User Manual
User Manual
DOC.MIE62153 REV. 1
DRTS 3 PLUS
INTRODUCTORY GUIDE
Doc. MIE62153 Rev. 1 Page 2/108
SHORT FOREWORD 6
1 INTRODUCTION 7
2 TEST SET EXPLANATION 8
2.1 The front panel and the key components 8
2.1.1 Connection to the mains and status lights 9
2.1.2 Output voltages and currents 9
2.1.3 Trip inputs and auxiliary outputs 10
2.1.4 Optional measurement inputs 10
2.1.5 Interface connections 10
2.2 Hazardous situations 11
2.3 Power-on 14
2.4 Connection to the relay 17
2.4.1 Burden 17
2.4.2 Current outputs 17
2.4.3 Low current ranges: option IN2-CDG 18
2.4.4 Voltage outputs 19
2.4.5 Trip inputs 20
2.4.6 Counting inputs 21
2.4.7 Auxiliary outputs 23
2.4.8 Low level signals 24
2.4.9 Optional measurement inputs 25
2.5 Connection to the PC 25
2.6 Execution of the test and problem solutions 26
2.7 Power-off 27
3 WHAT’S INSIDE? 28
3.1 Physical description and components location 28
3.2 Detailed block schematics 35
3.2.1 PASS, PWA11316 (21) 36
3.2.2 INTE, PWA21310 (23) 37
3.2.3 RELE, PWA11373 (24) 38
3.2.4 CONV.6, PWA11372 (25) 39
3.2.5 AMCO, PWA11414 (26) 40
3.2.6 AMTE, PWA11405 – 125 V, OR WA11426 –
300 V (27) 41
3.2.7 Power supply 43
4 TROUBLESHOOTING 46
Doc. MIE62153 Rev. 1 Page 4/108
4.1 Introduction 46
4.2 First checks 46
4.3 The test set cannot be powered-on 48
4.4 The test set re-sets after power-on or does not
proceed 49
4.5 FAULT RECOVERY PROGRAM 52
4.6. Fault on the current amplifier 53
4.6.1. Overload 53
4.6.2. Current amplifiers power supply error 53
4.6.3. Over temperature 55
4.6.4. Amplifier replacement 55
4.7. Fault on the voltage amplifier power supply 56
4.8. Fault on the voltage amplifier 58
4.9. Fault on the optional DC SUPPLY 60
4.10. Fault on trip inputs 62
4.11. Fault on the microprocessor board 63
4.12. Problems with upgrade or with the diagnostic 64
4.12.1. Upgrade problems 64
4.12.2. Diagnostic problems 66
4.13. Problems with the USB interface 66
4.14 The fault cannot be fixed 66
5 SPECIAL SITUATIONS 70
5.1 Addition of the MISU option 70
5.2 Transformation of a 125 V unit into a 300 V one 73
6 FUNCTIONAL TEST 77
6.1 Introduction 77
6.2 Voltage outputs 78
6.3 Current outputs 78
6.4 Trip inputs and auxiliary outputs 79
7 DRTS 3 PLUS CALIBRATION 82
8 MEASUREMENT OPTION 83
8.1 Introduction 83
8.2 Description of Measurement option 83
9 GPS OPTION 85
9.1 Introduction 85
9.2 Description of GPS option 85
Doc. MIE62153 Rev. 1 Page 5/108
SHORT FOREWORD
I often wondered why the user’s manual is not very much used,
even if it includes valuable information. As me too I am a user of
such manuals, the answer I have given myself is that valuable
information are concealed somewhere in the thick thing, and I do
not have time to waste to find it. So, either the manual is actually
of help, or I ignore it.
Primo Lodi
Q&A Manager
Doc. MIE62153 Rev. 1 Page 7/108
1 INTRODUCTION
The following is the front panel; all components on the front, and
the key ones inside the test set, are listed here below.
Trip inputs are 10 in all, divided in two groups of five inputs each:
the two groups are isolated between them. First group includes
sockets C1 to C4 (14), and socket IMP1 (7); second group
includes sockets C5 to C8 (14), and socket IMP2 (7). IMP1 and
IMP2 can be used both for trip contacts monitoring and for
counting impulses such as those coming from an energy meter.
The round connector (19) hosts the zero power signals, and
signals for the buffers control.
