Fit - Up and Visual Examination Report: Attachment Drawing Joint Detail
Fit - Up and Visual Examination Report: Attachment Drawing Joint Detail
Revision : 0
FIT - UP AND VISUAL EXAMINATION REPORT
Date : October 11, 2018
PT. UNIXINDO EKATAMA SENTANA Page : 1 of 1
Job No : - Drawing No : -
Project : - Procedure No : QP-23
Costumer : - Applicable Code : ASME SECTION IX
Check of Completed Weld
Part / Weld Welding Welder Fit-Up Check
Reinforcement
WPS No Thickness Remarks
Fillet Weld Surface
Identification Process Stamp No. Alignment Root Opening Angle Grove Grove
L1 L2 Tr
TC-2 003/WPS/SMAW SMAW Z 15 6 to 6 0 2 60⁰ 2 - - - ACC -