Guidance Note On Welding
Guidance Note On Welding
SUMMARY
It is recognized that welding and weld quality are critical factors with respect to the structural
performance of a tanker. Ensuring good quality of welding is a means to improve the
reliability of tanker structures with a consequent reduction of costs for both shipyards and
owners. The aim of this paper is to provide a “layman’s” guide to welding for superintendents,
inspectors, staff naval architects, etc. who are not necessarily welding experts.
Disclaimer: The information in this Paper has been developed by the members of the Tanker Structure Cooperative
Forum based on their individual experiences and using the best information currently available. The Paper can be
downloaded, copied or redistributed (with attribution to the TSCF) at the user’s own discretion and risk. The Paper
is not a substitute for proper engineering analysis, or the text of any law, treaty, convention or technical or reference
material referred to in the Paper. No responsibility or liability is accepted by TSCF, its members, or any person, firm,
corporation or organization in any way involved with the furnishing, compilation, translation, publication, or supply
of any information or materials contained in the Paper, or for the accuracy of any information or advice given in the
Paper or any omission from the Paper or for any consequence whatsoever resulting directly or indirectly from
compliance with, or adoption of or reliance on guidance contained in the Paper, even if caused by failure to exercise
reasonable care.
CONTENT
1 Introduction ........................................................................................................................... 5
1.1 Purpose ........................................................................................................................ 5
1.2 Scope ........................................................................................................................... 5
1.3 Safety ........................................................................................................................... 5
2 Welding Basics ....................................................................................................................... 6
2.1 The Welding Process ................................................................................................... 6
2.2 Joint Types ................................................................................................................... 6
2.2.1 Butt Joint .............................................................................................................. 6
2.2.2 T-joint ................................................................................................................... 6
2.2.3 Corner Joint .......................................................................................................... 7
2.2.4 Edge Joint ............................................................................................................. 8
2.2.5 Cruciform Joint .................................................................................................... 8
2.2.6 Lap Joint ............................................................................................................... 9
2.3 Welding Positions ........................................................................................................ 9
2.3.1 Flat ........................................................................................................................ 9
2.3.2 Horizontal ............................................................................................................. 9
2.3.3 Vertical ................................................................................................................. 9
2.3.4 Overhead .............................................................................................................. 9
2.4 Features of a Weld ..................................................................................................... 10
2.4.1 Parent Material ................................................................................................... 10
2.4.2 Filler Metal ......................................................................................................... 10
2.4.3 Weld Metal ......................................................................................................... 10
2.4.4 Heat Affected Zone (HAZ) ................................................................................ 10
2.4.5 Fusion Line ......................................................................................................... 10
2.4.6 Weld Zone .......................................................................................................... 10
2.4.7 Weld Face ........................................................................................................... 10
2.4.8 Root .................................................................................................................... 10
2.4.9 Toe ...................................................................................................................... 11
2.4.10 Wetting ............................................................................................................... 11
2.4.11 Coalescence ........................................................................................................ 11
2.5 Shielding Gases ......................................................................................................... 11
2.5.1 Argon .................................................................................................................. 11
2.5.2 Carbon Dioxide .................................................................................................. 11
2.5.3 Helium ................................................................................................................ 11
2.6 Welding Processes ..................................................................................................... 12
2.6.1 Manual Metal Arc Welding (MMAW) .............................................................. 12
2.6.2 Submerged Arc Welding (SAW) ....................................................................... 12
2.6.3 Metal Inert Gas/Metal Active Gas Welding (MIG/MAG) ................................. 12
2.6.4 Flux Cored Arc Welding (FCAW) ..................................................................... 13
2.6.5 Electroslag Welding ........................................................................................... 13
2.6.6 Tungsten Inert Welding (TIG) ........................................................................... 13
2.6.7 Plasma Arc Welding........................................................................................... 14
2.6.8 Electro Gas Welding .......................................................................................... 14
3 Certification ......................................................................................................................... 15
3.1 Weld Engineer Qualification ..................................................................................... 15
3.2 Welder Qualification ................................................................................................. 15
3.2.1 Welder Certification ........................................................................................... 15
3.3 Weld Procedure Certification .................................................................................... 16
2 / 102
TSCF IP 007/2016 Guidance Note on Welding
3 / 102
TSCF IP 007/2016 Guidance Note on Welding
4 / 102
TSCF IP 007/2016 Guidance Note on Welding
1 Introduction
1.1 Purpose
Welding and weld quality are recognized as being critical for the structural integrity and
reliability of tanker structures. Many of the damages observed on tankers are cracks related to
weld execution. Many of these damages can be traced back to poor weld execution, poor fit-
up or other factors which could have been addressed when the welding was carried out. In
addition it is well known that weld quality can have a dramatic effect on the fatigue life in
service.
By providing practical information with respect to welding it is hoped that the number of
damages, and consequent cost for both yards and owners, can be reduced.
The aim of this guidance note is to provide a practical “layman’s” guide to welding. It is
primarily intended for superintendents, inspectors, naval architects and others working in the
field with responsibility or interest in welding quality. The information presented is applicable
to both new building at the yard as well as in-service repairs.
1.2 Scope
Section 2 of the Note presents a basic introduction to welding, including a description of the
most commonly used welding procedures.
The remaining sections present the information which is typically of interest for personnel on
site, for example welder qualification, fit-up, typical defects, etc.
The guidance note is not intended to be a textbook on welding. If more detailed information is
required then some of the documents referenced here may be of interest.
1.3 Safety
Safety is outside the scope of this note but is an issue which must be addressed anytime
welding is carried out. Welding can be a dangerous activity and proper procedures should
always be adhered to. This includes such factors as gas freeing to avoid explosion danger, safe
access, proper training, etc.
The welding process can be dangerous and damaging to the human body if the correct
precautions are not taken. Since many common welding procedures involve an open electric
arc or flame, the risk of burns and fire is significant. It is known as a ‘hot work’ process. To
prevent injury, welders should wear the correct Personal Protective Equipment (PPE), usually
consisting of but not limited to: heavy gloves, boiler suit, safety glasses and welding helmet
with UV shield. Should the reader intend to undertake welding activities, relevant HSE
material must be used in association with the correct training and risk assessment prior to
commencement of the job. Reference is also made to “The International Safety Guide for Oil
Tankers and Terminals” (ISGOTT).
5 / 102
TSCF IP 007/2016 Guidance Note on Welding
2 Welding Basics
2.1 The Welding Process
Welding is a fabrication process for joining metals. The process takes place at a high enough
temperature to cause the base material (the pieces to be joined) to melt and then fuse. In many
welding processes additional material is added to the joint. The additional material forms a
pool of molten metal which then cools and fuses with the base metal. The resulting joint can
be as strong as or stronger than the base material.
This is in contrast to other processes such as brazing or soldering. In these processes the
temperature is not high enough to melt the base material and no fusion takes place. These are
essentially mechanical joints.
2.2.2 T-joint
A T-joint is where the connection between the ends/edges of the plate makes an angle to one
another of more than 5o up to and including 90o in the region of the joint. T-joints can be done
as fillet, partial or full-penetration welds. Selection of the type of weld will depend on the
geometry and stress level in the joint.
6 / 102
TSCF IP 007/2016 Guidance Note on Welding
7 / 102
TSCF IP 007/2016 Guidance Note on Welding
8 / 102
TSCF IP 007/2016 Guidance Note on Welding
2.3.1 Flat
A welding position where the welding is horizontal with the centerline of the weld vertical.