Of these points, the first two are very hazardous, both for the
user and the test set. THESE TYPES OF FAULT ARE NOT
COVERED BY THE WARRANTY.
The second hazard does not apply if the relay to be tested is not
connected to the plant. If, instead, the connection to the relay is
performed by means of a test connector (or directly to terminal
blocks), the operator must be sure to interrupt the connection to
the V.T. secondary and to the ground. This is normally true;
however, we experienced some instance were this was not
performed.
Doc. MIE62153 Rev. 1 Page 14/108
2.3 Power-on
- At the end of this test, all lights are turned on and off.
- Next, the microprocessor tests the speed of the Static RAM, and
decides whether to add one wait cycle. During this test all lights
turn on and off from bottom to top.
- At the end of this test, all lights are turned on and off.
- At the end of this test, all lights are turned on and off.
- Last, the microprocessor tests the FLASH EPROM, with its CRC
code. In case of error, it turns on lights ON; ! and ERR.
- This is the last test of logic circuits ; next steps refer to analog
circuits. The following table summarizes logic errors.
- Next step is the test of DAC’s that generate low power signals to
be fed into current and voltage amplifiers. First test is zero
voltage output; next maximum voltage; next minimum voltage.
During this test outputs are inhibited: no output is generated by
the instrument.
- Other errors cause the ERR light to turn on; they are also
reported to the P.C. with the corresponding error message.
During this last session, the four LED’s blink in pairs. At the end
of diagnostics, the green light OK turns on: this confirms that the
microprocessor operates correctly. If there is a fault sensed on an
amplifier (current, voltage), you have the two lights: OK and !
turned on, plus the buzzer beeping. In this situation, you can
connect your PC and start the test program: it will display you the
code message telling which one is the faulty amplifier. In order to
proceed, please go to the Troubleshooting chapter.
2.4.1 Burden
RANGE (A) 45
N. OF OUTPUTS 3
BURDEN (Ohm) 0.12
POWER (VA) 240
SELECTION THRESHOLD
V V
5 4.5
24 22
48 42
> 100 57
At sockets (7) are available the count inputs IMP1 and IMP2, that
serve to test energy meters. The threshold level of these inputs is
the respectively same of inputs C1-C4 and of inputs C5-C8, but
there is no de-bounce.
Input IMP1 has the same common of C1-C4; input IMP2 has the
same common of C5-C8.
IMPORTANT NOTE
Some energy meters have the following internal connection (3-
pin).
Doc. MIE62153 Rev. 1 Page 23/108
1 2
V
3
These outputs are relay, that can be operated via software; relay
operation can be timed with respect to currents and voltages. The
relay under test is connected to sockets (12), either on Normal
Closed or Normal Open contact.
Optional measurement inputs (17) are four: low and high current;
low and high voltage.
Low current and voltage inputs are used to test transducer
outputs, respectively with current (0-5; 4-20 mA) or voltage (10
V) outputs.
High current and voltage inputs are used to measure currents up
to 20 A, and voltages up to 200 V.
The 20 mA input is protected against over-currents: a temporary
fuse opens the circuit. However, take care not to apply 20 A to
the 20 mA input.
These inputs are used only if the optional MISU board has been
installed. Connect converter inputs to DRTS 3 PLUS current and
voltage outputs, and converter output to the measurement input.
Start the manual or automatic test and verify the error of the
converter.
Before test start the test set checks voltage output sockets. If a
voltage greater than 10 V is detected, the PC gives a
message of counter-feed on voltage outputs: this avoids
connecting test set’s output voltage to a live wire. In this
instance, remove the voltage before proceeding.
SITUATION V1-V2-V3-V4
At power-on Open; protected
Counter-feed alarm At test start, even if V = 0
During tests; STOP not Closed; not protected
pressed
After RESET Open; protected
After STOP Closed; not protected
If the red ! LED turns on (and a buzzer is heard) during the test,
it alerts about the following problems:
. Error on a voltage output, usually an overload.
. Error on a current output, usually an overload (including the
open circuit).
. Over-temperature sensed on a voltage or current amplifier.
The PC gives a message that helps selecting the type of fault.
Usually, it is sufficient to correct the load and start over again.
In case of over-temperature, go to zero with the outputs and
start over again after some minute. Other faults have an
internal origin: try again, and, if it does not disappear, it is
necessary to repair the instrument. Appendix 4 lists error codes,
and the corresponding fault area.
