ARCHITECTURAL
1.All dimensions are in millimeters unless otherwise specified.
2.All dimesnions should be checked on site and any discrepancy reported to the architect.
3.All works to be carried out in accordance with local authority regulations.
4.Use figured dimesnions only,do not scale from drawing.
5.walls above 200 mm thick to be reinforced with hoop iron at alternate courses.
6.DPC to be laid under all walls and to be min.150mm above floor level.
7.All drainage pipes passing under building and driveway to be encased with 150mm
concrete surround.
8.All inspection chambers in driveways to heavy duty covershave.
9.All reinforced concrete works is to be in accordance with engineers details.
10.500 gauge polyethene DPM and anti termite treatment provided undergroundfloor
concrete slab.
11.Foundation depth to be determined on site as per engineer instruction.
12.Permanent ventilation to be provided to all openings as indicated on plans above.
CIVIL WORKS
PUBERI SPAR
1.All soils under slab and around external foundation to be treated
around external foundations to be treated for termite control,
2.All soils on cut embarkments to be stabilised,slope
not to exceed the natural angle of repose.
SOUND PROOFING 3.All slabs at ground level to be poured over 1000
COMPANY KENYA gauge polyethene sheeting on 50mm stone blinding
on hardcore.
CL
S PROPOSED SITE
ND
TLA STRUCTURAL WORKS
ES 1.All black cotton soil to be removed from all building
W
plinths.All buildings to be clear of black cotton doil to a distance
CL CONSULATE OF
of 3m.
DS LIBERIA
LAN MU 2.All basement columns to be provided with angle iron protection
SKYFIRE T TH 1500mm high.
ES W I
W ES
TL MICRO ENTERPRISES THI 3.All paved surfaces to be clear of black cotton soil to
RO
AN AD a distance of 500mm outside the edge of the surface.
DS 4.Refer to structural engineers details for all RCC works.
RO
AD 5.Foundation depth to be determined on site to structural engineers
PRIDE INN HOTEL approval.
POS KENYA 6.All walls less than 200mm thick to be reinforced with hoop
irons at every alternate courses.
GRAFFINS 7.All adjacent RC works and masonry walls to be tied with strap irons
AD at every course.
RO
US
I
MECHANICAL WORKS
TA
1.All sanitary fittings,doors,windows and lifts to schedules.
N.I.T 2.All plumbing and drainage to comply with city council specification.
3.All service ducts to be accesible from every floor
4.SVP denotes soil vent pipe to be provided at the head of the drainage.
STATUS PROPOSED LEARNING
GLOBAL TOURS MA
GI
CA RESOURCE CENTRE
LS
EA
GO SO
LD NS
EN
M
EM
SLATER AND WHITTAKER OR
IE
S
JIMMY'S CLOSE OCTOBER FIRM
TA TOURS&TRAVELS
DESIGN CONSULTANCY
SITE WESTLANDS,NAIROBI
QS09-006/017
REG NO:
SITE LOCATION PLAN
MOHAMED ABDI
DRAWN BY:
LRCC1452
LAND REG NO:
DRAWING NAME: SITE LOCATION PLAN
CHECKED BY: MR MBOGUA
1:400
SCALE:
GSPublisherVersion 0.1.100.100