100% found this document useful (1 vote)
68 views2 pages

Oromia Credit and Saving Share Company Information System Department SDT Individual Weekely Plan

This document contains an individual weekly plan for employees of the Information System Department at Oromia Credit and Saving Share Company. It outlines 6 activities from July 22, 2019 to July 27, 2019 related to writing a project proposal. The activities include identifying the project objectives and scope, defining and characterizing problems, and identifying issues. The plan specifies dates for each activity and includes spaces to report performance and remarks.

Uploaded by

endale
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
68 views2 pages

Oromia Credit and Saving Share Company Information System Department SDT Individual Weekely Plan

This document contains an individual weekly plan for employees of the Information System Department at Oromia Credit and Saving Share Company. It outlines 6 activities from July 22, 2019 to July 27, 2019 related to writing a project proposal. The activities include identifying the project objectives and scope, defining and characterizing problems, and identifying issues. The plan specifies dates for each activity and includes spaces to report performance and remarks.

Uploaded by

endale
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

OROMIA CREDIT AND SAVING SHARE COMPANY

Information System Department


SDT Individual weekely Plan
To: Information System Department
Employees:- Indaalee Dh., Guutamaa K, Asaamminaw B
Signature:_______________
Date:________________ From: 22/07/2019 To: 27/07/2019

SNO Activity List Plan Performance Remark


Writing project proposal From date To date
1 Will tasks identifiying to achieve objectives 7/22/2019 7/22/2019
Will identifying scope and limitation of
2 project 7/22/2019 7/22/2019
3 Problems definition/characterize problems 7/23/2019 7/24/2019
4 identify and characterize issues 7/25/2019 7/26/2019
5 Methodology of project implementation may be next may be next

At end we will discourse about this proposal


6 7/27/2019 7/27/2019
This format is prepared in two copies
While reporting the performance, use complete for activity completed and not yet completed/on process for acti
If activity planned is not accomplished as required, justify the reason for delay under remark
OROMIA CREDIT AND SAVING SHARE COMPANY
Information System Department
SDT Individual weekely Report
To: Information System Department
Employee Name: _________________
Signature:_______________
Date:_______________ From:________________ To:____________
SNO Activity List Plan Performance Remark
From date To date

This format is prepared in two copies


While reporting the performance, use complete for activity completed and not yet completed/on process for activity under proce
If activity planned is not accomplished as required, justify the reason for delay under remark