PROJECT : PTA
CLIENT : JBF
PMC :TECHNIP INDIA LMITED
PROJECT NO :830
UNIT NO: OSBL
REPORT NO: DATE:
FORMAT-I
INTIMATION REGARDING NON-PROCESS / PROCESS SYSTEM COMPLETION
Following Non-process system / Process system has been mechanically completed in all
respects with exceptions noted below. The Non-process system / Process system can be
taken up for checking and preparation of checklist.
Non-Process / Process System No :
Description Drawing no.
Exceptions:
1
NOTE: REFER ANNEXURE -A OR B TO FORMAT -I
Performed by: Checked by: Approved by:
Signature:
Name:
Date:
CONTRACTOR TECHNIP JBF
QUALITY CONTROL FORM :TPIL/JBF/SITE-04A
PROJECT : PTA
CLIENT : JBF
PMC :TECHNIP INDIA LMITED
PROJECT NO :830
UNIT NO: OSBL
REPORT NO: DATE:
ANNEXURE-A TO FORMAT-I (PROCESS SYSTEM)
SIGNATURE
APPLICABLE /
SL NO. DESCRIPTION NOT
APPLICABLE
Format No No Of sheets
CONTRACTOR TP JBF
REMARKS
1 Mark up P&ID
2 MC Filled Format
Pressure test / Pneumatic test
3 report
4 Punch List
5 Flage joint history sheet
Equipment allignment report
6a. Static
6
6b. Rotary - Without Piping
With Piping
7 Final Box up report
List of Instrument
8 8a. Instrument Installation report
8b.Instrument Calibration Report
8c. Instrument Cold loop Checking
8d. Instrument Hot loop Checking
List of Electrical items
9a. Electrical items Installation
9 report
9b. Motor / other No load run
Report
10 Insulation Report
PLEASE FILL ALL THE BLANK AREAS
Performed by: Checked by: Approved by:
SIGNATURE:
NAME:
DATE:
CONTRACTOR TECHNIP JBF
QUALITY CONTROL FORM :TPIL/JBF/SITE-04B
PROJECT : PTA
CLIENT : JBF
PMC :TECHNIP INDIA LMITED
PROJECT NO :830
UNIT NO: OSBL
REPORT NO: DATE:
ANNEXURE-B TO FORMAT-I (NON-PROCESS SYSTEM)
SIGNATURE
APPLICABLE /
SL NO. DESCRIPTION NOT Format No Of REMARKS
APPLICABLE No sheets CONTRACTOR TP JBF
1 Civil
POUR CARD ALONG WITH
a SUMMARY SHEET
b CHECK LIST FOR BULIDING
c Water Fill Test Report
d EPOXY SCREEDING REPORT
Electrical
2 (Final Comssioning
Report)
a Lighting
b Cabling
c Earting
d PA System
e FA System
f Telephone System
Instrument
3 ( Final Comssioning
Reprt)
a Cabling
b Gas Detection System
c Sprinkler System
d Fire Alarm System
4 Punch List
5 As Built Drawing
PLEASE FILL ALL THE BLANK AREAS
Performed by: Checked by: Approved by:
SIGNATURE:
NAME:
DATE:
CONTRACTOR TECHNIP
JBF