Material and Labor Cost
Material and Labor Cost
9294 16
12 6 5.32656 205.8183 10
16 6 9.46944 365.8992
20 6 14.796 571.7174 24
25 6 23.11875 893.3085 28
28 6 29.00016 1120.566
32 6 37.87776 1463.597 6
59.184 24 227.2666
53.2656 10 53.2656
55 203.445
227.2666
103.572 38 140.562
31.95936
Project : 1 Storey Residential House
Location : San Pedro, Laguna 2 257.00
Subject : Material and Labor Cost
Date :
I. EARTHWORKS/SITEWORKS
1 Site Clearing 1.00 lot - 2,000.00 2,000.00
2 Site lay-out 1.00 lot - 3,000.00 3,000.00
3 Demolition Works / Disposal (Optional) 29.07 sq.m. - 2,500.00 72,675.00
4 Excavation 6.75 cu.m. - 486.73 3,285.43
5 Backfill 4.77 cu.m. - 160.00 762.40
6 Gravel Bedding 4.16 cu.m. 800.00 3,331.20 110.00 458.04
7 Soil Poisoning 40.00 sq.m. 75.00 3,000.00 30.00 1,200.00
8 Compaction 31.50 sq.m. - 70.00 2,205.00
Sub-total of Item I 6,331.20 85,585.87 91,917.07
II. REBARS
Unit Cost of GRADE 40 per kg. 38.64 per kgs.
1 Column & Wall Footing 112.45 kgs. 38.64 4,345.05 9.00 1,012.05
12mm dia. By 6m length 10.00 pcs 206.00 2,060.00
10mm dia. By 6m length 16.00 pcs 145.00 2,320.00
2 Column 330.84 kgs. 38.64 12,783.60 9.00 2,977.55
16mm dia. By 6m length 24.00 pcs 366.00 8,784.00
10mm dia. By 6m length 28.00 pcs 145.00 4,060.00
3 Beam 483.98 kgs. 38.64 18,700.88 9.00 4,355.79
16mm dia. By 6m length 24.00 pcs 145.00 3,480.00
12mm dia. By 6m length 10.00 pcs 206.00 2,060.00
10mm dia. By 6m length 55.00 pcs 145.00 7,975.00
4 Slab on Grade 140.56 kgs. 38.64 5,431.32 9.00 1,265.06
10mm dia. By 6m length 38.00 pcs 145.00 5,510.00
G.I. Tiewires 52.00 kgs. 38.00 1,976.00 -
Sub-total of Item III 41,260.85 9,610.45 50,871.29
IV. FORMWORKS
1 Formworks 43.50 sq.m. 180.00 7,830.00
Form Plywood (Ordinary) 17.00 pcs. 700.00 11,900.00
2 Scaffolding & Staging 1,486.00 Bd.ft 17.50 26,005.00 4.00 5,944.00
2x2x12 Coco Lumber 130.00 pcs. 70.00 9,100.00
2x3x12 Coco Lumber 161.00 pcs. 105.00 16,905.00
C.W. Nails #4 14.00 kg 50.00 700.00
C.W. Nails #2 (1/2) 3.90 kg 50.00 195.00
Finishing Nails #1 1.70 kg 50.00 85.00
Sub-total of Item IV 38,885.00 13,774.00 52,659.00
V. MASONRY WORKS
1 4" CHB 866.00 pcs. 18.00 15,588.00 26.20 22,689.20
Cement 37.00 bags 275.00 10,175.00
Sand 3.10 cu.m. 800.00 2,480.00
Rebar (10mm dia. By 6m length) 45.00 pcs. 145.00 6,525.00
G.I. Tiewires 2.90 kg 38.00 110.20
2 Plastering 125.90 sq.m. - - 180.00 22,662.00
Cement 38.00 bags 275.00 10,450.00
Sand 2.20 cu.m. 1,200.00 2,640.00
Sub-total of Item IV 47,968.20 45,351.20 93,319.40
