Check List Start Up and Comissioning of Fire Pumps 2

This document provides a checklist for starting up and commissioning fire pumps. It lists 25 activities to inspect, including checking the pump specifications match approved drawings, rotating the shaft by hand, performing electrical checks of wiring and grounding, and recording test results. A separate section provides a test sheet to record pump performance data during testing, including flow rates, pressures, speeds, voltages, currents, and ensuring automatic changeover functions properly. The checklist and test sheet are used to verify fire pumps are installed correctly and operate as designed before being put into service.

Uploaded by

ismail_khans
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views6 pages

Check List Start Up and Comissioning of Fire Pumps 2

This document provides a checklist for starting up and commissioning fire pumps. It lists 25 activities to inspect, including checking the pump specifications match approved drawings, rotating the shaft by hand, performing electrical checks of wiring and grounding, and recording test results. A separate section provides a test sheet to record pump performance data during testing, including flow rates, pressures, speeds, voltages, currents, and ensuring automatic changeover functions properly. The checklist and test sheet are used to verify fire pumps are installed correctly and operate as designed before being put into service.

Uploaded by

ismail_khans
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

CHECK LIST START UP AND COMISSIONING OF FIRE PUMPS

Pump :
Make :
Configuration :
Driven :
Electrical
Location :
Details :

Sl.
Description Duty + Standby Jockey
No.

Serving to Tower
1 Model
2 Type
3 Flow
4 Head

5 Motor
6 Controller
Doc. No. :
Rev. No. : 0
Date :
Pre commissioning Check list for Fire
Water Pumps MECH Division
Design
Client Project MEP Consultants
Consultant

Location / Area :
S. Verification Sign of
Activities / Items to be Inspected
No. Engineer
Check the make, model and type of the
1. installed pump as per approved drawing
and submittal.
Check the location of pumps as per
2.
approved drawings.
Ensure the method statement and test
3. report formats are approved prior to
testing and commissioning.
Check availability for access to all
4. components for testing and
commissioning.
Check shipping bolts/clamps are removed
5.
prior to start-up.
Ensure alignment is checked and
6. completed as per manufacturer’s
instructions.
Check the provisions for anti vibration as
7.
per approved details and submittals.
Check all piping connections are complete
8. including flexible connections as per
approved details.
Check all nuts, bolts, screws, etc., are
9.
secure and tightened as required.
Rotate the pump shaft manually and
10.
ensure it rotates freely.
Location / Area :
S. Verification Sign of
Activities / Items to be Inspected
No. Engineer
Check the emergency manual
11.
start.
12. Check automatic start and stop.
13. Check auxiliary alarm contacts.
Check identification labels/tags are
14. provided as per approved
submittals/details.
Installation of pump/s certified by
15. manufacturer or their authorized
representative.
On initial start-up check for correct
16.
direction of rotation.
Check for any unusual noise and
17.
vibration on start-up.
Electrical Checks prior to Start-up
Check all cabling and control
18 wiring is completed and tightened
as required.
Check the provision of grounding
19 as per approved drawing and
details.
Check cables have been tested
20 verify test reports prior to start-
up.
Check the isolator is fixed close to
pumps for emergency shutdown
21
and maintenance, as per approved
drawings.
Check the line voltage and phase
22 rotations as per requirement prior
to start-up
Ensure all identification works are
23
complete.
Check the current drawn by pump
24
motor is normal on initial startup.
Record all test results on approved
25
commissioning format.

Comments / Remarks, if any

QA/QC ENGINEER

Signature
Name
Date
PLANT PERFORMANCE TEST SHEET - FIRE PUMP SETS
Client :
Project :
System :
Location :
Drg. Ref.:

P Manufacturer : Type :
U Serial No. : Size :
M
P Model No. : Stages :
M Manufacturer : Type :
O Serial No. : Size :
T
O
R Frame No. : Output (KW) :
S
Manufacturer : O/L Range :
T
A Type : Timer Setting :
R
T
E
R O/L Setting : Fuse Rating :
Design Test

Flow rate
a. Jockey pump
Pressur Psi Psi
e, b. Electric standby pump
Cut Psi Psi
P
`in’ c. Diesel pump
P U Psi Psi
E M
a. Jockey pump
R P
Pressur Psi Psi
F
e, b. Electric duty pump
O
Cut Psi Psi
R
`off’ c. Electric standby pump
M
Psi Psi
A
N
Speed rmp
C
rmp
E
Voltage/phase/frequency
v/p/hz v/p/hz
M
Current (R,Y,B)
O
fls (amps) Running amps
T
Speed
O
rmp rpm
R
Power
kw kw
FUNCTIONAL TEST
Observatio
Sl. No. Description Comments
n
1 Auto changeover
2 Standby pump
Water flow rate from
3
manufacturer’s curve
4 Interface with BMS

INSTRUMENTS USED / COMMENTS: