within four
(4) hours of the incident occurring.
• The company Site Representative will fax or e-mail the Contractor’s Incident
Report to the Owner project manager within 15 hours of the incident occurring.
• Company will determine if there is a requirement to report an incident to
Authorities.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 14 of 26
The Contractor shall prepare an Emergency Response Plan for all work sites and
marine vessels as part of the Contractor HSE Plan.
The plan shall integrate the emergency response plans of the Contractor, any involved
subcontractors, and any marine vessel plans. The Emergency Response Plan shall
detail the Contractor’s procedures, including detailed communications arrangements,
for dealing with all emergencies that could affect the Site. This include where
applicable, injury, sickness, vessel evacuation, fire, fuel or chemical spillage, severe
weather and search and rescue.
At the conclusion of the works at any site, the Contractor shall provide the Company
site Representative with a report of the performance against the Works HSE targets.
All progress reports are to include HSE issues, performance against targets and
activities.
As part of regular monthly reporting, contractor shall provide a monthly report with a
summary of reported incidents. The report shall be forwarded to company not later
than 3 work days after monthly out-off date, unless otherwise instructed by company.
The report shall contain at least the following information for the personnel working at
the site and for principal subcontractors working off-site unless otherwise instructed by
Company.
• Number of incidents
- Total number of incidents
- Occupational injury (total number)
- Environment
- Material (fires and explosions, other)
- Production loss.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 15 of 26
Accident all reported files and explosions and occupational illnesses shall be listed,
together with the preventive measures, as a part of the HSE report. The forms shown in
Appendices 2 and 3 or similar shall be used.
In addition, the report shall give a summary of site HSE related activities during the
month such as audits, inspections, HSE motivation and training etc. Contractor shall
keep a file of restricted work cases. Compliance with established HSE goals shall also
be measured and reported.
Quarterly, Contractor shall upon request submit a sickness leave report showing
Contractor’s own employees overall sickness leave in percentage of possible working
days.
13.1 Audits
Formal audits by Company will be undertaken and Contractor shall provide full
cooperation in these audits.
In addition, the Company Site Representative will monitor the Contractor compliance
with the Contractor HSE Plan, procedures and ITPs. In the event of a breach of the
plans and procedures, the Company site Representative will order the cessation of Site
Work and formally issue a corrective action request. Work may re-commence when it
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 16 of 26
is safe to do so and when an action or process to achieve compliance has been agreed
by the Company Site representative and the Contractor.
Audits instigated by the Contractor are encouraged and Company may elect to
participate if invited.
13.2 Inspections
Contractor shall establish a HSE inspection plan to ensure safe working conditions and
compliance with rules and regulations. The plan shall identify participants and
frequencies. Line management and safety representative of the workers shall
participate as a minimum and regular participation by site middle and top management
shall be ensured.
The Contractor is required to investigate the environmental effects and issues arising
from the Works and to identify these and any mitigating actions are required to be
included in the Contractor HSE Plan for the work.
Waste management strategies for all aspects of the project shall be described in the
HSE Plan.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 17 of 26
The Contractor shall provide first aid facilities and first aid personnel in accordance
with the applicable legislative and guidance requirements.
16. HEALTH
16.1 Smoking
Smoking shall only be permitted in designated smoking areas detailed in the Contractor
HSE Plan.
The Contractor shall have a drug and alcohol policy, which shall be described in the
Contractor HSE Plan.
Alcohol and drugs (other than drugs required for bonafide medical reasons) shall not be
permitted on Site.
The Contractor’s Representative shall ensure that personnel under their supervision and
authority do not at any time during the performance of the work, take or work under the
influence of any alcoholic liquor, narcotic or other intoxicating substance, other than
drugs required for bonafide medical reasons which have been approved in advance by
either the Company Site Representative or the Contractor’s Representative. Reporting
for work under the influence of any alcoholic liquor, narcotic or other intoxicating
substance may result in removal from the site and or dismissal.
Persons carrying medically prescribed drugs shall report these to the Contractor’s
Representative and in the case of work on marine vessels, to the Vessel Master.
Persons consuming non-medically prescribed but legal drugs which have attendant side
effects (eg. Drowsiness) shall report these to the Contractor’s Representative and in the
case of work on marine vessels to the Vessel Master.
The Contractor HSE Plan shall include requirements for personal protective equipment
that shall apply to Contractor’s and its subcontractor’s personnel. This equipment shall
meet to the following requirements :
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 18 of 26
For site work required to be performed on a 24 hour basis, sufficient personnel shall be
allocated to the Works to ensure that the work time of each person does not exceed 14
hours per 24 hour period, except in the case of emergencies.
16.5 Harassment
Harassment of persons shall not be permitted and during the Contractor’s HSE
inductions the Contractor shall explain what constitutes harassment and the measures to
be taken when it occurs.
When Work is conducted on or in the Vicinity of Well Platform, the Contractor shall
comply with the Company’s policies and procedures for these areas.
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 19 of 26
Contractor’s HSE Plan shall be adapted to the site in question, taking into account the
work to be carried out during the different project phases, local conditions, emergency
preparedness, communications etc. ONGC’s HSE policies as per ISRS system shall be
provided to the successful bidder for incorporation in the HSE policy/plan. The HSE
Plan shall when relevant also cover the items listed below.
3.1 Procedures
• Coordination of contractor group’s activities
• Coordination with company
• Handling of incidents
• HSE inspections
• Constructability evaluations
• Risk assessment
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 20 of 26
3.2 Requirements
• Mandatory personal protective equipment
• Notification of incidents (accidents and near accidents) and unsafe conditions
• Electrical installations/use of electrical equipment
• Radioactive materials
• Work permits e.g. hot work, safe work (electrical locks, pressure testing, pad
locking, blinding of piping etc.) entering of tanks and vessels, forms for work
permits.
• Rigging and crane safety, certification
• Scaffolding, ladders
• Working and emergency lighting
• Protection against chemical exposure (gases, dust, solvents vapour etc.)
• Provisions for good order, housekeeping
• Internal regulations regarding littering, pollution
• Temporary cables, hoses and equipment
• Signs, barricades
• Provisions regarding alcohol and drugs
• Prevention of fires, fire guards
• Storage and use of explosives and combustibles
• Storage and use of chemicals/noxious substances
• Smoking restrictions
• Infringement of safety provisions
• Evaluation of personnel from contract object
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 21 of 26
5. Security
• Security provisions
• Perimeter guarding
• Restricted areas
• Checks of entries and exists
• Visitors
• Photography
• Sabotage
• Criminal acts
• Espionage
• Original documents and drawings
• Confidentiality
• Data security
6. Emergency Preparedness
• Organization Plan (during / Outside office hours)
- Personnel
- Line of command
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 22 of 26
6.1 Appendices
• Site safety plot plan
• Safety plot plan for contract object
• Map showing location of waste skips and storage facilities
• Safety data sheet index (copy to company representative)
• Discharge permits
• Personal HSE handbook
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 23 of 26
Note 1 : Including lost work days this month from earlier injuries.
Date: Signature
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 24 of 26
Date: Signature:
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 25 of 26
Strong acids
Strong alkalic
compounds
Other organic
substances (Specify)3)
Aerosol cans
Other (Specify if
relevant)
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003
OFFSHORE SPEC No. 5104
SPECIFICATION
DESIGN FOR Rev. No. I
SECTION HSE REQUIREMENT
Discipline Mechanical
Page 26 of 26
Notes :
FORMAT No. Ref. PROCEDURE No. ISSUE No. REV. No. REV. DATE:
ODS/SOF/004B ODS/SOP/008 TO 015 01 01 15/10/2003