01. Ram starts working on a job and works on it for 12 days and completes 40% of the work.
To help him complete the work, he employs Ravi and together they work for another 12 days
and the work gets completed. How much more efficient is Ram than Ravi?
#Solution::
40% work= 12 days
=> 100% work = 12*100/40= 30 days
60% work (Ravi+Ram)=12 days
=> 100%= 1200/60= 20
Ravi can do the work in = 1/20-1/30
= 1/60
So, Ravi:Ram= 1/60:1/30
= 1:2[Time]
= 2:1 [Eff.]
More= (2-1)= 1
%= 1*100/1= 100%[ Answer.]
===========================
02.
A and B can do a piece of work in 10 days. B and C in 15 days. C and A in 20 days. ALL of
them work at it for 2 days, then A leaves. After 2 days of this, B also leaves.C will complete
rest of the work in how many days?
#Solution::
LCM of 10,15 &20= 60
A+B= 6
B+C= 4
C+A= 3
2*(A+B+C)= 13
=> A+B+C= 6.5
So,
A= 2.5
B= 3.5
C= 0.5
Atq
2*6.5+4*2+0.5*x= 60
=> 0.5*x= 39
=> x= 78 days [Answer.]
============================
03. 06. A cylindrical overhead tank is filled by two pumps P1 and P2. P1 can fill the tank in 8
hr while P2 can fill the tank in 12 hr. There is a pipe P3 which can empty the tank in 8 hr.
Both the pumps are opened simultaneously. The supervisor of the tank, before going out on a
work, sets a timer to open P3 when the tank is half filled so that the tank is exactly filled up by
the time he is back. Due to technical fault P3 opens when the tank is one-third filled. If the
supervisor comes back as per the plan what percent of the tank is till empty?
#Solution::
Let, total Capacity of tank = 24 L (By LCM)
A= 3L/hr(Fill)
B= 2 L/hr(Fill)
C= 3 L/hr (Empty)
Half tank full means= 24/2= 12 L by (A+B)= 12/(3+2)= 2 hr 48 min
Remain 12 L by (A+B+C)= 12/(3+2-3)= 6 hr
Total time = 8 hr 48 min[ First condition]
But, Unfortunately 3rd pipe open when the tank is 1/3 rd full.
So, 1/3 rd full means= 1/3*24= 8 L
Remain= 16 L
Now, 8 L full in= 8/5 = 1 hr 36 min
Time at hand = [8 hr 48 min- 1 hr 36 min]
= 36/5 hr
Now, [3+2-3]= 2 unit fiil in = 1 hr
So, 36/5 hr can fill= (36/5)*2= 72/5= 14.4 L
Empty = (16 -14.4)= 1.6 L
% Empty= (1.6*100)/16= 10%
04. A and B working together can finish a job in T days. If A works alone and completes the
job, he will take T+5 days. If B works alone and completes the same job, he will take T+45
days. What is T?
#Solution::
A= T+5
B= T+45
ATQ,
1/(T+5)+1/(T+45)= 1/T
=> (T+45+T+5)*T= (T+5)*(T+45)
=> 2T^2-T^2-50T-50T= 225
=> T^2= 225
=> T= 15
Shortcut::
T^2= ab
=>T= ab= (45*5)= 15
Shortcut formula from below::
1/(T+a)+ 1/(T+b)= 1/T
=> (T+b+T+a)*T= (T+a)*(T+b)
=> 2T^2+Ta+Tb= T^2+Ta+Tb+ab
=> T^2= ab
=> T= (ab)
============================
05. Three professors Dr. Gupta, Dr. Sharma, Dr. Singh are evaluating answer script of a
subject. Dr. Gupta is 40 more efficient than Dr. Sharma, who is 20 more efficient than Dr.
Singh. Dr. Gupta takes 10 days less than Dr. Sharma to complete the evaluation work. Dr.
Gupta starts the evaluation work and works for 10 days and then Dr. Sharma takes over. Dr.
Sharma evaluates for next 15 days and then stops. In how many days, Dr. Singh can complete
the remaining evaluation work?
Solution::
Gupta:Sharma= 140:100= 7:5= 42:30
Sharma:Singha= 120:100= 6:5= 30:25
Gupta:Sharma:Singh= 42:30:25[Eff.]
Gupta:Sharma:Singh= 1/42:1/30:1/25[Time]
= 25:35:42[Time]
Now, ATQ,
10/25+15/35+x/42= 1
=> x/42= 6/35
=> 35x= 42*6
=> x= (42*6)/35= 36/5= 7.2 days [Answer.]
============================
============================
#BCB_MATH_PRACTICE_PROGRAM_DAY_2
============================
01. Water flows into a reservoir which is 200 m long and 150 m wide, through a pipe of cross-
section (0.3m x 0.2m) at 20 kmph. In what time will the water level be 8?
#Solution::
200*150*8= 0.3*0.2*20000*T
=> T= 200 hrs[Answer.]
============================
02. Anil does a work in 90 days, Bittu in 40 days and Chintu in 12 days. They work one after
another for a day each, starting with Anil followed by Bittu and then by Chintu. If the total
wages received are Rs 360 and Anil, Bittu, Chintu share them in the ratio of the work done,
find their respective individual wages.
#Solution:
LCM of 90,40,12= 360
Anil= 4
Bittu = 9
Chintu= 30
They work 1 day each, start with anil.
(4+9+30)*8= 344 unit in = 24 days
So, everyone work 8 days each.
In 25th day Anil work alone= 344+4= 348
In 26 th day= 348+9= 357 unit done.
