1 THE SITE
1.1 Site of the Six lane Project Highway shall include the land, buildings, structures and
road works as described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in Annex-
II of this Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works, trees
and any other immovable property on, or attached to, the Site shall be prepared jointly
by the Authority Representative and the Contractor, and such inventory shall
form part of the memorandum referred to in Clause 8.2.1 of this Agreement.
1.4 The proposed alignment plans of the Project Highway are specified in Annex-III
which shall be followed by the Contractor with minimum finished roadway level (FRL)
as indicated in the alignment plan.
1.5 The status of the environmental clearances obtained or awaited is given in Annex
IV.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 1
Annex – I
(Schedule-A)
Site for Six Laning
1. Site
The Site of the Six lane Project Highway comprises the section of National Highway
No 4 commencing
In the State of Maharashtra. The land, carriageway and structures comprising the Site are
described below.
2. Land (ROW)
The Site of the Project Highway comprises the land described below
Design Chainage (Km)
S No LHS (m) RHS (m) Total ROW (m)
From To
1 771.730 772.230 30 30 60
2 772.230 775.200 New alignment
3 775.200 776.160 10 30 40
4 776.160 776.560 Realignment
5 776.560 777.250 10 30 40
4 777.250 778.190 30 30 60
3. Carriageway
The existing carriageway of the project highway is of 6-lane with paved shoulders.
Carriageway details are given below:
NIL
7. Grade Separators
8. Underpasses
Existing Span
S. Lengt Widt
Chainage Side Arrangement Remarks
No h (m) h (m)
(Km) (m)
NIL
9. Minor Bridges
10. Culverts
Details of existing pipe culverts for cross draiange are given below:
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 3
S Existing Span Arrangement Width
No. Chainage (km) (No x Vent) (m)
1 777.815 2 x 1.0 17.00
2 778.110 2 x 1.0 12.00
3 781.433 2 x 0.9 29.35
Existing Span
Width
S.No Chainage Type of Culvert Arrangement
(km) (m)
(No x Vent)
NIL
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 4
S. No. Location(km) Remarks
NIL
-NIL-
A. Major Junctions
B. Minor Junctions
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 5
Annex-II (Schedule-A)
The dates on which the Authority shall provide Right of Way to the Contractor on different
stretches of the Site are stated below:
Note:
(i) The Authority shall provide the Right of Way on no less than 90% (Ninety per cent) of
the total length of Project Highway on Appointed date in compliance to Clause 8.2 of
EPC Contract Agreement.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 6
Annex-III
(Schedule-A)
Alignment Plans
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 7
Annex-IV
(Schedule-A)
Environment Clearances
The project highway is less than 100 km length and does not involve additional
Right of Way or land acquisition more than 60m on existing alignment and 90m
on Bypass/Realignments. Therefore, the Environmental clearance is not
required for the instant project in terms of latest MoEF notification No.
S.O.2559(E) dated 22.08.2013
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 8
SCHEDULE - B
(See Clause 2.1)
The Project Highway shall be designed and constructed in conformity with the
Specifications and Standards specified in Annex-I of Schedule-D.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 9
Annex – I
(Schedule – B)
1.1 The Project Highway shall follow the existing alignment unless otherwise
specified by the Authority and shown in the alignment plans specified in
Annex III of Schedule-A. Geometric deficiencies, if any, in the existing
horizontal and vertical profiles shall be corrected as per the prescribed
standards for plain/rolling terrain to the extent land is available.
1.2 Width of Carriageway
1.2.1 Main carriageway:
Six laning with paved shoulder shall be undertaken. The paved carriageway shall be
25.0 m (2 x 12.5 m) wide including paved shoulders and excluding the median for 6-
lane divided carriageway.
1.2.2 Main Tunnel:
Two tunnels, one for each direction traffic shall be provided. The paved carriageway
in each tunnel shall be 13.10 m wide including paved shoulder and 1.35 m wide
walkway on median side and 1.5 m escape footway on the left side. The vertical
clearance should be minimum 5.5m as shown in TCS – Appendix D-12 of Schedule
D.
