Column Footing Wall Footing Slab Column Beams Tie Beams: RIB Type Roofing (1.05mx3m)
Column Footing Wall Footing Slab Column Beams Tie Beams: RIB Type Roofing (1.05mx3m)
Materials
100mm thk. CHB 35,938 pcs. 12.00 431,250.00
Portland Cement 1150 bags 260.00 299,000.00
Washed Sand 30 cu.m. 550.00 16,500.00
10mmØx6m def bars (Grade 40) 312 pcs. 150.00 46,800.00
#16 G.I Tie Wire 18 kg 70.00 1,260.00
Materials
100mm thk. CHB 4,313 pcs. 12.00 51,750.00
Portland Cement 150 bags 260.00 39,000.00
Washed Sand 30 cu.m. 550.00 16,500.00
10mmØx6m def bars (Grade 40) 312 pcs. 150.00 46,800.00
#16 G.I Tie Wire 18 kg 70.00 1,260.00
Materials
100mm thk. CHB 4,313 pcs. 12.00 51,750.00
Portland Cement 150 bags 260.00 39,000.00
Washed Sand 30 cu.m. 550.00 16,500.00
10mmØx6m def bars (Grade 40) 312 pcs. 150.00 46,800.00
#16 G.I Tie Wire 18 kg 70.00 1,260.00