Other logic errors can turn on the ERR LED of the DRTS 3
PLUS. The error message explains which kind of error has been
sensed. If the error is in the connection area, check the
connection cable (see appendix 2).
2.7 Power-off
After all tests have been performed, set all outputs to zero,
remove all relay connections and power-off the test set. Do not
power off with outputs being generated, and with the relay
connected: high voltage spikes could be generated; the test set
could be faulty at next power-on.
Doc. MIE62153 Rev. 1 Page 28/108
3 WHAT’S INSIDE?
Next picture shows the same view from the front, with the
addition of the front frame.
Next picture shows the detail of the nut that locks the four front
panel screws to the front frame.
Last, the two protections are kept in place by two plastic feet,
that are locked by four screws.
MOUNTING
SCREWS
The grid and the air filter is kept in place by six screws, that don’t
need to be removed to dismount the test set.
The following drawing shows the boards location; next are the
pictures of the test set, seen from above and below after
removing the protection covers.
Doc. MIE62153 Rev. 1 Page 33/108
Starting from the left, for each board we give the physical
location of interface connectors and a more detailed description of
the circuits on board.
Doc. MIE62153 Rev. 1 Page 36/108
FUNCTIONS
1) Transit of MICR bus from MICR board to back panel and other
boards.
2) Circuits for external modules (round connector) and for 0-
power outputs:
• Analog switches;
• Op amps;
• RS485 circuits.
3) Circuits for the USB I/F:
• Logic circuits;
• N. 3 opto-isolators;
• N. 2 DC/DC converters 5 V > 3.3 V.
Doc. MIE62153 Rev. 1 Page 37/108
FUNCTIONS
N. 8 circuits (two isolated groups) detect the trip input status and
communicate it to the MCR board.
Doc. MIE62153 Rev. 1 Page 38/108
FUNCTIONS
• N. 4 auxiliary relays.
• N. 10 Comparators + logic for V,I LED’s.
• N.1 GAL generates the general fault alarm.
• No fault if V,I amplifiers are removed (fault on DRTS,
DRTS.3).
• N. 4 op-amps add 2.5 V for the counter-feed analog
signals (going to CONV analog switches and then to MICR
0-5V ADC’s inputs).
• The 40-way connector J805 receives all auxiliary supplies
from ALIAUX > FRONT.6, and distributes it to all other
boards.
• Connectors J801, J802 carry range selection and faults for
V1, V2 and V3, V4 amplifiers respectively.
• J803 has the logic signal bus for current outputs: it
performs range selections and carries back fault signals.
• J861 has the serial signals to the auxiliary DC voltage
module.
Doc. MIE62153 Rev. 1 Page 39/108
FUNCTIONS
FUNCTIONS
The following picture shows the DIP’s and the LED’s locations.
FUNCTIONS
The mains supply plug includes two fuses, rated 16 A; the power-
on switch includes a lamp that turns on as the switch is operated.
The switch is connected to the filter board (36), whose block
schematic is the following.
Inside the board there are two filters, that feed separately two
intelligent bridges that are mounted on FRONT.6.
The important circuit to note is the set of voltage suppressors,
that limit spikes in differential and also in common mode.
FRONT.6 FUNCTIONS
FUNCTIONS
4 TROUBLESHOOTING
4.1 Introduction
Please mention in your e-mail how did the fault occur: this serves
us for our continuous improvement program. In all instances,
after replacement of the faulty board or module, it should
immediately be returned to the agent or to ISA.
Last, our experience is that our test sets withstand very heavy
duty cycles for long wiles, if correctly used; most problems arise
because of the problems that you have found listed in the former
paragraph: please read it!
There are many types of faults: this chapter refers to the most
common ones. The message displayed by the program (unless
when the unit cannot be powered on) tells you the faulty area;
so, paragraphs are divided According to the type of fault.
To open the test set (please refer to the what’s inside chapter):
. Remove screws on the rear;
. Remove the two protection lids, and the grounding wire;
. Remove the four nuts on the corner that keep the front panel;
. Remove the two screws on the front;
. Shifting the front panel you can access the screws that lock the
frame to the side panels: unscrew them;
. Now you can remove the frame. If necessary, remove the
aluminium sheet that keeps boards in place, and un-tighten the
two nuts: you can remove boards, after having removed the
corresponding connectors. The two boards to the left are
mechanically linked, and have to be removed together.