1.2.3 Cross Passage:
The paved carriageway shall be 3.5 m wide with 1.0 m edge strip and 1.0 m walkway
on either side and vertical clearance should be 5.5m as shown in TCS – Appendix D-
12 of Schedule D. These should be provided at every 287 m at locations given in
Clause 2.8.1 of Schedule B
1.2.4 Except as otherwise provided in this agreement, but subject to the
provisions of Annex – I of this Schedule – B, the width of the paved carriageway shall
conform to Clause 1.1 above.
2.1 General: Geometric design and general features of the Project Highway shall
be in accordance with Section 2 of the Manual.
2.2 Design Speed: The design speed shall be the minimum design speed of 100
km/h for plain/ rolling terrain.
2.3.1 In the following sections, where improvement of the existing road geometrics
to the prescribed standards is not possible, the existing road geometrics shall
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 10
be improved to the extent possible within the given right of way and proper
road signs and safety measures shall be provided:
2.3.3 Bypasses: The existing road shall be bypassed to the standards as specified in
the manual at the following locations:
Design Chainage
Sl.
(Km) Length (m) Remarks
No.
From To
NIL
2.4 Right of Way: Details of the Right of Way are given in Annex II of Schedule-
A.
(b) In open country, paved shoulders width shall be provided as shown in indicative
TCS given in Clause 2.11, Annex I of Schedule B.
2.6 Underpasses: These shall be provided at the locations given at para-2.9 of this
Annex-I of schedule.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 11
2.7 Lateral and Vertical Clearance at Overpasses
2.7.1 Lateral and Vertical clearances at over passes shall be as per paragraph 2.11 of
the Manual.
2.7.2 Lateral clearance: The width of the opening at the Overpasses shall be as
follows:
Service Roads shall be constructed at the locations and for the lengths
indicated below:
Number
Location
Total and
Sl. of Approach Vertical
Width length of Remarks
No structure gradient Clearance
(m) Spans
(km)
(m)
Not VUP for
2x steeper Connectivity to
1 777.308 1 x 30 5.5 m
14.5 than 1 in existing RHS
40 Carriageway
Note:
i) Any variations in the lengths specified in the above table shall not constitute a
Change of Scope, save and except any variations in the length arising out of a Change
of Scope expressly undertaken in accordance with the provisions of Article 13.
ii) Fig 2.4A, Fig 2.4B, Fig 2.4C, Fig. 2.8A, Fig 2.8B, 2.8C, Fig. 2.8D, Fig 7.2A, Fig
7.8A, 7.8B, 7.8C and 14.2A mentioned in above table are based on standard figures
given in Six lane Manual and same is appended as appendices in Schedule D of this
technical Schedules
All intersections and grade separators shall be as per Section 3 of the Manual.
Existing intersections which are deficient shall be improved to the prescribed
standards.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 13
Properly designed intersections shall be provided at the locations and of the
types and features given in the tables below:
Major Junctions:
Existing Proposed Proposed
Sl. Chainage Chainage Cross Road Type of Imroveme
No. (km) (Km) Details Junction nt
Connectivity to
existing Vehicular
1 772.180 772.180 Y
LHS/RHS Overpass
Carriageway
Existing RHS Vehicular
2 778.400 777.308 Y
Carriageway Underpass
Minor Junctions:
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 14
4.4 Cut Section – Existing ground
The existing ground shall be cut in the following sections:
In above section, rock surface of side slopes of the cut sections shall be treated
with shotcrete, rock bolting preventing of rock falls and weep holes for release
seepage water.
PAVEMENT DESIGN
Pavement design shall be carried out in accordance with Section 5 of the Manual.
Minimum thickness of PQC, DLC and Granular Sub-Base in rigid pavement
shall be 280mm, 150mm and 150mm respectively. Service road shall be
designed for design traffic stipulated in Clause 5.5.5 of Schedule D - Six lane
Manual.
