SFM Formulas Sheet For Quick Revision Before Exam
SFM Formulas Sheet For Quick Revision Before Exam
SFM M n A FM
Sheet forFormulae
Quick Revision
1. Capital Budgeting
TYPES OF CAPITAL BUDGETING PROPOSALS
If more than one proposal is under consideration, then these proposals can
be categorised as follows:
OR
Annuity (A) = Present Value (P V) X Cost of Capital (K)
Risk Adj. Disc. Rate (RADR): Risk free rate (Rf)+ Risk Premium
OR
Risk Adj. Disc. Rate (RADR): Risk free rate (Rf)+ β X Risk Premium
𝐒𝐃 𝐒𝐃
Coefficient of Variation = =
𝐄𝐱𝐩𝐞𝐜𝐭𝐞𝐝 𝐍𝐏𝐕 𝐀𝐯𝐞𝐫𝐚𝐠𝐞 𝐍𝐏𝐕
Page 4 of 32
The lower coefficient of Variation, the better it is.
OR
Initial Investment
Pay Back Period =
Annual Cash flows
Accept the Project with least Payback Period.
Where A‾t is the expected cashflow in period t and Rf is risk free rate of
interest.
Project NPV is the one which is calculated for the whole Project. Equity NPV
is the one which is calculated to know the return of equity holders. In this
case funds relating to equity holders alone are considered for computation.
I R R is the rate at which the present value cash inflows equal the present
value of cash outflows i.e. NPV is zero. For Project IRR all cashflows of the
project are considered and in case of Equity IRR only cashflows relating to
equity holders are considered. In case IRR is greater than interest rate on
loan, then, the excess rate will accrue to the benefit of equity holders.
Page 5 of 32
Standard Deviation = Variance1/2
𝒏
𝝈𝟐 𝒕
𝝈=
(𝟏 + 𝑹𝒇 )𝟐𝒕
𝒕=𝟏
𝒏
𝝈 = 𝒕=𝟏(𝑵𝑷𝑽 − 𝑵𝑷𝑽‾)𝟐 𝑷𝒕
In case if two or more projects have same mean cashflows, then, the project
with lesser standard deviation is preferred.
Joint probability: Joint Probability is the product of two or more than two
dependent probabilities. Sum of Joint Probabilities will always be equal to 1.
Conditional Event: If A & B are two events, then, if event B occurs after
occurrence of event A, it is called conditional event and is denoted as (B/A)
P(A ∩ B)
P(B/A) = ⇨ P A ∩ B = P A X P(B/A)
P(A)
Notation of Events:
Event A or Event B Occurs AUB
Event A & Event B Occur A ∩ B
Page 6 of 32
c c c
Neither A Nor B Occur (A U B) = A ∩ B = A‾ ∩ B‾
A Occurs but B does not Occur A ∩ Bc = A / B
2. Leasing
Evaluation of lease for Lessee: In this case comparison is to be made
between the NPV of outflows:
a. in case an asset is leased and used, or
b. the asset is bought and used.
BELR for lessor is the amount at which he will be indifferent between buying
the asset and giving it for lease and / or investing the funds elsewhere and
earning desired cost of capital.
While ascertaining Present Values, people are using different rates for
discounting like interest rate, net of tax interest rate, cost of capital etc.
based on respective views. Ideal one will be the one using net of tax
interest rate in case of borrowing or using the cost of capital in case of using
own funds.
3. Dividends
Page 7 of 32
Traditional Theory:
𝐦(𝟒𝐃 + 𝐑) 𝐄
𝐏= = 𝐦(𝐃 + )
𝟑 𝟑
Where, P = Mkt. Price of share; D = Dividend per share; R = Retained
Earnings per share; E= EPS & m = a constant multiplier.
Walter Model:
𝐫 (𝐄 –𝐃)
𝐃+
𝐤
P=
𝐊
Gordon Model:
𝐃𝟏 𝐃𝐨 (𝟏 + 𝐠) 𝐄 (𝟏 − 𝐛)
𝐏𝐨 = = =
𝐊−𝐠 𝐊−𝐠 𝐊 − 𝐛𝐫
Where, P0 = Mkt. Price per share before dividend; D1 = Dividend per share
in year 1; D0 = Dividend per share in current year; k = cost of equity; g =
growth rate of dividends; E = EPS, b = % of earnings retained; and r =
Return on internal retentions
g=b*r
Page 8 of 32
If r < k, then also share price will increase because Div. Payout increases.