If there is a connector out of its place, fit it into its position and
power-on again.
To restore the test set, set the board, and then repeat the same
steps, tightening the rod so that boards are not free to move.
2. Once you are sure that boards are in place, power-on the test
set, and upgrade the resident program to the latest revision.
To perform this:
- Start TDMS, select INFO and read the firmware revision
number;
- visit out website: www.isatest.com and verify the actual
revision number for your instrument. If it does coincide,
please get in touch with your agent, otherwise follow the
instructions to download it from the website;
- using UPGRADE, update the resident program with the one
you downloaded.
Doc. MIE62153 Rev. 1 Page 48/108
4. Open the test set and clean carefully from dust the fan filters
and all the inside of the test set. In some sites (like mines) the air
is very much polluted of conductive dust: we once occurred a
case of a test set that did not work any more because of this.
After cleaning, it recovered its operation.
Then, check that screws are tight. Last, check the connectors:
they should be firmly fit.
When the unit cannot be powered-on, first of all check the fuse,
that is incorporated in the power supply pug, into the small
drawer. If the fuse is OK, the cause is most likely located in the
front-end board PWA11386, that is the rightmost one looking
from the front.
If the test set does not operate at any power supply, proceed as
follows. On AMCO amplifiers are located two LED’s that turn on
when the amplifier is powered. The first test is to verify if only
one of the modules is failing, or both. Open the unit, power on
and check for these lights.
If I3 is on and the other two are OFF, also the microprocessor
and fans are off (case 1).
Doc. MIE62153 Rev. 1 Page 49/108
If you see the light on the I1 and I2, but not on the I3 amplifier,
the test set starts and communicates the diagnostic error (case
2).
In both instances, there is a risk that the fault has been caused
by a fault on current amplifiers for the first one, or by the current
amplifier or voltage amplifier supply for the other one. For this
reason, proceed as follows:
. Case 1. Remove the green connector from amplifiers I1 and I2.
Power-on, and measure the voltage between pins o1 and 2 of a
current amplifier connector: take care, because they are not
isolated from the mains. The voltage should be 300 V. If so, the
fault is not on the FRONT-END board, but it is on one of the
amplifiers. To find out which one, connect one at a time, until the
fault comes back.
. If the power supply does not come back, it is necessary to
replace the front-end board, and the modules powered by it,
because they also could be damaged.
. If no power is generated, it is better to return the test set to the
agent, because the fault can be very severe.
. Case 2. Remove the green connectors to current amplifier I3 and
from the voltage amplifiers. Power-on: if the test set turns on, the
fault is not on the FRONT-END board, but it is on one of the
amplifiers. To find out which one, connect one at a time, until the
fault comes back.
4.4 The test set re-sets after power-on or does not proceed
If the test set does not proceed, very likely an auxiliary supply is
missing. To verify this, proceed as follows:
. Open the test set, and remove the rear protection.
. To the left, there is the power back panel, with three boards
connected: the front-end, the ALIAUX, and the power supply
module. The following picture shows the board; the table lists all
voltages that should be measured on the pins of the first
connector to the left.
Doc. MIE62153 Rev. 1 Page 50/108
1C 1A 1C 1A 32A 32C
. If this is not enough, extract also the CONV board: also it can be
the cause of the fault.
If the fault persists with all boards removed, then the ALIAUX
power supply module needs to be replaced.
4.6.1. Overload
2. The load is not too much for the test set; please refer to the
relay connection paragraph. The first check is to measure the
voltage drop across the load: if it is more than 6 V, the
intervention is normal. To know the load impedance it is enough
to inject a low current, say 1 A or less if necessary, and measure
the voltage on the output sockets: if the ratio V/I is greater than
the given value, there is an overload and the error raised is
appropriate. Another check is to short-circuit the current output
and retry generating the current: if there is no overload message,
maybe that the load is too high. In this situation, reduce the
current and try again.
A: actual fault.
. Power-on the test set. On AMCO boards are located two red
LED’s in the center of the board. For normal operation they must
be ON: if one or both is OFF, this means that there is a fault
either to the DC to DC converter module, or to the power
MOSFET. In alternative, it can be caused by the missing of the
300 V supply on the green connector, or by the missing of the
ENABLE signal, still on the green connector. You should have 300
V between pins 2 (negative) and 1 of the green connector, and
about 12 V between pins 2 and 3 (ENABLE). If you don't, also
voltage generators should be not operational, and the fault is in
the FRONT-END board: see the procedure in paragraph 3.3.