Rigid pavement is proposed for main carriageway for entire project length and
flexible pavement for service/slip roads.
Rigid pavement is proposed for main carriageway for entire project length.
Where, existing flexible pavement overlap with new pavement, it shall be
reconstructed.
ROADSIDE DRAINAGE
Drainage system including surface and subsurface drains for the Project
Highway shall be provided as per Section 6 of the Manual.
Suitable catch water drains shall be provided for safe discharge of rain water
from hill slopes away from the tunnel faces as per Clause 14.5 of Schedule D –
Six lane Manual.
DESIGN OF STRUCTURES
General
7.1.1 All bridges, culverts and structures shall be designed and constructed in
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 15
accordance with Section 7 of Schedule D – Six lane Manual and shall conform
to the cross- sectional features and other details specified therein.
7.1.2 Width of the carriageway of proposed bridges and structures shall be as given in
para 7.3 of this Schedule-B.
7.1.5 The structures shall be designed to carry utility services as per site requirement.
7.1.6 Cross-section of the new culverts and bridges at deck level for the Project
Highway shall conform to the typical cross-sections given in Section 7 of the
Manual.
Culverts
7.2.1 Overall width of all culverts shall be equal to the roadway width of the
approaches.
7.2.2 Reconstruction of existing culverts:
All existing culverts which are not to be reconstructed shall be widened to the
roadway width of the Project Highway as per the typical cross section given in
section 7 of Schedule D- Six lane Manual. Repairs and strengthening of existing
structures where required shall be carried out.
Details of
proposed Total
Existing Design
Sl. Proposed structures width of
Chainage Chainage Provision
No. Type Size of structure
(Km) (Km) No. of
Vent in in (m)
Vents
m
1 777.815 776.719 HPC HPC 2 1.0 52.0
2 778.110 777.019 HPC HPC 2 1.0 52.0
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 16
Details of
proposed Total
Existing Design
Sl. Proposed structures width of
Chainage Chainage Provision
No. Type Size of structure
(Km) (Km) No. of
Vent in in (m)
Vents
m
3 781.433 777.624 HPC HPC 2 0.9 52.0
7.2.4 Additional new culverts shall be constructed as per particulars given in the table
below:
Sl. Design Proposed Details of Proposed Total width of
No Chainage Type Structures structure in (m)
. (km) No. of Size of Vent in m
Vents
1 772.200 Box 1 3mx2m 33m
7.3 Bridges
(i) The existing bridge at the following location shall be re-constructed as new
Structures:
Sl. Existing Design Type of Existing Total Proposed Total Remar
No Chainage Chainage crossing Bridge width of Bridge propo ks
(Km) (Km) (Retained/Re (2-lane/3-lane / sed
pair/ Re- 4-lane) length
construction)
Nil
Note: Width of the structure shall be as per IRC:SP: 87:2013.
(ii) The following existing narrow bridge shall be widened and additional new 3-
lane bridge shall be constructed as under:
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 17
Sl. Existi Design Type of Existing Total Total Remarks
No ng Chainage crossing Bridge Proposed propose
Chain (Km) (Retained/Re width of d
age pair/ Re- new length
(Km) construction) Bridge (2- (m)
lane/3-lane
/ 4-lane)
NIL
7.3.3 The railings of existing bridges shall be replaced by crash barriers at the
following locations:
Nil
Sl. No. Location of Level crossing (km) Number and length of span
(m)
Nil
The grade separated structures shall be provided at the locations and of the
type and length specified in paragraph 2.9 of this Annex-I.
A. Bridges
B. ROB/RUB
7.8 Tunnel
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 19
Twin tube six lane tunnel is proposed at the following location:
S. Chainage (Km)
Length (m)
No. FROM TO
1 772.730 773.878 1148
Cross passages are located at every 285 m. The cross passages are provided at the
following locations:
S.
Chainage (Km) Remarks
No.
1 773.017
Location chainages are along
2 773.304
centerline of Project Highway
3 773.591
7.9 Viaduct
8.1 Traffic control devices and road safety works shall be provided in accordance
with Section 9 of the Manual.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 20
8.2 Specifications of the reflective sheeting shall be in accordance with Section 9 of
the Manual.
8.3 Safety during the construction of the Tunnel shall be taken in accordance with
section 14.12 of the Manual.
8.4 Traffic control devices for the Tunnel location shall be in accordance with
Section 14.10 of the Manual.
9 ROADSIDE FURNITURE
9.1 Roadside furniture shall be provided in accordance with the provisions of the
Section 9 of the Manual.
10 COMPULSORY AFFORESTATION
11 HAZARDOUS LOCATION
12 SPECIAL REQUIREMENT
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 21
13 CHANGE OF SCOPE
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 22
SCHEDULE - C
(See Clause 2.1)
PROJECT FACILITIES
1 Project Facilities
The Contractor shall construct the Project Facilities in accordance with the
provisions of this Agreement. Such Project Facilities shall include:
(b) Road side furniture: The roadside furniture shall be as per Section 9 of
the manual and shall include
Traffic signs for the Tunnel location include Variable Messages signs
inside the tunnel, traffic lights above each lane at entry portal end and
inside.
iii. Pavement Markings: Shall cover road marking for the entire Project
highway. Tunnel carriageway markings shall be provided in
accordance with the section 14.10.2 of the Manual.
viii. Lighting:
Approaches to tunnel: Shall be provided in accordance with
Section 12.3 of the Manual
(f) Bus bays and shelters: Bus bays with Bus Shelter shall be provided at
below mentioned locations.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 24
Sl. Design Side Village Name
No. Chainage (LHS/RHS/Both)
(km)
1 771.800 BOTH Vele
2 775.900 BOTH Begrutwadi
3 777.400 BOTH -
h) Emergency Facilities:
Emergency facilities for the proposed tunnel shall be provided in accordance
with the clause 14.11 of the Manual.
The Contractor is required to design, install, operate and maintain Highway Traffic
Management System (HTMS) / Advanced Traffic Management System (ATMS) as
part of the project facilities. Advanced Traffic Management System shall be provided
as specified the manual.
j) Tunnel control center: The integrated tunnel control system (SCADA - Supervisory
Control and Data Acquisition) shall be provided to monitor all technical systems in
proposed tunnel. There shall be built-up two control centres near both portals of the
tunnel.
The system shall operate and supervise following subsystems of for the proposed
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 25
Tunnel:
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approachesin Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 26
SCHEDULE - D
(See Clause 2.1)
1 Construction
The Contractor shall comply with the Specifications and Standards set forth in
Annex-I of this Schedule-D for construction of the Project Highway.
2 Design Standards
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 27
Annex – I: Specifications and Standards for
(Schedule-D)
All Materials, works and construction operations shall conform to the Manual of
Specifications and Standards for Six -Laning of Highways (IRC:SP:87-2013), referred
to as the Manual, and MORTH Specifications for Road and Bridge Works. Where the
specification for a work is not given, Good Industry Practice shall be adopted to the
satisfaction of the Authority’s Engineer.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 28
S. Manual Clause Provision as per
Item Modified Provision
No. Reference Manual
footpath+0.30m footpath+0.50m
Pedestrian railing) Pedestrian railing)
Clause 5.2.1. of IRC
SP: 87-2013. Where
new carriageway is to
Type of Pavement shall
Pavement type for be provided when the
(v) Flexible/ Rigid be as mentioned in
Main Carriageway Contractor may adopt
section 5 of Schedule B
any type (flexible/rigid)
of pavement structure
for new construction.
