Proyek Goldvitel Hotel Surabaya Pekerjaan: STRUKTUR

The document is a schedule for the structural works of the Goldvitel Hotel project in Surabaya from April 2016 to May 2017. It details 12 preparatory works like project management and site coordination that will take place throughout the duration. It also outlines 7 foundation and piling works like installing sheet piles, excavating and compacting soil, and installing driven piles that will primarily take place between April 2016 to September 2016. The schedule aims to complete all structural works for the project within the given timeframe.

Uploaded by

Dimaz Mahaes
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views3 pages

Proyek Goldvitel Hotel Surabaya Pekerjaan: STRUKTUR

The document is a schedule for the structural works of the Goldvitel Hotel project in Surabaya from April 2016 to May 2017. It details 12 preparatory works like project management and site coordination that will take place throughout the duration. It also outlines 7 foundation and piling works like installing sheet piles, excavating and compacting soil, and installing driven piles that will primarily take place between April 2016 to September 2016. The schedule aims to complete all structural works for the project within the given timeframe.

Uploaded by

Dimaz Mahaes
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

TIME SCHEDULE GOLDVITEL

Proyek Goldvitel Hotel Surabaya


Pekerjaan : STRUKTUR
100.01

No. Uraian Pekerjaan APRIL 2016 MEI 2016 JUNI 2016 JULI 2016 AGUSTUS 2016 SEPTEMBER 2016 OKTOBER 2016 NOPEMBER 2016 DESEMBER 2016 JANUARI 2017 FEBRUARI 2017 MARET 2017 APRIL 2017 MEI 2017
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

I PEKERJAAN PERSIAPAN
1 Biaya Manajemen dan Koordinasi Lapangan 2.17 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
2 Kantor Pemborong 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Gudang Bahan dan Los Kerja 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 Apar, P3K, dan Peralatan Kerja 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 Mobilisasi dan Demobilisasi 0.36 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
6 Penjagaan royek 0.62 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
7 Pengadaan Sumber Air 0.36 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
8 Pengadaan Listrik 2.17 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
0
.
0
9 Perbaikan Trotoar 0.11 4 0.04 0.04
1
0 Kebersihan dan Kerapihan 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1
1 Peralatan dan Kelengkapan Kerja 2.54 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
1
2 Asuransi 0.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

II Pekerjaan Tanah & Pondasi


1 Pekerjaan Dinding Penahan Tanah
- Bor Pile + Bentonite 5.23 1.74 1.74 1.74
- Pekerjaan Sheet Pile 4.90 3.812 1
2 Pekerjaan galian, urugan kembali dan pemadatan tanah 0.60 0.20 0.20 0.20
Mob Demobilisasi Alat Pancang ( injection 320 ton ) 0.30 0.10 0.10 0.10
3 Pekerjaan pondasi pancang ( L=36 meter ) 7.43 1.95 2.74 2.74
5 Pre boring pancang 1.79 0.89 0.89
6 Potong Tiang Pancang 0.22 # #
7 Pekerjaan site pile penahan tanah 4.90 3.119 1.8
8 Pekerjaan galian tanah lantai basement (h=3 mtr) 1.06 0.16 0.224 0.224 0.224 0.224
9 Pekerjaan Urugan pasir bawah pondasi, t = 10 cm 0.04 0 0
1
0 Pekerjaan lantai kerja bawah pondasi, t = 5 cm 0.09 0.07
1
1 Pekerjaan Urugan pasir bawah lantai basement, t = 10 cm 0.07 0.06
1
2 Pekerjaan lantai kerja bawah lantai basement, t = 5 cm 0.16 0.1 0
1
3 Buang Tanah keluar lokasi ex. Galian dan Dewatering 2.42 0 0.546 0.546 0.546 0.546

III PEKERJAAN STRUKTUR

Pekerjaan GWT
Pile Cap PC-A 0.10 0.03 0.03 0.03
Sloof 30/50 0.38 0.1 0.15 0.15
Lantai GWT t= 25 cm 0.46 0.18 0.18 0.1
Tutup GWT t = 15 cm 0.42 0 0.17 0.17
Dinding GWT t = 20 cm 1.66 0 0.58 0.58 0

Pekerjaan STP
Lantai STP t= 30 cm 0.11 0.08 0
Dinding STP t = 20 cm 0.08 0.05 0

a. Lantai Basement
1 Pek. Pile cap 4.48 2.8 2
2 Pek. Slof 0.50 0.31 0
3 Pek. Retaining Wall 1.69 0.84 0.84
4 Pek. Pelat Lantai 2.02 1.01 1.0114
5 Pekerjaan Kolom 0.66 0.33 0.33
6 Pek. Shear Wall 0.41 0.21 0.21
7 Pek. Tangga 0.07 0.05 0
8 Pek. Pelat Lantai RAM 0.39 0.28 0
9 Pek. Balok RAM 0.19 0.14 0

b. Lantai Lower Ground (LG)


1 Pek. Pelat Lantai 0.65 0.29 0.29 0
2 Pek. Balok 0.80 0.35 0.35 0
3 Pek. Kolom 0.42 0 0.21 0.1
4 Pek. Shear Wall 0.42 0 0.21 0.1
5 Pek. Tangga 0.15 0 0.1
6 Pek. Pelat Lantai RAM 0.40 0.2 0
7 Pek. Balok RAM 0.20 0.174

c. Lantai Ground Floor (GF)