2.3.2 Horizontal
A welding position where the welding is horizontal with the centerline of the weld horizontal.
2.3.3 Vertical
Vertical up is where the welding is executed vertically upwards. Vertically down is where the
welding is executed vertically downwards.
2.3.4 Overhead
A welding position where the welding is horizontal and overhead, with the centerline of the
weld vertical.
9 / 102
TSCF IP 007/2016 Guidance Note on Welding
2.4.8 Root
The zone on the side of the first run which is furthest from the welder.
10 / 102
TSCF IP 007/2016 Guidance Note on Welding
2.4.9 Toe
The boundary between the weld face and the parent metal. This is an important feature of a
weld given that they are points of high stress concentration and are often initiation points for
cracking. In order to reduce this stress concentration, the toe area must blend smoothly into
the parent material surface.
2.4.10 Wetting
The bonding of a liquid filler metal or flux on a continuous solid base metal.
2.4.11 Coalescence
Where two or more work pieces are bonded together by liquefying the places they are to be
bonded, joining these liquids (coalescing), and allowing the coalesced liquids to solidify. At
the end of the process the two work pieces have become a continuous solid metal that will be
as strong as the original material if the weld has been carried out properly.
2.5.1 Argon
Argon is an inert gas which can be used either on its own or in combination with other gases
to achieve an arc for the welding of ferrous and non-ferrous metals, i.e. aluminum. Almost all
welding processes can use argon or argon mixtures to create efficient weldability. When using
ferrous metals, argon is usually mixed with other gases such as oxygen, helium, hydrogen,
carbon dioxide and nitrogen. With non-ferrous metals such as aluminum, nickel based alloys
etc., argon is used alone. The low ionization of argon creates an excellent current path and
good arc stability. Argon produces a constricted arc column at a high current density which
causes the arc energy to be concentrated in a small area.
2.5.3 Helium
Helium is an inert gas which is used on weld applications requiring higher heat input for
deeper penetration welds and higher travel speeds. However, in the Gas Metal Arc Welding
(GMAW) process, helium produces a less stable arc compared with argon and therefore is
often mixed with argon to take advantage of the good characteristics from each gas. The
argon improves arc stability and cleaning action when welding aluminum and magnesium,
while the helium improves wetting and weld metal coalescence.
11 / 102
TSCF IP 007/2016 Guidance Note on Welding
12 / 102
TSCF IP 007/2016 Guidance Note on Welding
(i) Semi-Automatic Welding: This means that the equipment only controls the electrode wire
feed with the movement of the welding gun being controlled by hand.
(ii) Machine Welding: This operation uses a welding gun that is connected to a manipulator of
some kind and an operator has to constantly set and adjust controls that move the
manipulator.
(iii) Automatic Welding: When the welding equipment doesn’t need constant adjusting of
controls by a welder or operator. On some equipment, automatic sensing devices control
the correct gun alignment in a weld joint.
Today MIG/ MAG processes are two of the most common industrial welding processes due to
its versatility, speed and relative ease for adapting to automation.
13 / 102
TSCF IP 007/2016 Guidance Note on Welding
therefore not consumed during the welding process. A filler metal is usually used, although
some welds, known as autogenous welds, do not require a filler metal. The filler metal is
typically in the form of a solid metal rod, with compatible properties with the base material,
and is manually added to the weld pool. This process produces high quality welds and in
general is spatter free. There is no slag formed as part of the process which makes the TIG
process well suited to welds requiring high degrees of cleanliness. Given the requirement for
the shieling gas, it can be difficult to shield the weld zone properly in windy conditions
therefore it is not often used on exposed work sites.
14 / 102
TSCF IP 007/2016 Guidance Note on Welding
3 Certification
3.1 Weld Engineer Qualification
A welding engineer is responsible for all design aspects related to welding. This includes
specifying what type of welding is to be applied, preparing the welding procedure
specifications, dimensioning the weld, etc. This is specialized work and it is important that the
weld engineer is properly qualified.
A degree in welding engineering from a recognized university would generally qualify the
individual. Other organizations, such as the International Institute of Welding (IIW), The
Welding Institute (TWI) and the American Welding Society (AWS), offer certification
programs for welding engineers.
With an approved Welding Procedure Specification (WPS), welders are required to demonstrate
that they can produce the joints it describes. This testing procedure is called the Welder
Performance Qualification (WPQ). The requirements of the WPQ test (such as position,
mechanical tests, non-destructive examination etc.) depend on the work that the welder is to be
qualified for and the standards to which the welder is being qualified. A WPQ may be certified by
the employer or a third party in accordance with a manufacturer’s standard or standards provided
by organizations such as Classification Societies, AWS, ASME, API, CSA, and ISO. Having a
third party representative certify test results in accordance with recognized standards allows others
outside the welder’s company to have confidence in WPQ results. For ships, the certification is
typically performed by the classification society that classes the vessel(s) for which the work is
being carried out.
When a WPQ is certified, a Welder Qualification Test Record (WQTR) is issued to the welder.
WQTR’s are usually valid for 2 years before the welder must be requalified. A qualified welder is
someone who has passed a WPQ test for a specific WPS and has obtained a WQTR. The
qualification is valid only for that WPS.
15 / 102
TSCF IP 007/2016 Guidance Note on Welding
same requirements and testing as any welder, and must pass a WPQ test and obtain a WQTR.
When referring to welders, sometimes the terms “certified” and “qualified” are used
interchangeably, so it is important to understand and clarify, as necessary, what a person
means when they say a welder is certified or qualified.
The scope of a WPS may be limited to a specific company, site, project, or certifier, and
requalification of a WPS may be required as companies, sites, projects, and certifiers change.
16 / 102
TSCF IP 007/2016 Guidance Note on Welding
typically include bend tests, tensile tests, and toughness tests. Testing may also include
micrographic and non-destructive examination and hardness tests. Passing these tests forms
the basis for issuing an approved WPS.
Figure 3.3-1 and Figure 3.3-2 below show a representative test weld and give an indication of
the types of mechanical tests which may be required and where the test pieces are taken. Note
that the ends of the sample weld are not used for testing since defects are often found at the
start and stop points of the weld.
Figure 3.3-1 - Typical test weld Figure 3.3-2 - Test samples for welding
qualification
Welding consumables and electrodes of all forms must be stored and handled correctly in
order to avoid moisture and surface contaminants from accumulating on them. Otherwise, the
welds produced by the consumables could be more prone to forming defects such as cracks,
pores, and voids. Most consumable manufacturers have guidelines for storing and drying their
electrodes and fluxes. In general, moisture and rusting is avoided by using sealed packaging and
17 / 102
TSCF IP 007/2016 Guidance Note on Welding
heated cabinets. Shielded electrodes used for SMAW are particularly prone to absorbing moisture
and usually must be dried at elevated temperatures before use. An electric oven is often used for
storage of electrodes. Other contaminants such as oil, grease, and paint must be avoided at all
times when handling, storing, and welding with consumables.
An example of this tier system is the CSWIP system (Certification Scheme for Personnel),
developed by The Welding Institute. The Welding Institute is accredited to administer the
examinations required to achieve certification for the various CSWIP levels. These levels are:
18 / 102
TSCF IP 007/2016 Guidance Note on Welding
It is the Yards or shops responsibility to carry this out but it needs to be followed up by Class
and Owner/Purchaser by witnessing tests and spot checks during the fabrication.