Optimal payout ratio will be for:
A growth co. (i.e r > k) is nil.
A normal co. (i.e. r = k ) is irrelevant, and
A declining (i.e. r < k) firm is 100%
Modigliani-Miller (M M) Model:
If dividend is declared;
𝐏𝟏 + 𝐃𝟏
𝐏𝟎 = ⇨ 𝐏𝟏 = 𝐏𝟎 𝟏 + 𝐊 − 𝐃𝟏
𝟏+𝐊
If dividend is not declared;
𝐏𝟏
𝐏𝟎 = = ⇨ 𝐏𝟏 = 𝐏𝟎 𝟏 + 𝐊
𝟏+𝐊
Where, P0 = Current Mkt. Price of share; P1 = Mkt. Price at the end of
period 1; K= Cost of capital; D1 = Div. In year 1.
Lintner Model:
D1 = D0 + [(EPS * Target payout) – D0] * Af
D1 = Div. In year 1; D0 = Div. In year 0; Af = Adj. Factor
Page 9 of 32
c. Variable growth rate model: Usually the three stages of growth,
the initial high rate of growth, a transition to slower growth, and
lastly a sustainable steady growth are considered. For each type of
stage, appropriate variables are considered and PVs‟ are calculated
and sum of the three PVs‟ is the intrinsic value of share.
Holding Period Return: This is the sum of dividend yield and capital gain
yield which is nothing but Total Yield.
𝐃𝟏 𝐏𝟏 − 𝐏𝟎
Total Yield = +
𝐏𝟎 𝐏𝟎
4. Capital Markets
𝐓𝐨𝐝𝐚𝐲 ′ 𝐬 𝐌𝐚𝐫𝐤𝐞𝐭 𝐂𝐚𝐩𝐢𝐭𝐚𝐥𝐢𝐬𝐚𝐭𝐢𝐨𝐧
𝐓𝐨𝐝𝐚𝐲 ′ 𝐬 𝐈𝐧𝐝𝐞𝐱 𝐕𝐚𝐥𝐮𝐞 = 𝐗 𝐘𝐞𝐬𝐭𝐞𝐫𝐝𝐚𝐲 ′ 𝐬 𝐈𝐧𝐝𝐞𝐱 𝐕𝐚𝐥𝐮𝐞.
𝐘𝐞𝐬𝐭𝐞𝐫𝐝𝐚𝐲 ′ 𝐬 𝐌𝐚𝐫𝐤𝐞𝐭 𝐂𝐚𝐩𝐢𝐭𝐚𝐥𝐢𝐬𝐚𝐭𝐨𝐧
The difference between the prevailing price and futures price is known as
basis.
Basis = Spot Price – Future Price
In a normal market, spot price will be less than future price as future price
includes cost of carrying also. Further, apart from carrying cost the future
price may also change due to dividends etc. So,
A = P (1+r/100n)nt
In case the compounding is more than once on daily basis, then the formula
stands modified as:
A = P * ern
Where e is called epsilon, a constant and its value is taken as 2.72
Page 10 of 32
Alternatively,
Future Value = Present Value * ert
In case any income flows are there, then they are to be deducted and the
formula will be:
A = (P – I) * ern
Where I is the present value of income inflow.
If the income accretion is in the form % yield y (like in index futures) then
the formula is:
A = P * e(r-y)n
Options Seller is called Writer or Grantor and the buyer is called simply
buyer or at times as dealer / trader.
In case of an option buyer, while there is no limit on the profit he can make,
loss is limited to the value of premium he pays to buy the option. In
problems, if premium is not given, loss is to be taken as zero. It will be
opposite in case of option seller i.e. Writer or Grantor.
Intrinsic Value and Time Value of Option: Option premium has two
components viz. Intrinsic Value and Time Value. Intrinsic Value is the
difference between Exercise price and Market price or Zero whichever is
higher. Time Value is the excess of Option price over its Intrinsic Value.
European Option can be exercised only on the due date of the option.
American Option can be exercised at any time during the period of option.
TIME IS THE ALLY OF WRITER AND ENEMY OF OPTION BUYER SINCE IN THE
LONG RUN GOOD STOCKS WILL USUALLY DO BETTER.