I. EARTHWORKS/SITEWORKS
1 Site Clearing 1.00 lot - 2,000.00 2,000.00
2 Site lay-out 1.00 lot - 3,000.00 3,000.00
3 Demolition Works / Disposal (Optional) 29.07 sq.m. - 1,000.00 29,070.00
4 Excavation 6.04 cu.m. - 486.73 2,941.43
5 Backfill 5.67 cu.m. - 160.00 906.88
6 Gravel Bedding 5.14 cu.m. 700.00 3,595.55 135.00 693.43
7 Soil Poisoning 41.60 sq.m. 75.00 3,120.00 30.00 1,248.00
8 Compaction 35.80 sq.m. - 80.00 2,864.00
Sub-total of Item I 6,715.55 42,723.74 49,439.29
II. REBARS
1 Column & Wall Footing 91.62 kgs. 48.64 4,456.24 6.00 549.70
2 Column 153.05 kgs. 48.64 7,444.34 6.00 918.30
3 Beam 468.03 kgs. 48.64 22,764.84 6.00 2,808.16
4 Slab on Grade 217.50 kgs. 48.64 10,579.26 6.00 1,305.01
5 G.I. Tiewires 52.00 kgs. 48.64 2,529.28 -
Sub-total of Item III 45,244.68 5,581.17 50,825.85
IV. FORMWORKS
1 Formworks 43.50 sq.m. 150.00 6,525.00
Form Plywood (Ordinary 4'x8'x1/4") 17.00 pcs. 490.00 8,330.00
2 Scaffolding & Staging 897.60 Bd.ft 17.50 15,708.00 4.20 3,769.92
C.W. Nails #4 14.00 kg 50.00 700.00
C.W. Nails #2 (1/2) 3.90 kg 50.00 195.00
Finishing Nails #1 1.70 kg 50.00 85.00
Sub-total of Item IV 25,018.00 10,294.92 35,312.92
V. MASONRY WORKS
1 4" CHB 934.00 pcs. 14.00 13,076.00 18.80 17,559.20
Cement 42.00 bags 260.00 10,920.00
White Sand 3.20 cu.m. 700.00 2,240.00
Rebar (10mm dia. By 6m length) 52.00 pcs. 145.00 7,540.00
G.I. Tiewires 3.50 kg 38.00 133.00
2 Plastering 133.25 sq.m. - - 190.00 25,316.55
Cement 38.00 bags 260.00 9,880.00
Vibro Sand 2.20 cu.m. 800.00 1,760.00
Sub-total of Item V 45,549.00 42,875.75 88,424.75
TOTAL OF W O R KS 522,988.22
CF 6
WF 12
Column 8
14
Beam 24
44
10 6 3.699 179.9194
12 6 5.32656 259.0839 Slab 49
16 6 9.46944 460.5936
20 6 14.796 719.6774
25 6 23.11875 1124.496
28 6 29.00016 1410.568
32 6 37.87776 1842.374
12 6 31.95936
10 6 44.388
91.61683
16 6 75.75552 19 2x2x12 76
10 6 51.786 19 2x2x12 76
153.0498 182.4
16 6 227.2666 41 2x2x12 164
10 6 162.756 23 2x2x12 92 132
468.0271 307.2 112
10 6 217.5012
36 2x3x12 216
32 2x3x12 192 1233.6
24 2x3x12 96
20 2x3x12 120
30 2x2x12 120
Material Cost
Item No. Description
U. Cost
I. EARTHWORKS/SITEWORKS
1 Backfill (Soil per Truck)
2 Gravel - G1
3 Soil Poison
II. REBARS
1 10mm dia. By 6m length
2 12mm dia. By 6m length
3 16mm dia. By 6m length
4 G.I. Tiewires (Alambre)
IV. FORMWORKS
1 Ordinary Plywood ( 4'x8'x1/4")
2 2x2x12 Coco Lumber
3 2x3x12 Coco Lumber
4 C.W. Nails #4
5 C.W. Nails #2 (1/2)
6 Finishing Nails #1
V. MASONRY WORKS
1 4" CHB
2 Cement
3 Vibro Sand per Sack