Welding machines.
The welding parameters are essential, they should comply with the parameters in the WPS.
Since the machines can suffer from wear and tear over time it is important that they are
controlled regularly and by random spot check. This should be part of the fabricators QA/QC,
Class and Owners/Purchasers scope of work.
The machines should be controlled by measurement by ampere meter and volt meter, to verify
that the correct current and voltage are indicated/shown on the machine. The gas flow should
also be measured. For larger yards this is normally done by a separate service department
integral to the yard. For smaller companies and workshops this is to be done by an authorised
service company.
For automatic welding machines, the actual welding speed should be verified by measurement
and compared to the indicated speed on the machine. This could be done during monitoring of
the fabrication, to ensure that the welding process is in accordance with the WPS.
Dimension control
Special equipment such as lasers, theodolite, etc. used for more advanced dimension control
should have a certificate issued by an accredited company showing that the equipment is
working and properly calibrated, no more than 6 months old.
Tightness control
If pressure testing is applied by compressed air, the manometers are to be calibrated and
certified.
19 / 102
TSCF IP 007/2016 Guidance Note on Welding
The equipment used in the test facilities, for hardness test, impact and tensile strength etc.
should be certified by an independent body, i.e. Class or similar. Certificates are to be
available. Normally such facilities have some certification of the type of tests that they are
entitled to carry out and the equipment used.
It is important that adjustments and calibration of the amplification of the machine for
different tasks, probes or material are verified by control measurement using a calibration
block before use. The calibration block shall have the same acoustic properties as the test
object. The probes shall be calibrated after 4 hours use.
The sensitivity calibration shall be verified as a minimum at the end of each shift and for any
change in operator, ultrasonic instrument, transducer, coaxial cable, battery, or if the
operator has any doubt about the accuracy of the calibration. However, it is good
practice to verify the instrument calibration on a more frequent basis
A machine calibrated for normal steel cannot be used for casting or stainless steel or vice
versa. The details of the calibrations are further described and regulated in Rules and
standards, e.g. EN 1711 or ASME V.
20 / 102
TSCF IP 007/2016 Guidance Note on Welding
However, on site tests or qualifications can be carried out in order to verify that the complete
set-up of film, radiation source and distances is suitable for the material such that it gives a
good quality of the image/optical density. This is checked using an Image Quality Indicator
(IQI) and is described in the standards or Class guidelines, for example DNV CN07, Sec 5.5.1.
Basically a set of thin wires is placed in the exposure area and they shall be clearly visible on
the developed film. The parameters used, i.e. exposure time, distance type of film etc., are to
be noted and be the same as for the actual RT used.
21 / 102
TSCF IP 007/2016 Guidance Note on Welding
4 Welding Execution
4.1 Pre-Weld Preparations
Correct pre-weld preparation, as described in sections 4.1.1 to 4.1.6, is essential to ensure
good quality welding.
At the design stage a Welding Table shall be prepared and typical welding sequences shall be
determined as described below (see Sections 4.1.1 - 4.1.2).
On-site pre-weld preparations include edge preparation by cleaning, beveling and fit-up of
members for welding with respect to alignment and gap (see Sections 4.1.3 - 4.1.6).
Pre-weld preparations shall also include check of base and filler materials against their
respective specifications.
Welding should not be allowed to start before all pre-weld preparations have been completed
satisfactorily.
Another important weld preparation, not mentioned in detail in this Guidance Note, is that for
manual welding there has to be sufficient room for the welder to get in position and perform
the welding at a steady state without obstructions. In general the structural designer has to
consider proper space for welding at the design stage. Improper or inadequate space will lead
to lower quality welding. For spaces not allowing proper access, one sided welding,
alternative welding sequences or temporary access holes can, amongst others, be considered.
An example of a location where one-sided welding is necessary is closure of rudder plating
where access inside the rudder does not allow sufficient room for proper welding. For this
case a permanent backing bar is often used.
22 / 102
TSCF IP 007/2016 Guidance Note on Welding
All yards and repair companies shall present a welding sequence which shall be reviewed by
the client. A welding sequence is a complicated matter which relies very much on experience
and tests. Unless specialized in welding it is hard to evaluate a welding sequence.
Below are a few examples of typical weld sequences for some general weld joints seen in
shipbuilding.
For smaller repair jobs, such as inserting plates, IACS Rec. No. 47 includes several welding
sequences to follow.
23 / 102
TSCF IP 007/2016 Guidance Note on Welding
The heating and cooling cycle may not just distort the members. In severe cases the material
properties of the members can be affected. When a steel material is heated and cooled rapidly
the material can turn brittle.
One of the most renowned examples of brittle cracking of vessels in way of welding are the
Liberty Class auxiliary vessels which were built in the US during the 2nd World War. Many of
these ships were lost due to cracks in the hull girder originating from brittle cracking as
welding at that time was a new assembly procedure and not all factors were accounted for.
A second example which relates to distortion due to a poorly planned welding sequence
resulted in a permanent and visible distortion of the complete hull girder. A poorly planned
block joint erection of a thin-skinned vessel, where excessive welding of the block joints was
performed, forced the entire vessel to be in a permanent hogging condition. The keel area in
24 / 102
TSCF IP 007/2016 Guidance Note on Welding
the midships region on the slipway was lifted more than 100 mm on a vessel with a length of
approximately 150 meters in spite of the weight of the vessel.
A third example of how severe distortion and residual stresses can be relates to the sandwich
deck construction described in Section 4.2.3 and shown in Figure 4.2-6. For this specific case
the sandwich deck (deck doubling plates) extended over more than half the vessel length on a
vessel with the main engines located forward. With this forced deflection at deck level,
combined with very long propeller shafts, the actual deflection of the propeller shafts had to
be considered. A detailed welding sequence was prepared by an accredited institute to
minimize stresses. The calculated stresses were imported to a beam model with the same cross
sectional properties as the vessel, and the actual deflection could be estimated. The deflection
of the propeller shafts was acceptable given that a certain welding sequence was followed.
With respect to cleanliness of edges these shall be visually inspected for foreign matter such
as paint, oil, water, grease, rust or scale. Poor cleaning of edges may lead to poor side wall
fusion of welding filler and porosity of welding due to inclusion of foreign matter in the weld.
With respect to surface roughness and straightness of edges these shall be visually inspected.
Surfaces intended for welding shall in general be planar, free of local discontinuities and with
a surface roughness within acceptable limits. IACS Rec. No. 47 gives guide lines on both
surface roughness and straightness.
Surface roughness and straightness outside specification may lead to poor side wall fusion
with the welding filler material.
25 / 102
TSCF IP 007/2016 Guidance Note on Welding
Figure 4.1-5 and Figure 4.1-6 below show examples of a poor edge preparation where the
member edges for a closed butt weld joint and a single-V butt joint have not been grinded
smooth prior to fit-up.
4.1.4 Beveling
Preparation of members for welding by beveling depends on the joint type, loads to be carried
by the weld, welding position and accessibility, welding location on the vessel and thickness,
type and shape of the members to be joined. As an example of beveling requirement
depending on the location on the vessel, the “IACS Common Structural Rules for Bulk
Carriers and Oil Tankers” requires full penetration welding between the lower end of
vertically corrugated bulkheads and the lower stool top plate.