If you have the supply but LED’s don’t turn on, then the amplifier
is faulty, and should be replaced: remove it.
NOTE: on the board are also located three red LED’s, that signal
the selected output. The inner one corresponds to I1; the second
one to I2; the external one to I3. There must be only one LED
turned on, corresponding to the output at which is connected;
else, the switch setting is wrong.
Besides, there is a sixth LED, on the centre and on the edge,
signaling that the local microprocessor is OK. If it is turned off,
either an auxiliary voltage is missing, what is signaled by the PC,
or the board must be replaced.
To fix the problem you should replace the faulty AMCO board.
Before doing it, please check the amplifier as follows.
You have to know that all AMCO amplifiers are identical; in order
to select the different positions (I1, I2, I3), we use the set of DIP-
switches that you can note on the board.
The selection is performed the following way:
. There are three groups of eight DIP-switches;
. The selection is performed setting ON all switches of one group,
and OFF the other two groups;
. The group marked SW1, located towards the center of the
board, selects I1; SW2 selects I2; SW3 selects I3.
If DIP switches are not correctly set, please correct and proceed.
If you don’t, there will be no output at the selected position, and
two outputs on the position set by switches.
. Withdraw the faulty AMCO and replace it with the new one.
Doc. MIE62153 Rev. 1 Page 56/108
. Replace connections.
. Power-on DRTS 3 PLUS and check that the fault message has
disappeared, and that all outputs are operational.
. Re-assemble the unit; do not forget to tighten the central rod,
as it ensures that cards stay in place during transportation.
. The replaced amplifiers need to be calibrated. To this purpose,
use DRTS 3 PLUS user’s manual, CALIBRATION user’s manual and
CALIBRATION program.
. 125 V error messages: 162 (+95 V); 222 (+125 V); 223 (+ 165
V); 224 (+200 V); 163 (-95 V); 225 (-125 V); 226 (- 165 V); 227
(-200 V)
. 300 V error messages: 164 (+ 115 V); 165 (+ 210 V); 166 (+
345 V); 167 (+ 460 V); 168 (- 115 V); 169 (- 210 V); 170 (- 345
V); 167 (- 460 V).
Doc. MIE62153 Rev. 1 Page 57/108
PIN 1 DC SUPPLY
SCREWS GREEN
CONN.
PIN 6
SOCKET C C1 C2 C3 C4
PIN 14 8 9 10 11
. Last check: via TDMS MANUAL, select inputs with voltage (for
instance 24 V). Generate 24 V on the voltage generator and
connect it to inputs C1 to C4: does the LED turn on? Is test
stopped? If yes, this confirms that fault is on board INTE-H2.
If a group of inputs does not trip with contact free selection, while
it trips with the with voltage selection, the corresponding 30 V
measurement is missing. In this situation, open the test set and
verify first of all on the rear of the unit. Looking from the rear,
there are two back panels: the one to the left receives the
auxiliary supply voltages from the ALIAUX.6 board, PWA11421
(11370): these are marked: 0C1, 0C5, 30C1, 30C5. On these
points should be soldered four wires, that go to the right back
panel, where the INTE.H6 board, PWA21310, is fit.
First of all, verify that wires are soldered. If so, measure the
voltage between 0C1 and 30C1, and also between 0C5 and 30C5:
it should be 30 V DC. Verify also that on INTE there are 30 V
between A30 and C30 (C1-C4), and between A27 and C27 (C5-
C8).
If the voltage is there, there is a fault in the INTE board; if it is
missing, there is a fault in the ALIAUX.6 board.
If after power-on the test set is powered, but control LED’s are
not in the standard configuration (ON turned on; the other ones
off), or if it is impossible to connect the test set to the PC, it is
possible that the fault is located in the microprocessor control
board.
If during the Upgrade the power went off, or if the DDRTS 3 PLUS
firmware was loaded into the DRTS 3 PLUS test set, it is possible
to recover the situation as follows.
. Open the DRTS 3 PLUS.
. Locate the MICR board: it is the second one from the left.
. From below you can gain Access to ten DIP-switches that allow
setting different models. Switch no. 10 is the one closest to the
rear of the unit.