1 Pek. Pelat Lantai 0.60 0.2 0.36
2 Pek. Balok 0.72 0.3 0.43
3 Pek. Kolom 0.37 0.26 0
4 Pek. Shear Wall 0.42 0.29 0
5 Pek. Tangga 0.15 0 0.1

d. Lantai Mezzanine
1 Pek. Pelat Lantai 0.50 0 0.32 0
2 Pek. Balok 0.68 0 0.43 0
3 Pek. Kolom 0.37 0.19 0.19
4 Pek. Shear Wall 0.41 0.21 0.21
5 Pek. Tangga 0.15 0 0.1

e. Lantai 2
1 Pek. Pelat Lantai 0.70 0.3 0.3
2 Pek. Balok 0.80 0.4 0.4
3 Pek. Kolom 0.93 0 0.65
4 Pek. Shear Wall 0.50 0 0.35
5 Pek. Tangga 0.16 0 0.11

f. Lantai 3
1 Pek. Pelat Lantai 0.86 0.4 0.4
2 Pek. Balok 0.83 0.4 0.4
3 Pek. Kolom 0.92 0 0.64
4 Pek. Shear Wall 0.50 0 0.35
5 Pek. Tangga 0.16 0 0.11

7 Lantai 4
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.80 0 0.5
Pek. Kolom 0.92 0.80
Pek. Shear Wall 0.50 0.43
Pek. Tangga 0.16 0 0.11

8 Lantai 5
Pek. Pelat Lantai 0.69 0 0.43
Pek. Balok 0.79 0 0.49
Pek. Kolom 0.46 0.40

Pek. Shear Wall 0.50 0.43


Pek. Tangga 0.16 0 0.11

9 Lantai 6
Pek. Pelat Lantai 0.73 0 0.46
Pek. Balok 0.79 0 0.49
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

10 Lantai 7
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.77 0 0.48
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

11 Lantai 8
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.77 0 0.48
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

12 Lantai 9
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.77 0 0.48
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

13 Lantai 10
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.77 0 0.48
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

14 Lantai 11
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.77 0 0.48
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

15 Lantai 12
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.77 0 0.48
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

16 Lantai 13
Pek. Pelat Lantai 0.70 0 0.44
Pek. Balok 0.77 0 0.48
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0 0.1

17 Lantai 14
#
Pek. Pelat Lantai 0.70 # 0.44
#
Pek. Balok 0.77 # 0.479
Pek. Kolom 0.38 0.33
Pek. Shear Wall 0.41 0.36
Pek. Tangga 0.15 0.10

18 Lantai 15
Pek. Pelat Lantai 0.70 # 0.5
Pek. Balok 0.77 # 0.55
Pek. Kolom 0.42 0.42
Pek. Shear Wall 0.41 0.41
Pek. Tangga 0.15 0 0.1

19 Lantai 16
Pek. Pelat Lantai 0.74 # 0.53
Pek. Balok 0.76 # 0.54
Pek. Kolom 0.43 0.4
Pek. Shear Wall 0.45 0.5
Pek. Tangga 0.15 0 0.1

20 Lantai LMR
Pek. Pelat Lantai 0.07 0.0
Pek. Balok 0.35 0.2
Pek. Kolom 0.06 0.06
Pek. Shear Wall
Pek. Tangga

21 Lantai Atap
Pek. Pelat Lantai 0.08 0.08
Pek. Balok 0.07 0.07

22 Atap Baja
0
.
Pek. Atap Kaca 0.38 1 0.15 0.15
0
.
Pek. Atap Baja 1.21 3 0.47 0.47

RENCANA 0.16 0.16 0.16 0.16 2.01 2.01 0.26 0.36 0.36 2.11 6.82 4.88 - - 2.90 0.16 0.16 0.16 0.16 0.16 0.16 0.56 7.29 5.81 3.50 3.18 1.21 1.58 1.95 2.05 2.19 3.32 2.91 3.28 2.92 2.94 3.01 3.33 3.32 3.02 2.75 2.57 2.57 2.34 2.62 2.39 0.67 0.77 0.78 0.82 0.20 0.20 0.16 0.16 0.16 0.16
TOTAL KOMULATIF RENCANA 0.16 0.32 0.49 0.65 2.65 4.66 4.92 5.28 5.64 7.75 14.57 19.45 19.45 19.45 22.35 22.51 22.68 22.84 23.00 23.16 23.32 23.88 31.17 36.98 40.48 43.65 44.87 46.45 48.39 50.44 52.62 55.94 58.86 62.14 65.06 68.00 71.01 74.34 77.65 80.67 83.42 85.99 88.57 90.91 93.53 95.92 96.59 97.36 98.14 98.96 99.16 99.36 99.52 99.68 99.85 100.0

REALISASI

TOTAL KOMULATIF REALISASI

DEVIASI

Libur Hari Raya Idul Fitri Surabaya, Mei 2016


Dibuat Oleh,
PT. MANDIRI DUTA CONTRACTOR

ITOK HENDARYANTO, ST
Site Manager