Black-Scholes Model:
𝐗 𝐍(𝐝𝟐 )
𝐎𝐏 = 𝐒 𝐍(𝐝𝟏 ) – , And
𝐞𝐫𝐭
𝐥𝐧 S + (𝐫 + 𝐯𝟐 ) 𝐭
𝟐
𝐝𝟏 =
X
𝟏/𝟐 𝐯𝐭
𝐒 𝐯𝟐
𝐥𝐧 +(𝐫 − )𝐭
𝐝𝟐 = 𝐗 𝟐
= 𝐝𝟏 − 𝐯𝐭 𝟏/𝟐 where,
𝐯 𝐭 𝟏/𝟐
Page 11 of 32
S = Current Stock Price
X = Strike Price,
r = Continuously Compounded Risk free Interest Rate
t = Balance period of option expressed as percentage,
N(d1) = Normal distribution of d1
N(d2) = Normal distribution of d2
ln = Natural Logarithm
e = exponential constant with value 2.72,
v = Volatility of stock, i.e. Standard Deviation
N(d1) is the hedge ratio of stock to options, to keep the writer hedged and
N(d2) / ert is Present Value of the borrowing.
The above formula can be used to find the Value of Equity also with little
changes. In this case, in the place current stock price we need to use
current value of business and in the place of strike price we need to use
value of debt. Rest of all the things are same.
Binomial Model:
𝐮𝐕𝐭+𝟏
Up tick 𝐮𝐭 = 𝐮𝐕𝐭
𝐝𝐕𝐭+𝟏
Down tick 𝐝𝐭 = 𝐝𝐕𝐭
Where uVt = up tick value in period t; uVt+1 = uptick value in period t+1.
Similarly, dVt & dVt+1 for down ticks.
Where e is epsilon (with value 2.72) and t is time period. Please note that
the t in rt indicates time period whereas the t in ut and dt indicates tick.
Page 12 of 32
Put Call Parity Theory: This theory holds good only when exercise price
and maturity of both put and call options are same.
Initial margin = D + 3 SD
Where, D = Daily Avg. Price, and SD is Standard Deviation of the
instrument.
TIME IS THE ALLY OF WRITER AND ENEMY OF OPTION BUYER SINCE IN THE LONG RUN GOOD STOCKS
WILL USUALLY DO BETTER.
Straddle means buying a Call Option and Put Option with same exercise
price and expiry date.
Strangle means buying a Call Option and buying a Put Option with same
expiry date but different exercise prices.
Butterfly Strategy: In this one buys a call option at price S+a and another
at price S-a. Then 2 call options are sold at price S. All calls are contracted
for same maturity date. The buyer of calls makes profit when the market
price lies between S+a and S-a. if the market price is outside the range
then he will not make any profit and loss will be to the extent of net of
premium paid and received on the four options. This strategy will give
limited profits with limited risks. Profits will be maximum when market price
is nearer to spot price. S means Spot price.
Page 13 of 32
Caps: Caps means setting the upper limit .Usually the upper limit is set by
Strike Price of a Call purchased
Floor: Floor means setting the lower limit .Usually the lower limit is set by
Strike Price of Put sold.
Collar: Combination of Caps and Floor is known as Collars .
Greeks:
Delta is the sensitivity of option price due to change in the value of the
underlying by a unit.
Gamma is the sensitivity of option price due to change in Delta.
Theta is the sensitivity of option price due to change in expiry date by a
day.
Rho is the sensitivity of option price due to change in interest rate.
Vega is the sensitivity of option price due to volatility of the underlying
asset.
5. Securities
Moving Averages: Moving averages of prices are plotted to make buy sell
decisions. Arithmetic Moving Average (AMA) is the simple average of the
available prices. In case of Exponential Moving Average (EMA) more
weightage is given to current results as against older results. The reduction
of weightage is done through a constant known as exponential smoothing
constant or Exponent. EMA is calculated by the formula:
Page 14 of 32
Required. Rate of return; n = maturity period; and 2n = maturity period
expressed in terms of half yearly periods;
Yield to maturity: The rate of return one earns is called the Yield to
Maturity (YTM). The YTM is defined as that value of the discount rate (“kd”)
for which the Intrinsic Value of the Bond equals its Market Price (Note the
similarity between YTM of a Bond and IRR of a Project). YTM is also known
as COST OF DEBT or REDEMPTION YIELD or IRR or MARKET RATE OF
INTEREST or MARKET RATE OF RETURN or OPPORTUNITY COST OF DEBT.
