0% found this document useful (0 votes)
48 views1 page

Chester S. Zapanta: Quotation/Contract

The document is a quotation from Chester S. Zapanta Construction for roofing materials and installation for a two-story residence in Cainta Rizal. It includes 99 linear meters of ribtype panels, gutters, flashings, and other accessories made of 0.40mm thick material. It also lists hardware like tekscrews, rivets, sealant, paint, and foam for ₱52,849. Additional costs include ₱8,335 for hardware, ₱4,500 for transport, and ₱18,800 for installation, for a total of ₱84,504.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views1 page

Chester S. Zapanta: Quotation/Contract

The document is a quotation from Chester S. Zapanta Construction for roofing materials and installation for a two-story residence in Cainta Rizal. It includes 99 linear meters of ribtype panels, gutters, flashings, and other accessories made of 0.40mm thick material. It also lists hardware like tekscrews, rivets, sealant, paint, and foam for ₱52,849. Additional costs include ₱8,335 for hardware, ₱4,500 for transport, and ₱18,800 for installation, for a total of ₱84,504.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Chester S.

Zapanta
Construction, Wood works, Glass & Aluminum

QUOTATION/CONTRACT

TO : Mrs. Aime Fonda

PROJECT : De Castro Subd, CAinta Rizal Two-Storey Residence

PROJECT SITE : De Castro Subd, Cainta Rizal

Subject : Roofing Materials & Installation

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Dear Maam:

We would like to offer you our best price quotation for the supply of roofing materials and labor needed for the above
mentioned project/subject. Hereunder are the following materials and spefications:

PANELS & BENDED ACCEESSORIES:

99 lmtrs. Ribtype 0.40mm x 1.06m x L.S. ₱ 306.00 /lmtr. ₱ 35,294.00

6 pcs. Outside Gutter 0.40mm x 0.915m x 2.44m 750.00/pc. 4,500.00

1 ½ pcs. Outside Flashing 0.40mm x 0.915m x 2.44m 750.00/pc. 1,125.00

5 pcs. Wall Flashing 0.40mm x 0.610m x 2.44m 500.00/pc. 2,500.00

2 pcs. Wall Flashing 0.40mm x 0.407m x 2.44m 340.00/pc. 680.00

9 pcs. W.F to Capping 0.40mm x 0.975m x 2.44m 750.00/pc. 8,750.00

Sub-total : ₱ 52,849.00

HARDWARE ACCESSORIES:

550 pcs. Tekscrew 12 x 55 (Steel) ₱ 1.50/pc. ₱ 825.00

600 pcs. Blind Rivet 0.60/pc. 360.00

7 ctges. Silicone Sealant 180.00/ctges. 1,260.00

1 qrt. Acrylic Paint 445.00/qrt. 445.00

130 pcs. Concrete Nail 0.50/pc 65.00

2 rolls P.E Foam 10mm x 1m x 50m with One Side Aluminized 2,700.00/roll 5,400.00

Sub-total : ₱ 8,335.00

Transport Charge : 4,500.00

Installation Cost : 18,800.00

TOTAL : 84,504.00