Doc. MIE62153 Rev. 1 Page 65/108
If you move these switches towards the edge of the board you set
them ON; otherwise they are OFF.
SWITCH 1 2 3 4 5 6 7
POSITION OFF OFF OFF X X X OFF
SWITCH 1 2 3 4 5 6 7
*POSITION ON ON ON X X X ON
With the instrument should come the mains supply cable, the
RS232 and the USB interface cables and all cables that serve to
connect modules (boosters). The user’s manual originally
delivered with the test set is not necessary.
Cover the instrument itself with a polyester film, in order to
protect it against dust and foam.
The instrument should be protected by anti-shock foam having a
minimum thickness of 5 cm ON ALL SIDES.
Use a new carton box as a container. On the box apply the UP
and the FRAGILE labels.
In the box the instrument will be placed horizontal or standing;
not upside down.
If the set is heavier than 20 kg it is better to use also a pallet:
this ensures that the box will not be packed upside down.
Last but not least, do not declare an high value for customs: this
expedites clearance of the good and lowers fees.
Doc. MIE62153 Rev. 1 Page 68/108
DATE __________________
AGENT _________________
COUNTRY _______________
TYPE OF INSTRUMENT ____________________
SERIAL NO. _____________________________
COMPANY ____________________________
USER’S REFERENCE ____________________
FAULT DESCRIPTION
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
5 SPECIAL SITUATIONS
If the customer wishes to add the MISU option, he can ask ISA
the upgrade kit, and add it by himself, with the following
instructions.
4) MISU calibration.
P6 P7
Doc. MIE62153 Rev. 1 Page 72/108
. After this, with trimmer P7, gain, make the readings equal to
9.000 V. Now generate again + 9 V and – 9 V and verify that the
gain correction did not alter the offset calibration; else, repeat the
procedure.
The test set must be instructed that the maximum voltage is 300
V rather than 125 V; this is obtained by modifying the switch
setting on MICR board.
For the switches, the ON position is towards the board edge; OFF
is towards inside. The setting you will find is the following.
SWITCH 1 2 3 4 5 6 7 8 9 10
SETTING ON ON ON ON OFF ON ON ON ON ON
Now press switch no. 4 towards the inside of the board, so that it
goes to OFF position. The final setting is the following.
SWITCH 1 2 3 4 5 6 7 8 9 10
SETTING ON ON ON OFF OFF ON ON ON ON ON
NOTE: if you do not feel safe to operate this way, you can
dismount MICR to perform it. In this instance, please consider
that:
. MICR and PASS boards are screwed together: the must be
removed together, this takes a certain amount of force. Same
force is to be used when fitting them back;
Doc. MIE62153 Rev. 1 Page 76/108
6 FUNCTIONAL TEST
6.1 Introduction
1, 12.5, 125 V (or 12.5, 125, 300 V) and 0.15, 1.5, 15 A. The
reason is that the multimeter changes range around 1.1:
measuring at 0.15 A implies a not acceptable measurement error.
2. The timer input can be taken from the auxiliary output A1.
. Connect the C contact of A1 to the C contact of group 1, and the
NO contact of A1 to C1.
. Program the test of voltage free contacts.
. Program the de-bounce equal to zero.
. Connect C and C1 to channel 2 of the oscilloscope (NOTE: with
the contact OPEN the voltage is about – 13 V; with the contact
CLOSED the voltage is zero).
. The time lag between V1 and C1 is the actual time delay, to be
compared with the measurement performed by the test set.
The duration of contact bounces does not influence very much the
measurement, provided that they are about 1 ms. Even if you
program different values for the de-bounce, the timing
measurement does not change.
Doc. MIE62153 Rev. 1 Page 82/108
8 MEASUREMENT OPTION
8.1 Introduction
9 GPS OPTION
9.1 Introduction
The GPS option has the purpose to allow testing the following
relays:
. Distance relays connected with permissive or blocking schemes;
. Line differential.
For the test are requested two test sets in distant sites, and the
possibility to simulate faults at the meantime on both
instruments. In the first instance the timing error can be in the
range of some millisecond; for the second one, the maximum
timing error is 100 us.
(hh; mm; 0”; hh; mm; 30“; hh; mm+1; 0“; hh; mm+1; 30“...).
The operators at both sites should connect first GPS to the mains
by the plug (1): the 1 pps light starts turning on, thus assuring
that GPS is operational.