YTM and Bond value have inverse relationship. i.e. if YTM increases Bond
value will decrease and Vice versa.
Page 15 of 32
Where, D = Duration;
r = Required yield;
n = Number of years; and
c = Coupon rate
Macaulay duration is the weighted average time until cash flows are
received, and is measured in years.
𝐧 𝐭∗𝐂 𝐧∗𝐌
Macaulay Duration (in years) =[ 𝐭=𝟏 (𝟏+𝐢)𝐭 + ] / P where,
(𝟏+𝐢)𝐧
𝐌𝐚𝐜𝐚𝐮𝐥𝐚𝐲 𝐃𝐮𝐫𝐚𝐭𝐢𝐨𝐧
𝐕𝐨𝐥𝐚𝐭𝐢𝐥𝐢𝐭𝐲 𝐨𝐫 𝐌𝐨𝐝𝐢𝐟𝐢𝐞𝐝 𝐃𝐮𝐫𝐚𝐭𝐢𝐨𝐧 𝐨𝐫 𝐒𝐞𝐧𝐬𝐢𝐭𝐢𝐯𝐢𝐭𝐲 (%) =
𝐘𝐓𝐌
Macaulay duration and modified duration are both termed "duration" and
have the same (or close to the same) numerical value, but it is important to
keep in mind the conceptual distinctions between them. Macaulay duration is
a time measure with units in years whereas, Modified duration is a derivative
(rate of change) or price sensitivity and measures the percentage rate of
change of price with respect to yield.
Zero Coupon Bond will have Macaulay Duration equal to maturity period.
Self Amortising Bonds: These are bonds which pay principal over a period
of time rather than on maturity.
Inflation Bonds: These are bonds where coupon rate is adjusted according
to inflation. That is investor gets inflation free interest. Suppose coupon
rate is 8% and inflation 6%. Then investor will get 14.48%.
If value of Bond > Market price, then Buy and vice versa.
Page 16 of 32
Bond with variable yield rates: In case a bond has different yields of Y1,
Y2 & Y3 in 3 years, then value of bond is calculated by the formula:
Callable Bond is the one where the issuer has an option to call back and
retire the bonds before maturity date.
Puttable Bond is the one where the investor has an option to get the Bond
redeemed before maturity.
6. Portfolio Management
Variance:
𝐧 𝟐
Variance (Sd2) = 𝐢=𝟏[ 𝐗𝐢 − 𝐗 ∗ 𝐏𝐢 (𝐗 𝐢 )] Where,
𝐑 𝐀 −𝐑̅𝐀 (𝐑 𝐁 −𝐑̅𝐁 )
CovAB =
𝐍
Page 17 of 32
RA = Return on security A;
R‾A = Expected or mean return of Security A;
RB = Return on security B;
R‾B = Expected or mean return of Security B.
𝐂𝐨𝐯𝐀𝐁 = βA βB sdm2
𝐂𝐨𝐯𝐀𝐁
rAB = ⇨ 𝑪𝒐𝒗𝑨𝑩 = rAB 𝑺𝒅𝑨 𝑺𝒅𝑩 where
𝐒𝐝𝐀 𝐒𝐝𝐁
Page 18 of 32
Calculation of risk In case of only 2 securities, A & B in portfolio, then
Variance of portfolio is given by the formula
𝒏 𝒏 𝒏 𝒏
Sdp2 = 𝒊=𝟏 𝒊=𝟏 𝑿𝒊 𝑿𝒋 𝑪𝒐𝒗𝒊𝒋 = 𝒊=𝟏 𝒊=𝟏 𝑿𝒊 𝑿𝒋 𝒓𝒊𝒋 𝑺𝒅𝒊 𝑺𝒅𝒋 where,
Page 19 of 32
Calculation of Beta: Covariance Method
𝛂 = 𝐘 − 𝛃𝐗 Where,
n = number of items;
X = Independent variable (market);
Y = Dependent variable (security);
XY = product of dependent and independent variable;
X͞ & Y‾ are respective arithmetic means
𝒏
Portfolio Beta, βp = 𝒊=𝟏 𝒙𝒊 β𝒊
βp = Beta of portfolio;
Page 20 of 32
xi = proportion of funds invested in each security;
βi = Beta of respective securities; and
n = number of securities.
