0% found this document useful (0 votes)
631 views5 pages

Safe Work Procedure for Area Grading

1. The document provides a safe work procedure for area grading work at a 3*8 MW STPP power plant project. 2. It outlines various hazards associated with excavation and backfilling work such as cave-ins, electric shock, snake bites, and falling. 3. The safety precautions include obtaining work permits, barricading work areas, using proper PPE like safety shoes, providing first aid, and coordinating with other agencies. Personnel are to be briefed on safety procedures before each shift.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
631 views5 pages

Safe Work Procedure for Area Grading

1. The document provides a safe work procedure for area grading work at a 3*8 MW STPP power plant project. 2. It outlines various hazards associated with excavation and backfilling work such as cave-ins, electric shock, snake bites, and falling. 3. The safety precautions include obtaining work permits, barricading work areas, using proper PPE like safety shoes, providing first aid, and coordinating with other agencies. Personnel are to be briefed on safety procedures before each shift.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

RVPR CONSTRUCTION PVT LTD

SAFE WORK PROCEDURE


Project Name : 3*8 MW STPP Name of Customer : NTPC /PVUNL

Department : CIVIL Name of Client : BHEL,TBG

Location : PVUNL, PATRATU Name of Working Agency : RVPR

Job Title : AREA GRADING Doc no : RVPR/SWP/00

Job Duration : Work order no :


Condition of Tools Reference to
Activities Person Responsible
SL NO Hazards Safety Precautions and Tackles Document/Criteria&
(Sequence of work) & PH NO
Ok/Not ok Remarks
 Prior to start the work the work SS/ENGG- 25(WORK
permit will be filled up in PERMIT SYSTEM)
triplicate to clarify the type of SS/ENGG-07(PPE’S)
work involved. SS/ENGG-
 Proximity / six directional 13(BARRICADING)
hazards of the area and SS/ENGG-
necessary precautions will be 45(MANAGEMENT OF
carryout. FIRST AID CASES IN
 Area will be barricaded with SHOP FLOOR)
1 General  Statutory warning tapes/safety nets
Prohibitions wherever is required
 Jobs carried out under
supervision
 Approach to DB ,panels,
switches to be kept clear
 First aid box must keep near the
work area.
 Employees will be made
acquainted with the use of

[Type text]
Client Representative safety Representative of client working agency safety Representative of working agency
RVPR CONSTRUCTION PVT LTD
safety appliances
 Job specific safety briefing will
be given before start the each
shift
 Co-ordination will be
maintaining with all other
agencies
 Proper identification mark will
be provided for every winch
unit/Rig unit
 Area should be cleaned before
starting the job and after
completed the job
 Lifting equipments, accessories
will be deployed at site
appropriately .Test certificates
of lifting equipments will be
ready at site& will be produced
on demand.
 Pollution under control
certificates for all vehicles
should be take from authorized
agency
 Unnecessary water
accumulation will be avoided
 Pest control will be deployed for
mosquito
 Contract board with details of
site supervisor& contact
number will be displayed
 Follow the all requirements of
OHSAS,TSL ,safety standards
and all legal appliances law
 Daily safety talk on Risk and
Rescue management at site

[Type text]
Client Representative safety Representative of client working agency safety Representative of working agency
RVPR CONSTRUCTION PVT LTD
Sl. Activities Hazards Control measures/Safety Precautions Responsible Condition References to
no Person & Ph no of Tools & Document/Criteria
Tackles & Remarks

2 Excavation &  Cave - in  Get clearance before starting


Backfilling  Electric the work from client SS/Engg/GEN -01
Shock. representatives / authorized
 Pipeline person of client.
Damage.

 Snake bite.  Anticipating identified bush area


by bamboos, stick or rod.
SS/Engg/GEN -03
 Foot injury.  Provide safety shoe and
gumboot.

 Immediately give the first – aid


treatment.

[Type text]
Client Representative safety Representative of client working agency safety Representative of working agency
RVPR CONSTRUCTION PVT LTD
 Slip,Trip &  Barrication should be provided
Falling. on the Excavated area.
 Provided Hard barrication,if the
Excavated area’s depth is more
than 1.5mtr.
 Provided warning signage &
caution board near Excavation
area.

Excavation &
Backfilling.  Ground water  De-watering continuously if
spillage. water spillage found on
Excavated area.

 Soil collapse.  Applied shoring process and


use safety net if the soil in
collapsible condition.
 Don’t kept the loose soil from
1mtr of the excavation area.

 Overhead  Operator & Signalman should


High voltage be briefed about overhead high
Transmission voltage Transmission line if any
line. at working area.

[Type text]
Client Representative safety Representative of client working agency safety Representative of working agency
RVPR CONSTRUCTION PVT LTD
 Equipment  Do not overload on the vehicle.
Toppling.  Do not allowed the
unauthorized person to
operate the vehicle.
 Checking the condition of Tools
Excavation & & Tackles before starting the
Backfilling work.
 Always provided a well trained
signalman / flagman on the
 Struck by. vehicle.
 Reverse Horn and back
indicator should be in working
condition.
 Do not comes under the
circumstances of Excavator’s
swing area.
 Always maintain a safe distance
of 3-5mtr from Excavator’s
swing area.

 Do not drive above 20km/hr at


site.
 Road
accident.  Followed all Traffic rules during
driving the vehicle.