Connect on the two sites the two DRTS 3 PLUS to the relays to be
tested; in particular, connect relay trip contacts to inputs C1 to
C4 (see figure).
TEST SETUP
the desired tests before starting the first one; then, they should
press test START on PC at approximately the same time. After
this, they should press the GPS START/STOP button (1): its light
turns on, and the PULSE light (3) turns on as the first
synchronization impulse is generated; it will be applied after one
to two selected periods. After this, impulses are generated at the
selected time interval.
When the two DRTS 3 PLUS sense the first pulse they execute the
first test at the meantime, and provide the first test result.
Pressing test START on PC again the second test can be initiated,
and so on until all tests are over. START commands cannot be
contemporary; they should be provided before the next
synchronization impulse.
1 2
GPS SYNCHRONIZER
PULSE
3
20 30
10 40
START/STOP
1 pps 5 60
4
GPS
5 PULSE INTERVAL
(seconds)
LOCKED
Doc. MIE62153 Rev. 1 Page 88/108
GPS ANTENNA
T0,5A 250V
PULSE
100-240V~ 50/60Hz 5W
8
00
10.1 Introduction
The three phase current amplifier and two voltage amplifier AMIV-
66 is an additional device to the DRTS 3 PLUS. This option offers
the following features:
. To multiply by two the three-phase test current by paralleling
outputs (3x30 A, 160 VA each);
. To multiply by two the test currents (from 3x15 A to 6x15 A);
. To generate a single phase output up to 90 A, 480 VA;
. To control six voltages, so that it is possible to have 6 currents
and 6 voltages at the meantime.
10.3.1 Power-on
Doc. MIE62153 Rev. 1 Page 90/108
Before executing the test with AMIV-66 check that the burdens
of the relay under test are compatible with the maximum load.
To this purpose, it is necessary to compare the burden declared
by the manufacturer to the maximum load.
I4
I5
I6
I4
I5
I6
In this instance, the relay under test needs six voltages: four
voltages will be connected to DRTS 3 PLUS; the remaining two to
AMV-66, as follows.
The option is made of a plug that fits into the mains, and that
has two banana sockets for the connection to the test set
counting input. The purpose is to synchronize the outputs of two
test sets to the mains: as the synchronisation is repeated every 2
minutes, the test set stays locked to the mains for the infinity.
Start the program that allows performing the differential test with
mains synchronisation: both test sets will be locked to the mains.
Now it is possible to apply the nominal current to both ends: as if
this is not at the meantime, just ignore the corresponding trip.
This is the pre-fault situation
Doc. MIE62153 Rev. 1 Page 96/108
PIN N° SIGNAL
1 DCD
2 RXD
3 TXD
4 DTR
5 GND
6 DSR
7 RTS
8 CTS
9 --
DRTS 3 PLUS PC
PIN SIGN PIN SIGNAL
1 DCD 1 DCD
2 RXD 3 TXD
3 TXD 2 RXD
4 DTR 6 DSR
5 GND 5 GND
6 DSR 4 DTR
7 RTS 8 CTS
8 CTS 7 RTS
Doc. MIE62153 Rev. 1 Page 98/108
This appendix lists the suggested spare parts. The list is divided
in two: main spare parts and other spares. The separation
follows the level of probability of the intervention.
N. DESCRIPTION CODE
1 FRONT.6 YWA11386
1 AMCO.6 YWA11374
1 AMTE .3 YWA11356
N. DESCRIPTION CODE
Error messages from the PC are listed in the following table. The
table lists also the meaning of the code, and the fault area or
the cause of the fault.