Re-beveling can be necessary if poor fit-up of plates with misalignment requires cutting of the
plate edges.
IACS Rec. No. 47 has guidance as to what gap size and alignment is adequate for specific
joints. The guidance includes limits and appropriate remedial action if the limits are exceeded.
For repair jobs with companies not used to working with ship structures the IACS Rec. No. 47
is a good starting point and should be included as a reference. Repair companies and
shipyards working with ship structures on a regular basis will have their own procedures for
gap size and alignment which are approved by the Classification Society. Normally shipyards
procedures and standards for this are based on IACS Rec. No. 47.
In general the gap has to be large enough to ensure proper side wall fusion through the entire
member thickness. The gap shall however not be larger than necessary to avoid excess use of
filler material from an economical point of view as well as possible problems with distortion
of members and residual stress in the weld. Figure 4.1-7 shows a fit-up where the gap is too
26 / 102
TSCF IP 007/2016 Guidance Note on Welding
large. The proper way to handle this would be to release enough of the completed weld so that
the elements can be adjusted and the gap reduced, or if this is not possible use an insert piece.
Edges of members are to be parallel and with a specified gap which is important for the later
straightness and overall tolerances of the construction. In general plate edges shall be as
parallel as possible and distance “d2-d1” shown in Figure 4.1-8 shall be as small as possible.
Alignment of members before welding is very important for the quality of the weld and for
the stress concentrations in and around the welding. For distributing the stresses in a structure
the most efficient way, the path of the stress shall be as smooth as possible. Abrupt changes in
sectional properties will lead to stress concentrations and subsequently possible cracks
depending on the actual loading of the joint. In general distance “dt” given on Figure 4.1-9
and Figure 4.1-10 shall be as small as possible and for highly stresses areas “dt” shall be close
to zero.
27 / 102
TSCF IP 007/2016 Guidance Note on Welding
In addition to the gap and linear alignment as described above, angular alignment must be
checked. Angular misalignment is when there is misalignment between two welded pieces
such that their surface planes are not parallel with each other or at the intended angle. It is
often caused by inaccuracies in the assembly procedures or distortion from other welds.
Angular misalignment can also be caused by local deformation of the edge of a plate if it is
not properly supported or has been distorted by heating due to welding.
Gap and alignment of plates shall be secured by fixation of the members to be welded. Use of
tab pieces for this purpose is described later in this section.
Two examples of poor alignment are shown in Figure 4.1-11 and Figure 4.1-12. Figure 4.1-11
shows a misalignment of a butt joint also shown in Figure 4.1-9. The actual misalignment was
measured to 8 mm compared to 3 mm allowed misalignment. Figure 4.1-12 shows
misalignment of a butt joint of the welded flange of a stiffener.
Figure 4.1-11 – Poor Butt Joint Alignment Figure 4.1-12 - Poor Alignment of Stiffener Flange
When proper edge preparation, beveling, gap and alignment is in place, it is essential that the
members up for welding are fixed to secure proper quality and strength of the weld, smooth
transfer of stresses from member to member and straightness and tolerances of the finished
structure.
Fit-up of smaller structures to ensure acceptable gap and alignment can be done by clamps
whereas larger structures are normally fit-up using welded strong backs (see Figure 4.1-13)
and wedges (see Figure 4.1-14) or hydraulic jacks.
28 / 102
TSCF IP 007/2016 Guidance Note on Welding
Fit-up can also be designed to take account the deformations the welding will impose on the
connection of members due to the shrinkage of the filler material when cooling off. Figure
4.1-15 shows an example of such a fit-up. The example of the sandwich deck construction
described further in Section 4.2.3 and shown in Figure 4.1-15 did not allow such an angled fit-
up, which could have reduced residual stresses considerably. For the case only one-sided
welding was possible.
Tab pieces are fitted to ensure a good “end” of the weld. As ends of welds are often prone to
have defects tab pieces at the ends of the weld are introduces to extend the welding. As a rule
of thumb a tab piece should extend as far out from the plate or stiffener as the thickness of the
plate or stiffener. After welding of the member the tab piece is removed and the area properly
cleaned and ground.
In Figure 4.1-16 and Figure 4.1-17 the correct use of tab pieces is shown. The tab pieces have
an adequate length and the shape of the tab piece matches the beveling of the members.
In Figure 4.1-18 and Figure 4.1-19 the incorrect use of tab pieces is shown. In Figure 4.1-18
the tab piece is missing and in Figure 4.1-19 the weld is not extended sufficiently over the tab
piece.
29 / 102
TSCF IP 007/2016 Guidance Note on Welding
4.1.6 Pre-Heating
Pre-heating of members up for welding is mainly done for 3 reasons:
1- Welding is done in an exposed climate where ambient temperature is around 0°C.
2- Members have large thickness
3- Members are high-carbon or alloy steel
For item 2, pre-heating can be necessary to slow down the cooling rate in the weld to avoid
hydrogen cracking. Increased thickness and increased carbon content in members can increase
the risk of hydrogen cracking. IACS Rec. No. 47 again gives good guidance as to the extent
of required pre-heating as a function of member thicknesses and carbon content.
30 / 102
TSCF IP 007/2016 Guidance Note on Welding
For item 3, high-carbon steel or alloy steel welding will contain a high percentage of
martensite which is brittle. Pre- and post-heating will reduce the martensite content in the
welding.
Any requirements to pre-heating will be given in the WPS and should be carefully followed.
In general a good joint design will provide proper access for the welder, adequate root
opening to permit proper side wall fusion of welding filler and at the same time secure the
least possible amount of welding filler.
In Section 2.2 several joint types are described. In the following sections beveling and gap is
described for the most common joint types in ship building, i.e. butt joints, T-joints and
cruciform joints.
In general “Gap” and “Bevel angle” in the following Section shall be described in the
Welding Procedure Specification “WPS” (See Section 3.3.1). Furthermore IACS Rec. No. 47
has guidelines.
In the following section the abbreviations as shown in Figure 4.2-1 will be used.
Where:
“t” is thickness of abutting plate.
“dt1” is defined in the Welding Table and is normally between 0.2 – 0.3 times the thickness of
the abutting member.
“dt2” distance gives type of welding. When distance “dt2” on figure 4.2-1 is 1-2 mm the
welding is classed as “full penetration”. When “dt2” is less than approx. 1/3 of the thickness
of the abutting member the welding is classed “partial penetration”.
31 / 102
TSCF IP 007/2016 Guidance Note on Welding
In order to perform welding with a larger current and reduced welding time, a backing can be
applied for all types of butt joint welding as shown in Figure 4.2-3. The backing reduces the
risk of filler material burning through the intended weld area. When both sides of the member
are accessible after the joint is welded, a temporary ceramic backing - often provided in the
form of self-adhesive tape - is used. When one side is not accessible after welding a
permanent backing is used. The permanent backing shall be of same material as the members
to be joined. Normally the backing is not to be less than 6 mm in thickness and it is welded to
one of the members to be joined. A weld with a permanent backing will have an additional
stress concentration in the root of the weld and they are generally not allowed in areas with
high stresses.