Since beta is the relative return of a security vis a vis market return, it can
also be calculated by the formula:
For Risk Free securities like GOI Bonds, T Bills etc. Beta is taken as ZERO
(unless otherwise given) implying non existence of Systematic Risk.
In case of change in capital structure, the company beta will not change but
only the components of debt beta and equity beta will change.
𝒏
Portfolio Return, rp = 𝒊=𝟏 𝒙𝒊 𝒓𝒊 Where
Page 21 of 32
Rm = Return on market index or Risk Premium
Rf = Risk Free rate
α = Return of the security when market is stationary
β = Change in return of individual security for unit change in return of
market index.
Security market line measures the relation between systematic risk and
expected return. Formula for Security Line is:
y = 𝜷x +𝜶 Where,
On Return Basis:
Expected Return < CAPM Return; Sell, since stock is overvalued.
Expected Return > CAPM Return; Buy, since stock is undervalued
Expected Return = CAPM Return; Hold.
On Price Basis:
Actual Market Price < CAPM price, stock is undervalued; so Buy
Actual market Price > CAPM price, stock is overvalued; so, sell.
Actual market Price = CAPM price, stock is correctly valued.;
Point of indifference.
Page 22 of 32
Beta in case of Leverage:
βl = Leveraged β
βul= Unleveraged β
D = Debt; E = Equity, and T = Rate of Tax
Equity Beta will be always greater than debt beta as risk of equity holders is
greater than risk of debenture holders.
Risk free securities are Government Securities, T Bills, RBI Bonds etc.
Arbitrage Pricing Theory Model: Uses 4 factors Viz., Inflation and money
supply, Interest Rate, Industrial Production, and personal consumption.
Under this method, expected return on investment is:
𝟐
Sdp2 = [( 𝒏 𝟐
𝒊=𝟏 𝑿𝒊 𝜷𝒊 ) 𝑺𝒅𝒎 ] +[ 𝒏 𝟐 𝟐
𝒊=𝟏 𝑿𝒊 𝑼𝑺𝑹 ] Where,
(Please note the difference between the above formula and the following
formula indicated elsewhere above. Sdp2 = [XA2 SdA2 + XB2 SdB2] +2 [XAXB (rAB 𝑺𝒅𝑨 𝑺𝒅𝑩 )].
This formula is used when 2 scrips are there and USR is not given)
Sharpe and Treynor ratios measure the Risk Premium per unit of Risk for
a security or a portfolio of securities for comparing different Securities or
Portfolios. Sharpe uses Variance as a measure whereas, Treynor uses Beta
as a mesure to compare the Securities or Portfolios.
Jensen’s Alpha: This is the difference between portfolio‟s return and CAPM
return.
Jensen Alpha = Portfolio Return – CAPM Return.
Sharpe’s Optimal Portfolio: Steps for finding out the stocks to be included
in the optimal portfolio are as below:
a. Find out the “excess return to beta” ratio for each stock under
consideration.
b. Rank them from the highest to the lowest.
c. Calculate Ci for all the stocks/portfolios according to the ranked order
using the following formula:
Page 25 of 32
USR = Unsystematic Risk i.e., variance of stock movement not related
to index movement.
d. Compute the cut-off point which the highest value of Ci and is taken as
C*. The stock whose excess-return to risk ratio is above the cut-off
ratio are selected and all whose ratios are below are rejected.
e. Calculate the percent to be invested in each security by using the
following formula:
𝒁𝒊
% to be invested = 𝒏 Where,
𝒊=𝟏 𝒁𝒊
𝜷𝒊 𝑹𝒊 −𝑹𝒇
Zi = 𝟐( − 𝑪∗ )
𝑼𝑺𝑹 𝜷𝒊
Run Test: If a series of stock price changes are considered, each price
change is designated + if it represents an increase and – if it represents a
decrease.
A run occurs when there is no difference between the sign of two changes.
When the sign of change differs, the run ends and new run begins.