Remain = 3 unit by chintu
So, Anil:Bittu:Chintu= (9*4):(9*9):(8*30+3)= 36:81:243
Since the wages total = 360
So, Share of Anil:Bittu:Chintu= 36:81:243
[Answer.]
03. There are 12 pipes attached to a tank. Some of them are fill pipes and some are drain
pipes. Each of the fill pipes can fill the tank in 12 hours, while each of the drain pipes will take
24 hours to drain a full tank completely. If all the pipes are kept open when the tank was
empty, it takes 2 hours for the tank to overflow. How many of these pipes are drain pipes?
#Let, inlet pipe= n
Outlet pipe= [12-n]
Atq,
n/12-(12-n)/24= 1/2
=>2* (2n-12+n)= 24
=> 6n= 48
=> n= 8
Drain pipe= [12-8]= 4 pipes[Answer.]
=============================
04. A can build up a structure in 8 days and B can break it is 3 days. A has worked for 4 days
and then B joined to work with A for another 2 days only. In how many days will A alone
build up the remaining part of the structure?
#Solution:
LCM of 8 & 3= 24
A= 3
B= 8
Atq,
3*4+(3-8)*2+x*3= 24
=> 12-10+3x= 24
=> 3x= 22
=> x= 22/3[Answer.]
===========================
05. In Nuts And Bolts factory, one machine produces only nuts at the rate of 100 nuts per
minute and needs to be cleaned for 5 minutes after production of every 1000 nuts.
Another machine produces only bolts at the rate of 75 bolts per minute and needs to cleaned
for10 minutes after production of every 1500 bolts.If both the machines start production at
the same time, what is the minimum duration required for producing 9000 pairs of nuts and
bolts?
#Solution::
Nut machine produce= 100 nuts per min
1000 nut time taken= 1000/100+5= 15 min
8000 nut taken= 15*8= 120 min
And remain 1000 nuts in = 10 min.
Total time taken nut machine= 130 min.
And bolt machine 1500 bolt in = 1500/75+10= 20+10= 30 min
7500 bolt in = 30*5= 150 min
And R= 1500 bolt in 20 min
So, total time taken= (150+20)= 170 min..
So, Minimum time=170 min [Answer.]
=============================
#BCB_MATH_PRACTICE_PROGRAM_TIME_WORK_LOFOYA_DAY_3
============================
01. Two workers A and B manufactured a batch of identical parts. A worked for 2 hours and
B worked for 5 hours and they completed half the job. Then they worked together for another
3 hours and they had to do (1/20)th of the job. How many hours time does B take to complete
the job, if he worked alone?
#Solution::
2A+5B= 1/2_________(1)
3A+3B= 1-(1/20+1/20)= 9/20_________(2)
6A+15B= 3/2
6A+6B= 18/20
________________
9B= 3/2-18/20
=> 9B = (30-18)/20= 12/20
=> B= 12/180= 1/15
So, 1/15========1
=> 1=========15 days [Answer.]
Alternatives:
(4A+10B)= 1_______(1)
And,
3(A+B)= 9/20
=> 60*(A+B)= 9
=> 60*(A+B)/9= 1______[2]
From (1) &(2)
60*(A+B)= 9*(4A+10B)
=> 24A= 30B
=> A:B= 5:4
Atq,
4*5+10*4= 4*D
=> 60= 4*D
=> D= 15 days.
============================
02. A and B borrowed a tractor for 23 days. A ploughed 12 acres per day for a certain number
of days and then Bused it to plough 15 acres per day for the remaining days. If they paid Rs
3,000 and Rs 2,000 respectively, for how many days did A use the tractor?
#Solution:
D*12:(23-D)*15=3:2
=> D*12/(23-D)*15= 3/2
=> 24D= 45*(23-D)
=> 69 D= 45*23
=> D= 15 days[Answer.]
============================
03. A red light flashes 3 times per minute and a green light flashes 5 times in two minutes at
regular intervals. If both lights start flashing at the same time, how many times do they flash
together in each hour?
#Solution:
LCM of 20,24= 120
So 120========1
1=========1/120
=> 3600======3600/120= 60
[Answer.]
============================
04. Pavan builds an overhead tank in his house, which has three taps attached to it. While the
first tap can fill the tank in 12 hours, the second one takes one and a half times than the first
one to fill it completely. A third tap is attached to the tank which empties it in 36 hours.Now
one day, in order to fill the tank, Pavan opens the first tap and after two hours opens the
second tap as well. However, at the end of the sixth hour, he realizes that the third tap has
been kept open right from the beginning and promptly closes it. What will be the total time
required to fill the tank?
#Solution:
LCM of 12,18,36= 36
A= 3
B= 2
C= 1
(3*2)+(3+2)*4-1*6= 20unit in 6 hrs
Remain = 16/(3+2)= 3(1/5)
Total time= 6 hr+ 3 hr 12 min
= 9 hr 12 min
============================
05. Pankaj can produce one unit in 15 days, while Bharti can do the same in 12 days. After
producing one unit, working together, they received Rs. 90, which they distributed amongst
themselves in proportional to their efficiency. If they work for 20 days, and sell the produce,
then Bharti should receive?
#Solution::
Pankaj can do 1 unit in= 15days
So, 15 days = 1 unit
20 days= 20/15= 4/3 unit
Bharti, 20 days = 20/12= 5/3 unit
Total unit = [4/3+5/3]
= 3 units
1 unit cost = 90
3 unit cost= 270 TK
Bharti:Pankaj= 5/3:4/3= 5:4
Bharti receive = 270*5/9= 150 RS.[Answr.]
=============================