32 / 102
TSCF IP 007/2016 Guidance Note on Welding
The V-shape joint normally has an angle between 40° to 50° depending on the welder’s
qualifications and the yards standard practice for the chosen weld method. The bevel angle
has to be large enough to ensure proper side wall fusion, but as small as possible to avoid
excess use of weld filler and minimise residual stresses. For thicker plates where distortion,
residual stresses and amount of necessary filler material increase excessively, double V-shape
penetrations are preferred. Single-V butt joints are most often used for welding of horizontal
joints and welding this type of joint in an overhead position should be avoided. As described
in the example below, this is for some cases not an option when only one-sided welding is
possible.
Figure 4.2-6 shows an example of welding 30 mm deck plates on top of an existing deck
structure forming a sandwich construction. The sandwich deck construction was introduced as
the as-built working deck of an anchor handling vessel did not have sufficient thickness and
loading capability for an increased deck load requirement. Extensive testing and inspection of
33 / 102
TSCF IP 007/2016 Guidance Note on Welding
weld method and angle of single-V were investigated to minimize residual stresses and the
amount of weld filler and at the same time ensure proper strength of welding as deck plates
are subjected to hull girder bending moment as well as local load from heavy cargo on deck.
Testing and inspection of welds included slicing up sections of the welded sections to visually
ensure proper side wall fusion. The angle of the single V beveling was by this procedure
decreased to 30° and accepted by Class.
Single- and double-U and J butt joints are all shown in Figure 4.2-8 and Figure 4.2-9 below.
U- and J-joints require special machine cutting to prepare edges and are subsequently more
costly than V-preparations. U- and J- joints are used when joining very thick plates as they
provide a stronger weld with less filler material than V.
34 / 102
TSCF IP 007/2016 Guidance Note on Welding
4.2.6 T-Joint
T-Joint welding as shown in Figure 4.2-10 is used to weld to members at an angle generally
larger than 30 degrees. The welding of the joint is based on the expected stress level in
members and position of the joint. Figure 4.2-10 shows a regular fillet weld of a T-joint. In a
fillet weld the welding is defined by the throat thickness “a” (or the leg length “l”, see Section
4.1.1) which is a function of the thickness of abutting plate and the position of the weld on the
vessel. Throat thickness is normally between 0.1 - 0.5 times the thickness of the abutting
member (t) and is specified in the welding table (see Section 4.1.1).
Figure 4.2-11 below shows a typical single bevel of a T-joint for both 90°and 45° angle. When
it is difficult to access the area behind the weld for post treatment of welding by gouging, a
small backing strip can be applied before welding, as seen on the left most figure. Instead of a
backing strip a permanent backing can be applied, by fillet welding, before welding the actual
member, as seen in the center figure. For definitions of full and partial penetration welds see
Section 4.2.
35 / 102
TSCF IP 007/2016 Guidance Note on Welding
36 / 102
TSCF IP 007/2016 Guidance Note on Welding
The advantage of intermittent welding is the minimized use of filler material as well as lower
distortion and residual stresses.
Increased requirements for welding surface profile can in some cases also be used to repair
cracks in an existing weld. If the scantlings and material of a joint are appropriate, it may be
37 / 102
TSCF IP 007/2016 Guidance Note on Welding
sufficient to gouge, re-welded and grind to achieve less surface roughness or a better profile
than the cracked weld.
Before and after grinding, the weld and adjacent member surfaces should be cleaned properly
by burr grinding or similar. To gain any advantage from grinding the weld it is important that
corrosion is avoided, so coating is critical.
38 / 102
TSCF IP 007/2016 Guidance Note on Welding
5 Welding Defects
5.1 Defect Types and Causes
5.1.1 Crack
An imperfection in the weld which is produced by a local rupture in the solid state. Cracking
may happen due to the effects of cooling or stresses acting on the structure. This is one of the
most serious defects as the geometry of a crack in a weld produces a very large stress
concentration at the crack tip, which can cause crack propagation. There are different types of
cracks which can be situated in different areas, including the weld metal, the HAZ and/or the
parent material.
(i) The weld bead does not penetrate the entire thickness of the base plate.
(ii) The two opposing weld beads do not interpenetrate.
(iii) When the weld bead does not penetrate the toe of a fillet joint but only bridges
across it.
39 / 102
TSCF IP 007/2016 Guidance Note on Welding
Welding current has the greatest effect on penetration. Incomplete penetration is usually
caused by use of a low welding current. It can be eliminated by simply increasing the input
amperage. Other causes can be the use of too slow a travel speed and an incorrect torch angle.
Both will allow the molten weld metal to roll in front of the arc, acting as a cushion to prevent
penetration.
5.1.5 Spatter
Spatter is beads of weld metal or filler metal which are expelled during the welding process
and stick to the surface of the parent metal. It can be caused by a high arc current, damp
electrodes or the selection of the wrong shielding gas for a given welding process. It is a
cosmetic defect which doesn’t affect the integrity of the weld profile however it is usually a
sign that one of the input parameters is wrong and hence the welding conditions are not
correct. Anti-spatter compounds can be used on the parent material to avoid the spatter
sticking. This allows the spatter to be simply scrapped off. If not used, spatter usually has to
be ground off.
40 / 102
TSCF IP 007/2016 Guidance Note on Welding
41 / 102
TSCF IP 007/2016 Guidance Note on Welding
5.1.8 Undercut
Undercut is a defect that appears as a groove in the parent metal directly along the edges of
the weld. It is characterised by its depth, length and sharpness. It is most common in lap fillet
welds but can also be found in fillet and butt joints. The undercutting defect is normally
caused by improper welding parameters such as incorrect travel speed or high welding current.
When the current is too high or the travel speed is too slow, the top edge of the parent
material melts at the free edge creating a groove. Undercut can either be a continuous defect
along the edge of the weld or found intermittently.
42 / 102
TSCF IP 007/2016 Guidance Note on Welding
5.1.13 Overlap
Overlap is an imperfection at the toe of a weld which is caused by metal flowing onto the
surface of the parent metal without it fusing onto the metal. It can be caused by poor
electrode manipulation, incorrect welding position and/or high heat input with a low travel
speed causing the metal to flow onto the parent material surface.
43 / 102
TSCF IP 007/2016 Guidance Note on Welding
44 / 102
TSCF IP 007/2016 Guidance Note on Welding
In some cases the thermal strain due to welding is sufficient to cause lamellar tearing.
Lamellar tearing can be prevented by using steel with a low percaentage of impurities,
particularly sulpher. It is also possible to use steel with guaranteed through-thickness
properties, denoted “Z-quality” steel. Ultrasonic testing can be used to identify lamellar
tearing.
45 / 102
TSCF IP 007/2016 Guidance Note on Welding
NDT is divided into various method groups, where each group is based on a particular
principle. Each method group may be further subdivided into various techniques which can
be applied for that testing group. The following sections explore the different NDT groups
that are available.
Advantages:
- This is a quick and simple process.
- Most reliable method of surface inspection on ferritic materials.
- Can be carried out at almost any location, including underwater.
- It is possible to detect (shallow) sub surface defects.
- Relatively low cost method.
Limitations:
- Difficult to use on rough surfaces.
46 / 102
TSCF IP 007/2016 Guidance Note on Welding
Advantages:
- Can be used on most materials for surface breaking defects.
- Equipment is portable and inexpensive.
- For the visible colour contrast, no power supply is required as long as light levels are
adequate for inspection.
Limitations:
- Cannot be used on porous surfaces.