1 - PARITY/FRAMING/OVERRUN CONNECTION
2 - NON-BCD CODE, LONGITUDINAL FIELD CONNECTION
3 - NON-BCD CODE, LRC FIELD CONNECTION
4 - NON-BCD CODE, ID PARAMETER FIELD CONNECTION
5 - INCORRECT LRC CONNECTION
6 - ETX PREMATURE CONNECTION
7 - ETX NOT ARRIVED CONNECTION
8 - NON-BCD CODE IN PARAMETER VALUE FIELD CONNECTION
9 - DROP IN DTR DURING TRANSMISSION CONNECTION
10 - FRAME LENGTH DOES NOT COMPLY CONNECTION
11 - ID PARAMETER CODE INCORRECT CONNECTION
12 - OVERFLOW BUFFER PARAMETERS CONNECTION
13 - UNDERFLOW BUFFER PARAMETERS CONNECTION
14 - START VALUES RECEIVED WHILE RUNNING SOFTWARE
15 - NEW VALUES RECEIVED WHILE RUNNING SOFTWARE
16 - REPEAT RECEIVED WHILE RUNNING SOFTWARE
17 - PARAMETER MEANINGLESS SOFTWARE
18 - PARAMETER VALUE OUT OF RANGE SOFTWARE
19 – NACK RECEIVED INSTEAD OF ACK SOFTWARE
20 - RECEIVED CHARACTERS DIFFERENT FROM ACK,NACK,STX
SOFTWARE
21 – RECEIVE DATA FRAME TIMEOUT CONNECTION
22 – DATA FRAME READ ERROR CONNECTION
67 - IR OVERLOAD LOAD
69 - IS OVERLOAD LOAD
71 - IT OVERLOAD LOAD
75 - VR OVERLOAD LOAD
77 - VS OVERLOAD LOAD
79 - VT OVERLOAD LOAD
128 -
DO_REPEAT BEFORE TEST DEFINITION SOFTWARE
129 -
CYCLE OPERATIVE MODE REDEFINITION SOFTWARE
130 -
VALI FORMAT STRING INVALID SOFTWARE
131 -
IMMEDIATE COMMAND FORMAT ERROR SOFTWARE
132 -
NUCI E CICO DISCORDANCE SOFTWARE
133 -
SAME CICO VALUE RECEIVED MANY TIMES SOFTWARE
134 -
INVALID SELECTION CODE SOFTWARE
135 -
PARAMETER RECEIVED BEFORE NUCI SOFTWARE
136 -
PARAMETER RICEIVED BEFORE CICO SOFTWARE
137 -
VOLTAGE RANGE OR AMPLITUDE ERROR SOFTWARE
138 -
VOLTAGE RANGE OR AMPLITUDE ERROR SOFTWARE
139 -
VOLTAGES ANGLE ERROR SOFTWARE
140 -
CURRENTS ANGLE ERROR SOFTWARE
141 -
ANGLE REFERENCE ERROR SOFTWARE
142 -
ATTEMPT TO RECORD WHILE OPERATING SOFTWARE
143 -
WAVE-FORM LOADING ERROR CONNECTION
144 -
FIRMWARE LOADING ERROR CONNECTION
145 -
ERROR IN FIRMWARE CRC CONNECTION
146 -
TEST CYCLE SEQUENCE ERROR CONNECTION
147 -
INCOMPATIBLE TEST CYCLE TYPE CONNECTION
148 -
INCOMPATIBLE GRADIENT TEST PARAMETERS
SOFTWARE
149 - INCOPATIBLE INPUTS PROGRAMMING CONNECTION
150 - REQUESTED H/W OPTION IS NOT PRESENT
SOFTWARE
151 - RESULTS TOO LONG SOFTWARE
152 - FLASH EPROM BUILDER NOT VALID MICR
153 - FLASH EPROM MEMORY CODE ERROR MICR
154 - PROTECTED SECTOR FOUND IN FLASH EPROM MICR
155 - FLASH EPROM CLEANING ERROR MICR
56 - FLASH EPROM PROGRAMMING ERROR MICR
157 - OUT OF TIME IN PROGRAM UPDATING MICR
158 - UPDATING PROGRAM DATA ERROR MICR
159 – INVALID POINT OF WAVE SOFTWARE
160 – CYCLE WITH ZERO DURATION SOFTWARE
192 –
BOOSTER ERROR LOAD
194 –
ZERO SEQUENCE OVERLOAD LOAD
195 –
V4 OUTPUT OVERLOAD LOAD
196 –
V4 THERMAL OVERLOAD LOAD
197 –
DIAGNOSTIC ERROR ON - 340 V SUPPLY (AMIV.33)
POWER SUPPLY
198 – DIAGNOSTIC ERROR ON - 454 V SUPPLY (AMIV.33)
POWER SUPPLY
199 – ERROR BOOSTER MISMATCH CONNECTION
A
B P
C R N
S Y
D M
T Z X
E L
U W
F V K
G J
H
FRONT VIEW OF EXT. AMP. CONNECTOR
Doc. MIE62153 Rev. 1 Page 108/108
CABLE TO BOOSTER