Times Dim Results Description Unit QTY
B.R.C mesh reinforcement with 150mm
side and end laps (measured net. and no
allowance made for laps)
249.20 No. A7 in ground floor slab m2 249.20
113.323 No. A7 in corridor slab m2 113.323
249.20 No. A8 in ground floor slab m2 249.20
113.323 No. A8 in corridor slab m2 113.323
113.323 No. A9 in corridor slab m2 113.323
249.20 No. A10 in ground floor slab m2 249.20
113.323 No. A10 in corridor slab m2 113.323
249.20 No. A12 in ground floor slab m2 249.20
Times Dim Results Description Unit QTY
Sawn formwork as described to
reinforced concrete work
Formwok
Pile cap (P2)
gth.
2/1.2+0.05 2.50
2/0.6+0.05 1.30
3.80
3/ 3.80 Fwk. to sides of isol. pile cap 7.98
0.70 7.98 [
Pile cap (P3)
2/0.48 + 0.77 + 0.05 2.60
0.60
1.20
4.40
5/ 4.40 Fwk. to sides of isol. pile cap m2 15.40
0.70 15.40 [
Pile cap (P4)
4/1.2 + 0.05 5.00
5.00
3/ 5.00 15.00 Fwk. to sides of isol. pile cap 15.00
[
Pile cap (P6)
2/1.90 + 0.05 3.90
2/1.2 + 0.05 2.50
6.40
1/ 6.40 6.40 Fwk. to sides of isol. pile cap 6.40
[
To sides of column stump
2/0.25 0.50
2/0.60 1.20
1.70
12/ 1.70 Fwk. to sides of isol. pile cap
4.00 81.60 [ m2 81.60