- False indications can occur on rough surfaces where excess dye is difficult to remove.
- It is a less sensitive method than MPI for in-service inspection on ferritic materials.
47 / 102
TSCF IP 007/2016 Guidance Note on Welding
Advantages:
- The location and size of internal defects can be detected.
- It is sensitive to both surface and sub-surface defects.
- Thick and thin work pieces can be inspected at the same time.
- UT is suitable for castings and forgings (thicker materials).
- Inspection can be completed with access to only one side of the component.
- Permits probing of joints inaccessible to radiography.
- There is no radiation hazard in UT examination and therefore no disruption of work. This
is not the case for radiography.
- Planar/linear defects can be detected irrespective of their orientation.
Limitations:
- Requires high degree of skill in interpreting pulse-echo patterns.
- Permanent record is not readily obtained.
- In some materials, such as austenitic steel, the large grain size found in welds can hide
defects when inspected by UT.
- Misreading of signals or false signals can lead to unnecessary repairs.
- Components of a thickness less than 8mm can be difficult to inspect.
- Surface must be accessible to probe and coupling medium.
48 / 102
TSCF IP 007/2016 Guidance Note on Welding
Radiographic inspection is very useful for welders and welding processes. Due to its cost
however, its use should be limited to those areas where other methods will not provide the
assurance required.
Advantages:
- Gives a permanent record when imperfections are recorded on film.
- Can be used to inspect a wide range of materials and thicknesses.
- Detects surface and sub-surface defects.
- It provides a low cost method of internal inspection when viewed using a fluoroscopic
screen.
Limitations:
- Requires skill when operating equipment and also choosing the angles of exposure.
- Access to both sides of the structure is usually required.
- Requires safety precautions to prevent radiation exposure.
- Not generally suitable for fillet/partial penetration weld inspection due to the existing void
at the root of the weld.
- Orientation of the radiation beam to non-volumetric defects is critical. It can be difficult to
detect defects such as solidification cracks, hydrogen cracks, lack of fusion etc.
49 / 102
TSCF IP 007/2016 Guidance Note on Welding
Advatages:
- Detects surface and near surface defects.
- It is not necessary to remove the coating when carrying out eddy current. Hence making
this a popular option for offshore operations.
- This method can be used for measuring coating thickness.
Limitations:
- Only conductive materials can be inspected.
- Ferromagnetic materials require consideration to address the magnetic permeability.
- The depth of a defect indication is limited.
- A high level of skill and training is required for this method.
50 / 102
TSCF IP 007/2016 Guidance Note on Welding
Advantages:
- Investigates more angles through one testing procedure.
- There is a permanent record of the inspection.
- Has the ability to define flaws in 3 dimensions.
Limitations:
- PAUT equipment is expensive.
- Equipment is more complex.
- There is no dedicated international standard.
- There are fewer manufacturers than conventional UT equipment.
- Transducers are expensive.
Advantages:
- Detects surface breaking cracks and can size length and depth of cracks (up to around
25mm deep)
- It works on paints and coatings and underwater and therefore a popular option for
offshore structures
- Lower false calls reducing costs from investigating spurious indications and all data is
saved for a later review and audit
- Can be deployed remotely by ROVs
Limitations:
- Only conductive materials can be inspected
51 / 102
TSCF IP 007/2016 Guidance Note on Welding
- Only surface breaking cracks are detected leaving the root cracks that have not yet
surfaced undetected
- Skilled or experienced technicians are needed to operate the ACFM equipment
52 / 102
TSCF IP 007/2016 Guidance Note on Welding
6 Special Welding
6.1 Introduction
This part of the information paper considers those types of welding other than the
conventional butt or fillet welds used in the majority of welded connections in a ship. It is
limited to welding of structural elements and thus the welding of machinery parts has not been
considered.
To counter-act these effects, pre-heating and post-weld heating are typically required or
specified. Pre- and post-weld heat treatment will be a function of both the material thickness
and chemical composition, particularly the carbon content. Necessary heat treatment will be
specified in the WPS.
Welding of castings in ship repair and construction is typically found in the following areas:
i) Welding of rudder, rudder horn, stern boss, stern frame, etc. for new construction.
ii) Welding of propellers
There are certain limitations when considering welding of propellers and so this will be
covered separately in this paper.
53 / 102
TSCF IP 007/2016 Guidance Note on Welding
i) Reduces the effect of the heat sink and thereby slows the cooling rate, improving
the weldability of the steel casting
ii) Helps to eliminate cracks in the weld by removing moisture from the area to be
welded.
Post-weld heat treatment of the casting and plates to be joined reduces residual stresses in the
weld but does not change the grain structure of the materials.
Pre-heating and post-weld heating are typically achieved through the use of gas-torches (using
propane gas for example) for smaller weld areas or electric heated blankets for larger welding
areas such as large castings (e.g. rudder horns). Care should be taken not to heat the work
piece too quickly as this can increase residual stresses as thinner sections of the casting will
heat more quickly than thicker sections.
During post-weld heat treatment the temperature of the work piece is raised, allowed to ‘soak’
for a defined time and then slowly reduced (see figure below).
54 / 102
TSCF IP 007/2016 Guidance Note on Welding
Figure 6.2-3 – Pre-heating of rudder horn, courtesy Figure 6.2-4 – Pre-heating of pipe
of DNV GL
The temperature of pre-heating and post-weld heating can be checked using tempilstiks
(crayons whose mark melts when the required temperature is reached), thermocouples and
digital thermometers attached to the workpiece which provide a constant temperature readout,
or optical pyrometers.
If welding is to be done on a casting to rectify a defect, the defect must first of all be
completely removed and confirmed as such via suitable non-destructive examination (e.g.
magnetic particle inspection, dye penetrant). Any resulting excavations must be shaped to
enable sufficient access for welding.
All castings in alloy steels, other than duplex and austenitic steels, are to be pre-heated before
welding. After welding is completed the weld and neighboring casting should be subjected to
further heat treatment, at a temperature not less than 550C, to remove any residual stresses
that may have built up during the welding process. The approved weld procedure used should
include the details of the pre-heat and post-weld heat treatment requirements.
However, this oxide layer may prevent a good quality weld being achieved and so must be
removed prior to welding. This is typically achieved through wire brushing of the areas to be
welded but blasting or machining can also be used. If blasting is to be used then care should
be taken that the blasting material does not introduce contaminants into the stainless steel (e.g.
grit blasting which may contain steel).
55 / 102
TSCF IP 007/2016 Guidance Note on Welding
Once the weld is completed then passivation, typically using nitric acid, is performed to
remove any contaminants introduced during welding and to help with the formation of the
protective oxide layer.
The high expansion coeffiecient and low thermal conductivity (low dissipation of heat) of
stainless steel can cause problems with distortion when welding stainless steels. Rigid fixing
of thin plates, welding sequences to reduce distortion (e.g. sequence welding) and chilled
metal backing can help to reduce distortion.
Typically weld repairs are not permitted in area A, weld repairs are permitted in area B with
the prior approval of the Class surveyor, weld repairs in area C are permitted provided they
are carried out to an approved procedure. More detailed requirements can be found in Class
Rules. Typically, the propeller will require stress relief heat treatment after welding followed
by dye penetrant inspection. Pre-heat may also be required.
