Managing Projects With Project Server 2013 - Presentation
Managing Projects With Project Server 2013 - Presentation
Muhammad Arief
[email protected]
What is Project?
◦ Planned set of interrelated tasks to be executed
over a fixed period and within certain cost and
other limitations.
2
3
4
5
6
7
8
9
10
11
12
Lab: Get started with a project site
13
Lab: Using Ms Project
Show Video WBS (Work Breakdown Structure)
Show Video How to Create WBS
Show Video Dependencies Task
14
The Deadline field shows the date you enter
as a deadline for the task. A deadline is a
target date indicating when you want a task
to be completed. If the deadline date passes
and the task is not completed, Project
displays an indicator. A deadline is also
shown as an arrow in the Gantt Chart view.
Data Type: Date
15
Apply a deadline to a task when you want to
track a deadline for a specific task but don't want
to lock your schedule by setting an inflexible
constraint such as Must Finish On or Finish No
Later Than. Such constraints affect scheduling
while the Deadline field simply causes an
indicator to show if a task has not been
completed by its deadline. Add the Deadline field
to a task sheet when you want to enter, view, or
change the deadlines of tasks in your project.
You can also use the Deadline field for sorting,
filtering, and grouping by deadline date.
16
Certain tasks in your project should finish by
specific target dates. However, you don't want
these dates to actually affect how Project
schedules the tasks; you just want to be
alerted if the tasks are not completed by
these dates. Add the Deadline field to the
Entry table of the Gantt Chart view, and set
the deadline dates for these tasks.
17
Fix a task start or end date in MS Project
There are two main ways that you can create
a constraint.
Lab: Deadline & Constraint
18
Use for work on a lot of different tasks at the
same time
Use for make sure the right things get done
on time and within budget
Use for get a result in better planning and
efficiency going forward
Use to prevent a lot of overtime to get the
work done on time
19
Administrators sets up the timesheet periods
20
Project Manager assigns members tasks
Each member fill out the actual hours on each
task and submit it
21
If a member timesheet is approved, the time
that submitted counts toward the total
amount of work done on the task, and the
amount of work remaining on the task is
reduced. This is recorded in the overall
project plan, so that the project manager can
accurately account for whether the project is
progressing as planned.
22
Lab. Using timesheet
23
Use to compare project progress with the
original plan.
Set baseline from your original schedule
before your project gets rolling.
24
Lab. Using baseline
25
Use Baseline
Track Plan by Specific Date
Track Plan by Actual Values
◦ Duration
◦ Start and Finish Date
26
Resource Types
◦ Work
◦ Material
◦ Cost
27
Creating work resources quickly in the Gantt Chart view
Creating resources using the Resource Sheet
Modifying resources
Entering resource holidays
Assigning a single work resource to a task
Adjusting the work, duration, and assignment units for a
task
Assigning material resources to a task
Assigning cost resources to a task
Resolving overallocated resources using the Task
Inspector
Deleting resources
28
When you assign or remove people from a
task, Project lengthens or shortens the
duration of the task based on the number of
resources that are assigned to it, but Project
does not change the total work for the task.
This is called effort-driven scheduling and is
the setting Project typically uses when you
assign resources to tasks.
29
WORK = Durations * Units
Suppose that you have an effort driven Task
with Fixed Duration! It means that no matter
how many Resources will work on the Task, it
should have fixed, and unchanged duration.
On the other hand, effort driven means that if
you add another resource to the Task, all
Resources should work less hours.
Lab. Effort Driven
30
Issues
◦ A point or matter in question or in dispute, or a
point or matter that is not settled and is under
discussion or over which there are opposing views
or disagreements
Risks
◦ An uncertain event or condition that, if it occurs,
has a positive or negative effect on one or more
project objectives
31
Risks might occur and we need to manage
this eventuality, where issues are events that
are already happening and we need to
manage consequences
32
Lab. Managing Issues & Risks
33
Lab. Create a Project Report
Show Video Ms Project Dashboard & Reports
Show Video Ms Project Custom Report and
Export to Excel or PDF
34
Projects inserted into a master project are
called subprojects.
35
Project is very large and detailed
Organization is not centralized
Increase the Effectiveness
Multiple Projects
Some projects are subordinate to others
Several People can modify the project
The Project has multiple stakeholders
Subprojects to be read only
To analyze the critical path for each phase
36
Lab: Master project & subprojects
37
Useful for knowing who’s available to work on
project in multiple projects
Useful for identifying assignment conflict
38
Lab: Resource Pool
39