Safe stopping sight
Clause 2.9.5 of IRC SP
distance shall be
87-2013. The desirable
Desirable minimum provided for a length of
values of sight distance
(vi) Sight Distance sight distance shall be summit at start of the
shall be adopted
adopted Project Highway (from
throughout unless
design Km 777.763 to
specified in Schedule B
design Km 772.120).
In fig 14.3 of IRC SP 87
Clause 14.2.6 of IRC
– 2013, it was shown as
(vii) Emergency Lay bye SP: 87 2013 – 10m
100m, Same shall be
emergency Lay bye
followed
Tunnel
illumination/lighting
for tunnel
shall be designed and
Clause 14.8 of IRC SP illumination/lighting
(viii) Tunnel Illumination provided as per MORTH
87-2013 refer Section 1500 of
guidelines for
this Manual
Expressway, Chapter
13.5 for tunnel lighting
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 29
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 30
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 31
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 32
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 33
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 34
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 35
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 36
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 37
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 38
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 39
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 40
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 41
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 42
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara Section of NH 4 in the State of Maharashtra under NHDP
Phase -V on EPC mode Page - 43
SCHEDULE - H
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 44
Weightage in
percentage to Percentage
S No. Item Stage for payment
the Contract weightage
Price
A - Widening & Repairs of
Major Bridges
1. Foundation 0.00%
2. Sub-structure 0.00%
3. Super structure (Including
0.00%
crash barrier etc. complete)
4. Approaches (excluding
0.00%
Retaining wall)
5. Retaining wall 0.00%
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 45
Weightage in
percentage to Percentage
S No. Item Stage for payment
the Contract weightage
Price
1. Foundation 8.06%
2. Sub-structure 5.82%
3. Super structure (Including
Structures (Elevated 32.03%
crash barrier etc. complete)
III Sections, Reinforced 29%
4. Approaches (excluding
earth) 24.74%
Reinforced Earth wall)
5. Reinforced Earth Wall 29.35%
Other works
1. Service Roads 4.69%
2. Toll Plaza 0.00%
3. Road side Drains 3.39%
4. Road signs, markings, Km
5.97%
stones, safety devices
5. Project facilities 0.99%
6. Repair to bridges / structures
a) Providing wearing coat 0.00%
b) Replacement of bearings,
0.00%
joints
c) Providing crash barriers 0.00%
d) Other Items 0.00%
7. Road side plantation 0.05%
IV Other Works 52%
8. Repair of protection works 0.00%
9. Safety and Traffic
0.11%
management during construction
10. Tunnel
a) Underground excavation and
installation of initial supporting
system for twin tube tunnels, 52.38%
emergency lay byes, cross
passages and E&M niches
b) Final lining of twin tube
21.79%
tunnels
c) Ventilation, lighting and fire
10.55%
fighting for twin tube tunnels
11.Miscellaneous like
0.07%
C&G,Dismantling etc.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 46
I. Road Works - Table No 1.3.1
Percentage
Stage of Payment Payment Procedure
- Weightage
A - Widening & Strengthening of
existing Road
1. Earthwork up to top of Sub-grade 1.10%
Unit of measurement is linear length.
2. Granular work (Sub-base, base and Payment of each stage shall be made
0.56%
shoulder) on pro rata basis on completion of a
3. Dense Bituminous Macadam 0.08% stage in a length of not less than 10
(ten) percent of the total length. @
4. Bituminous concrete 0.06%
Cost of ten completed culverts shall
be determined pro rata with respect to
5. Widening and Repair of Culverts 0.31% the total number of culverts. Payment
shall be made on the completion of ten
culverts.
Cost of each minor bridge shall be
determined on pro rata basis with
6. Widening and Repair of Minor Bridges 0.00% respect to the total linear length of the
minor bridges. Payment shall be made
on the completion of a minor bridge.
Unit of measurement is linear length.
Payment of each stage shall be made
7. CC Pavement 2.10% on pro rata basis on completion of a
stage in a length of not less than 10
(ten) percent of the total length. @
B - New / Realignment / Bypass
1. Earthwork up to top of the Sub-grade 68.07%
2. Granular work (Sub-base, base and Unit of measurement is linear length.
1.75% Payment of each stage shall be made
shoulder)
on pro rata basis on completion of a
3. Dense Bituminous Macadam 0.00% stage in full length or 5 (five) km
4. Bituminous concrete 0.00% length.
5. CC Pavement 12.28%
C - New Culverts, Minor Bridges,
Underpasses, Overpasses on existing
road, Realignments and Bypasses
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 47
I. Road Works - Table No 1.3.1
Percentage
Stage of Payment Payment Procedure
- Weightage
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 48
II. Major Bridge works and ROB / RUB - Table No 1.3.2
Percentage
Stage of Payment Payment Procedure
Weightage
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 49
II. Major Bridge works and ROB / RUB - Table No 1.3.2
Percentage
Stage of Payment Payment Procedure
Weightage
length (m) of the Major Bridges.
2. Sub-structure: On completion of abutments, Payment shall be made on
0.00%
piers up to abutment to the abutment/pier cap completion of each stage of a
Major Bridge as per the
3. Super structure: On completion of the super weightage given in this table
structure in all respects including hand
0.00%
rails/crash barriers, tests on completion etc.,
complete in all respects
4.Approaches: On completion of approaches
(excluding retatining wall if any),filter media 0.00%
etc. and complete in all respects & fit for use.
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 50
III. Structures (Elevated sections, Reinforced earth) - Table No 1.3.3
Percentage -
Stage of Payment Payment Procedure
Weightage
Structures (Elevated sections, Reinforced
earth)
1. Foundation: On completion of the
foundation work including foundation for 8.06%
wing and return walls
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara
Section of NH 4 in the State of Maharashtra under NHDP Phase -V on EPC mode Page - 51
IV. Other Works - Table No 1.3.4
Percentage
Stage of Payment Payment Procedure
Weightage
Other Works
Unit of measurement is linear length in km.
Cost per km shall be determined on pro rata
basis with respect to the total length of the
1. Service Roads 4.69% service roads. Payment shall be made for
completed service road in a length of not less
than 20 (twenty) percent of the total length of
service roads.
Unit of measurement is each completed toll
plaza. Payment of each toll plaza shall be made
2. Toll Plaza 0.00%
on pro rata basis with respect to the total of all
toll plazas.
Unit of measurement is linear length in km.
3. Road side Drains 3.39%
Payment shall be made on pro rata basis on
4. Road signs, markings, Km stones, completion of a stage in a length of not less than
5.97% 10 % (ten per cent) of the total length.
safety devices….
Payment shall be made on pro rata basis for
5. Project facilities 0.99%
completed facilities
6. Repair of bridges / structures
a) Providing wearing coat 0.00%
b) Replacement of bearings, joints 0.00%
Payment shall be made for completed items.
c) Providing crash barriers 0.00%
d) Other Items 0.00%
Unit of measurement is linear length. Payment
7. Road side plantation 0.05% shall be made on pro rata basis on completion of
a stage in a length of not less than 10% (ten per
8. Protection works 0.00% cent) of the total length.
9. Safety and Traffic management Payment shall be made on pro rata basis every
0.11%
during construction six months.
10.Tunnel 0.00%
a) Underground excavation and
installation of initial supporting Unit of measurement is linear length. Payment
system for twin tube tunnels, 52.38% shall be made on pro rata basis on completion of
emergency lay byes, cross passages a stage in a length of not less than 10% (ten per
and E&M niches cent) of the total length.
b) Final lining of twin tube tunnels 21.79%
c) Ventilation, lighting and fire Payment shall be made on pro rata basis for
10.55%
fighting for twin tube tunnels completed facilities
Payment shall be made on pro rata basis for
11. Miscellaneous 0.07%
completed facilities
Construction of new 6 lane Tunnel in Khambataki Ghat Section including approaches n Pune - Satara