56 / 102
TSCF IP 007/2016 Guidance Note on Welding
Figure 6.5-1 shows a rudder with the side shell plate welded to the internal stiffening with
numerous slot welds, together with a close up photograph of those slot welds.
Classification Society Rules contain requirements for the design and execution of slot welds.
For example for slot welds of rudder shell plating Lloyds Register’s Rules require:
i) Length of the slot shall be no less than 75mm
ii) Width of the slot shall be no less than twice the side plating thickness
iii) The ends of the slot shall be rounded and spaced not more than 150mm apart.
Other requirements for slot welds, used elsewhere in vessel construction, include the slots
being free of notches and not to be completely filled with welding.
In Figure 6.5-2 the slot design includes a 6mm diameter round bar used to help locate the
epoxy putty used to fill the slot. The epoxy putty provides a smooth external surface on the
ruder shell plate and thus prevents erosion of the slot edges.
57 / 102
TSCF IP 007/2016 Guidance Note on Welding
As with any welds, care should be taken when producing them. Defects in the slot welds can
act as stress raisers and cause premature failure of the weld as shown in Figure 6.5-3 below.
Figure 6.5-3 - Fracture initiated by poor weld profile and excessive vibration of rudder
58 / 102
TSCF IP 007/2016 Guidance Note on Welding
However, the Class Society may consider its use on the basis of certain criteria being met,
which may include:
a) The welding procedure having been performed and tested with water backing of
suitable temperature and flow rate.
b) The welding procedure having been performed on plating thickness equal to the
minimum hull plating thickness.
c) Pre-heating, for example by torch, to prevent rapid cooling and condensation with the
subsequent risk of hydrogen cracking.
d) Additional non-destructive testing of the welds.
e) The use of low hydrogen electrodes.
Wet underwater welding uses DC current and insulated gloves to maximize the protection of
the diver from being electrocuted. The electrodes typically used are similar to the Manual
Metal Arc electrodes used for dry welding in that they are comprised of an electrode core
surrounded by flux which is then protected by a waterproof coating. This waterproof coating
protects the flux from absorbing water and burns away as the welding rod is consumed.
With wet welding hydrogen cracking presents a significant risk to the quality of the resulting
weld. During the welding process the welding arc dissociates the sea water into oxygen and
hydrogen. The oxygen reacts with elements in the weld resulting in an environment rich in
hydrogen. This hydrogen can dissolve into the molten weld and become trapped as the weld
cools. If the dissolved hydrogen is present in sufficient amounts it can cause porosity in the
weld or even crack the weld.
59 / 102
TSCF IP 007/2016 Guidance Note on Welding
The hydrogen produced by the welding process not only adversely affects the quality of the
weld, it also poses a danger to the welder. If the environment in which the wet weld is
produced does not enable the rapid dispersion of the produced hydrogen as small bubbles it
can accumulate into gas pockets that could cause an explosion when ignited by a heat source,
such as a piece of hot slag.
60 / 102
TSCF IP 007/2016 Guidance Note on Welding
Due to their use of steel and aluminium superstructures, explosion welding is often found on
large passenger ships.
With friction stir welding, a rotating tool is introduced into the gap between the two metal
plates to be joined. The friction between the rotating tool and the plates creates heat, which
reduces the yield stress of the materials and allows them to be ‘stirred’ together at a
temperature below their melting point. The plates to be joined must be tightly clamped into
position to prevent them moving during the operation. There should be no gap between the
plates during the process, allowing the weld to be created without the need of filler material.
61 / 102
TSCF IP 007/2016 Guidance Note on Welding
The rotating tool is pressed down into the gap between the two plates, the probe part of the
tool first touches the plates, creating friction and thus heat, reducing the yield stress of the
plates and thus allowing the probe to be pressed down into the gap between the plates. The
tool shoulder then reaches the surface of the plates providing additional heating and
preventing material flowing away from the fusing gap. The tool then traverses along the gap
heating the plates and stirring them together, thus creating the ‘weld’.
There are some disadvantages of friction stir welding the main ones for shipbuilding being the
relatively inflexible operation as the process is only applicable to butt welds and requires the
plates to be heavily clamped. In addition, when the tool is withdrawn at the end of the weld
the probe will leave a small hole in the gap between the plates.
62 / 102
TSCF IP 007/2016 Guidance Note on Welding
Laser hybrid welding is currently being trialed by major European shipyard building
passenger ships, e.g. Meyer Werft, Fincantieri. The process uses a combination of a laser and
an arc welding process (such as MAG) within the same weld pool to produce a butt weld with
reduced distortion, due to lower heat input from laser welding, and an increased gap between
the plates to be joined, due to the filler metal being provided by the arc welding process.
However the gap between the plates to be joined is still limited (circa 1mm) and thus the
process is currently limited to the panel line.
63 / 102
TSCF IP 007/2016 Guidance Note on Welding
In shipbuilding resistance welding can be found as both spot welding and seam welding. Spot
welding is found in the form of stud welding, where typically threaded studs are welded to a
metal panel to provide an anchor for linings, insulation, containment systems etc.
64 / 102
TSCF IP 007/2016 Guidance Note on Welding
65 / 102
TSCF IP 007/2016 Guidance Note on Welding
Appendix 1
Welding Experience
66 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of
defect/damage
67 / 102
TSCF IP 007/2016 Guidance Note on Welding
68 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of
defect/damage
69 / 102
TSCF IP 007/2016 Guidance Note on Welding
70 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of
defect/damage
71 / 102
TSCF IP 007/2016 Guidance Note on Welding
72 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of - Cracks at erection fillet weld joint of T.BHD in way of vertical stiffener
defect/damage
73 / 102
TSCF IP 007/2016 Guidance Note on Welding
How discovered - Alleged oil leakage from COT to WBT through oil-tight bulkhead was
reported.
- Leak test was used to identify the extent of the cracks.
Probable cause of - Excessive gap (about 9mm to 10 mm) between T. BHD and vertical
Damage stiffener on the occasion of erection fillet welding.
Description of Repair - Affected T. BHD and vertical stiffener were partly cropped and
renewed. The concerned fillet weld was gouged out and re-welded with
full penetration weld.
Preventative - Excessive gap shall be avoided on the occasion of erection welding.
action/lessons learned - Highlights the importance of good fit-up inspection and following the
WPS.
74 / 102
TSCF IP 007/2016 Guidance Note on Welding
Location of damage: - Fillet weld joint between T. BHD and bilge hopper plate
Photo/Sketch of
defect/damage
Description of - Pin hole and cracks in the fillet weld joint between T. BHD and bilge
defect/damage hopper plate
- Type of weld – Fillet weld
- Welding method – CO2 welding
- Plate thickness‐T. BHD: 18mm AH36
‐Hopper Plate: 30mm and 20mm AH36
.
How discovered - Oil mark was found on the occasion of the internal examination at class
75 / 102
TSCF IP 007/2016 Guidance Note on Welding
periodical survey.
- PT was used to identify the extent of the defects.
Probable cause of - Presumably welding conditions of the approved Welding Procedure
Damage Specifications (WPS) were not observed and/or environmental condition
of welding work was not appropriate.
Description of Repair - Pin hole and cracks were permanently repaired by gouging and re-
welding.
Preventative - Welding shall be conducted in accordance with the approved WPS.
action/lessons learned - Moisture, grease, rust, etc. shall be removed from the intended weld part
properly.