Price Incr. / Decr. +,+,+,-,-,+,-,+,-,-,+,+,+,-,+,+,+,+
Run 1 2 345 6 7 8 9
Page 26 of 32
𝟐 𝐍+ 𝐍−
µ= + 𝟏
𝐍
Fifthly, Standard deviation, σ is calculated by the formula:
µ − 𝟏 (µ − 𝟐)
𝛔=
𝐍−𝟏
Sixthly, If the sample size is N, then it will have (N - 1) degrees of
freedom. For this particular degrees of freedom, and the given level of
significance, using the value „t‟ from t-table, Upper and Lower limits are
found by the formula:
Upper / Lower Limit = µ ± t * 𝛔
Lastly, If the value of r falls within the upper and lower limits, it is called
weak form of efficiency, and if it falls outside the limits, it is called strong
form of efficiency.
7. Mutual Funds
Net Assets of the Scheme is calculated as below:
Market value of investments + Receivables + Accrued Income + Other Assets – Accrued Expenses –
Payables – Other Liabilities
Page 27 of 32
The asset values as obtained above are to be adjusted as follows:
Additions Deductions
Dividends and Interest accrued Expenses accrued
Other receivables considered good Liabilities towards unpaid assets
Other assets (owned assets) Other short term or long term liabilities
8. Money Markets
Effective Yield (EY) is Calculated by the formula,
𝐅𝐕 − 𝐒𝐕 ∗ 𝟑𝟔𝟓 𝐨𝐫 𝟏𝟐 ∗ 𝟏𝟎𝟎
𝐄𝐃=
𝐒𝐕 ∗ 𝐃𝐚𝐲𝐬 𝐨𝐫 𝐌𝐨𝐧𝐭𝐡𝐬
9. Forex
Direct quote is the one where the home currency is quoted per unit of
foreign currency (eg. USD 1 = INR 60) and vice versa is the indirect quote
i.e where the foreign currency is quoted per unit of home currency (eg. INR
1 = USD 0.01667).
𝟏
𝐃𝐢𝐫𝐞𝐜𝐭 𝐐𝐮𝐨𝐭𝐞 =
𝐈𝐧𝐝𝐢𝐫𝐞𝐜𝐭 𝐐𝐮𝐨𝐭𝐞
PIP is the smallest movement a price can make.
Page 28 of 32
Bid rate is Buy rate and Ask rate is Sell rate.
American Terms are the rates quoted in USD per unit of foreign
currency.
European Terms are the rates quoted in foreign currency per unit of USD.
Premium / Discount = [Forward (F) – Spot (S)] / Spot (S) X (12 / n) X 100
Premium / Discount = [Spot (S) – Forward (F)] / Forward (F) X (12 / n) X 100
𝐅𝐂𝐅
𝐓𝐕= Where,
𝐤
Page 29 of 32
Depending on the availability of information, Terminal Value can also be
calculated by the formulae:
11.Miscellaneous
In case of rights issue, there will not be any change in the pre issue and post
issue wealth of Shareholders provided, they subscribe to the shares, or sell
their rights. If they neither subscribe nor sell their rights , then they lose
value.
Value of right / share = Market Price before Rights issue – Market Price after Rights issue
𝐄𝐁𝐈𝐓
𝐈𝐧𝐭𝐞𝐫𝐞𝐬𝐭 𝐂𝐨𝐯𝐞𝐫𝐚𝐠𝐞 𝐑𝐚𝐭𝐢𝐨 =
𝐈𝐧𝐭𝐞𝐫𝐞𝐬𝐭 𝐂𝐡𝐚𝐫𝐠𝐞𝐬
Page 30 of 32
𝐅𝐢𝐱𝐞𝐝 𝐈𝐧𝐭. 𝐛𝐞𝐚𝐫𝐢𝐧𝐠 𝐅𝐮𝐧𝐝𝐬 𝐏𝐫𝐞𝐟. 𝐂𝐚𝐩. +𝐃𝐞𝐛𝐞𝐧𝐭𝐮𝐫𝐞𝐬
𝐂𝐚𝐩𝐢𝐭𝐚𝐥 𝐆𝐞𝐚𝐫𝐢𝐧𝐠 𝐑𝐚𝐭𝐢𝐨 = =
𝐄𝐪. 𝐒𝐡𝐚𝐫𝐞𝐡𝐨𝐥𝐝𝐞𝐫 𝐅𝐮𝐧𝐝𝐬 𝐄𝐪. 𝐂𝐚𝐩𝐢𝐭𝐚𝐥 + 𝐑𝐞𝐬𝐞𝐫𝐯𝐞𝐬
(x1, y1) and (x2, y2) are any 2 points on the line.
Page 31 of 32