76 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of
defect/damage
The defect was found when inert gas was seen to be bubbling through water
on the main deck in way of an erection butt weld located close to the deck
store vertical stiffeners.
77 / 102
TSCF IP 007/2016 Guidance Note on Welding
78 / 102
TSCF IP 007/2016 Guidance Note on Welding
How discovered - Inert gas was seen to be bubbling up through water on the main deck
in way of an erection weld located close to the vertical stiffeners of a
deck store bulkhead.
- MPI was used to identify the extent of the defect. Subsequent
gouging and further MPI ensured the true extent of the defect was
found.
Probable cause of Inspection of the weld revealed that a weld procedure had been used
Damage whereby, after a root run is applied, specially prepared welding wire
is placed into the weld gap. An automatic weld is then made using
two electrodes; the first electrode melts the embedded wire in the gap
and the second provides a capping run of weld.
Description of Repair - All main deck plating welds were examined with UT to identify lack
of inter-run fusion and sidewall fusion.
- All defective areas were gouged and re-welded
Preventative - Newbuild specifications now require that all weld procedures are
action/lessons learned submitted to the Buyer.
79 / 102
TSCF IP 007/2016 Guidance Note on Welding
Location of damage: Main Deck: Erection welds in way of No. 4 & No.5 COT/WBT’s
Photo/Sketch of
defect/damage
80 / 102
TSCF IP 007/2016 Guidance Note on Welding
Description of - Porosity in the root run, with long pores causing wormholes.
defect/damage - Material –Grade ‘A‘ Mild Steel,
- Type of weld – Full penetration butt weld - erection welds
- Welding method - Likely, FCAW with gas shielding, using backing
strip, although unconfirmed
- NDT applied - UT and RT
- Plate thickness - 12mm
How discovered - Initial discovery from surface visual defect under corrosion. Further
investigation undertaken with UT and RT
81 / 102
TSCF IP 007/2016 Guidance Note on Welding
Location of damage:
82 / 102
TSCF IP 007/2016 Guidance Note on Welding
Probable cause of Welding is done at overhead position. Due to the height of T bar being small,
Damage/defect welding to build up the scallop becomes difficult. Therefore, weld zone of
scallop has more possibility of defect.
Description of Repair Gouge/ Reweld
Preventative Extensive NDT at this location.
action/lessons learned Consider changing the detail to something easier to construct, i.e. a larger
scallop closed with a collar plate.
83 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of
defect/damage
Poor workmanship.
84 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of
defect/damage
85 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo/Sketch of
defect/damage
86 / 102
TSCF IP 007/2016 Guidance Note on Welding
Location of damage:
Photo/Sketch of
defect/damage
87 / 102
TSCF IP 007/2016 Guidance Note on Welding
Description of Welding defect in hopper corner. Voids and slag inclusions. Intermittent
defect/damage defects along entire length of hopper corner. Material HTS 32.
How discovered Discovered due to cargo oil leakage into ballast tank after short time in
service.
Probable cause of Poor fit-up – gap too large. Poor welding with insufficient back-
Damage gouging/cleaning between welding passes, likely that WPS not followed.
Description of Repair Gouge/reweld. Due to poor fit up (see macro section) inserts were also
required.
Preventative Fit-up inspection before welding commencement would have detected the
action/lessons learned poor fit-up. This could have been corrected by inserts or possibly building up
the edge of the sloping plate (“buttering”). The defects could have been
picked up at an early stage of production by a competent NDT operator.
The owner may consider requiring full penetration welds at this joint to ease
NDT. With a partial penetration weld UT will detect the gap at the root and
results may be unclear.
88 / 102
TSCF IP 007/2016 Guidance Note on Welding
Location of damage: This relates to a crack on a CU3 propeller blade which developed during
service.
Photo/Sketch of
defect/damage
89 / 102
TSCF IP 007/2016 Guidance Note on Welding
How discovered This relates to a crack on a CU3 propeller blade which developed during
service.
Probable cause of Most likely the crack could have initiated due to a sudden impact.
Damage
Description of Repair The requirements for weld repair of copper alloy propellers are given in
Class Rules for Materials.
Although the defect falls in Zone A for this repair, we do not envisage or
recommend any condition of Class or memorandum provided that the repair
is carried out in accordance with the Class requirements.
Preventative
action/lessons learned
90 / 102
TSCF IP 007/2016 Guidance Note on Welding
Location of damage:
Photo/Sketch of
defect/damage
Description of During rudder inspection it was found that a horizontal crack has developed
defect/damage on the rudder stock (please see the pictures attached) on about ¾ of total
perimeter. Crack depth was measured with UT and it varied from15 mm to
20 mm.
Rudder stock diameter at the cracked area is 524 mm. The material is forging
with carbon content less than 0.23.
91 / 102
TSCF IP 007/2016 Guidance Note on Welding
Location of defect: Fracture noted in a transverse erection weld in the main deck plating.
Photo/Sketch of defect
92 / 102
TSCF IP 007/2016 Guidance Note on Welding
The defect was first detected from the crack on the main deck, however
following the internal inspection it was noted to have propagated from the
construction weld of the bulb profile.
Description of damage - Through thickness crack found in the deck erection weld during
visual inspection by ships staff. Further visual inspection and MPI/
UT carried out to confirm extent of the defects.
- Type of weld – Butt erection weld
- Plate thickness – Deck 21mm A 36, Bulb Profile 300x12mm A 36
Probable cause of - Samples of the butt weld in deck longitudinals were sent to the
defect Classification Society for further analysis including x-ray, macros and
microstructure examination. Examples of the results shown below:
93 / 102
TSCF IP 007/2016 Guidance Note on Welding
Micrograph of the cavity in the weld root area. A crack was observed from the cavity to the
outer surface.
94 / 102
TSCF IP 007/2016 Guidance Note on Welding
Description of Repair - Defective welds were gouged and re-welded with suitable edge
preparation. Insert repairs carried out where defects had propagated
to the base material.
- Following completion of repairs MPI and UT carried out.
95 / 102
TSCF IP 007/2016 Guidance Note on Welding
Photo//Sketch of
defect/damage
96 / 102
TSCF IP 007/2016 Guidance Note on Welding
Description of Repair - Unknown, but the work has to be re-done. Either gouge and re-weld
or new pieces.
97 / 102
TSCF IP 007/2016 Guidance Note on Welding
Appendix 2
Sample WPS, WPQR, WQTR
98 / 102
TSCF IP 007/2016 Guidance Note on Welding
99 / 102
TSCF IP 007/2016 Guidance Note on Welding
100 / 102
TSCF IP 007/2016 Guidance Note on Welding
101 / 102
TSCF IP 007/2016 Guidance Note on Welding
Appendix 3
References
1. “The Welding Handbook for maritime welders”, UNITOR/Wilhelmsen Ships Services,
11th edition, Revision 0.
2. “Rec. No. 47 Shipbuilding and Repair Quality Standard”, IACS, Rev.7, June 2013.
7. “The International Safety Guide for Oil Tankers & Terminals” (ISGOTT), Fifth
edition, Witherby & Co., Ltd., 2006.
9. DNV GL Rules for the Classification of Ships, Part 2 “Materials and Welding”,
January 2016.
10. Course Material - CSWIP Visual Welding Inspector Level 1, TWI Training and
Examination Service, Cambridge, United Kingdom.
102 / 102