TEST METHOD:AASHTO T127, ASTM C136 (Dry) ASTM C117 Procedure A (Wet), BS 812 PART 103

This document contains the results of two tests: [1] A sieve analysis test to determine the particle size distribution of a soil sample, and [2] A moisture-density relationship test to establish the optimum moisture content and maximum dry density of a soil. The sieve analysis showed that the soil sample has particles ranging in size from 37.5mm to 0.075mm. The moisture-density relationship test established that the optimum moisture content is 13.4% and the maximum dry density is 1.791 g/cc.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views

TEST METHOD:AASHTO T127, ASTM C136 (Dry) ASTM C117 Procedure A (Wet), BS 812 PART 103

This document contains the results of two tests: [1] A sieve analysis test to determine the particle size distribution of a soil sample, and [2] A moisture-density relationship test to establish the optimum moisture content and maximum dry density of a soil. The sieve analysis showed that the soil sample has particles ranging in size from 37.5mm to 0.075mm. The moisture-density relationship test established that the optimum moisture content is 13.4% and the maximum dry density is 1.791 g/cc.
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 8

SM 3

Bin Hafeez Gen.Cont.Est,


ABU DHABI UAE
AECOM MIDDLE EAST
Sieve Anlysis (Particle Size Distribution)
TEST METHOD:AASHTO T127,ASTM C136(Dry)ASTM C117 procedure A (wet), BS 812 PART 103
Client Abu Dhabi Muncipality
Prroject Internal Roads and Services in Muhammad Bin Zayed City
Consultant Jacobs International Inc Req No
Cotract no MBZ - 05 Sector Z - 36 BHE Sample No 1
Cotractor Bin Haffez General Contractor Est, BHE Project Code PA 089
Sample Description Pipe line Formation Date of Sample 4/10/2012
Source Site Date Test Started 6/10/2012
Sample By Consultant Date Test Completed 7/10/2012
Location Sector Z- 36

Sieve size Ret WT Ret % Passing% Average Ret WT Ret % Passing%

37.5 0.0 100.0 100.0 0.0 100.0

25.0 0.0 0.0 100.0 100.0 0.0 0.0 100.0

19.0 0.0 0.0 100.0 100.0 0.0 0.0 100.0

9.50 0.0 0.0 100.0 100.0 0.0 0.0 100.0

4.75 18.4 1.4 98.6 98.5 21.6 1.5 98.5

2.00 356.8 26.9 71.7 71.5 381.6 27.2 71.2

0.425 295.4 22.3 49.4 49.6 301.2 21.5 49.7

0.075 495.7 37.4 12.0 11.8 533.6 38.1 11.6

Pan 158.7 12.0 0.0 0.0 163.0 11.6 0.0

Total 1325 100.0 1401 100.0

Gradation Curve
8

3
2

100
Passing %

90

80

70

60

50

40

30

20

10

0
0.0 0.1 1.0 10.0 100.0
Sieve Size

Remarks

Tested by Checked By Witness By.


Lab Technician (Cont) Material Engineer (Contractor) (Consultant)
SM 3
BIN HAFEEZ GEN COT EST,
ABU DHABI UAE
AECOM MIDDLE EAST
Dry Density/Moisture Content Relationship
TEST METHOD:AASHTO T180, ASTM D 1557,BS 1377: Part 4
Client Abu Dhabi Muncipality
Prroject Internal Roads and Services in Muhammad Bin Zayed City.
Consultant Jacobs International Inc
Cotract no MBZ - 01 Sector Z -31 BHE Sample No 1
Cotractor Bin Haffez General Contractor Est, BHE Project Code PA 090
Sample Description Pipe line Formation Date of Sample 8/10/2012
Source MCG 8 Date Test Started 9/10/2012
Sample By Consultant Date Test Completed 10/9/2012
Location MCG 8
Wet Density calculation
Wt of Mould+Sample (g) 8818 9021 9160 9220 9087

Wt of Mould (g) 4890 4890 4890 4890 4890

Wet Density (g/cc) 1.848 1.943 2.008 2.037 1.974

Dry Density Calculation


Container No 6 2 14 27 26

Cont + Wet Sample (g) 487.0 476.0 532.0 541.0 498.7

Cont + Dry Sample (g) 457.0 439.0 488.0 491.9 455.1

Container Weight (g) 107.0 100.0 137.4 148.4 184.0

Moisture Content (%) 8.6 10.9 12.5 14.3 16.1

Dry Density (g/cc) 1.702 1.752 1.785 1.782 1.701

Mould No 1
1.800 Proctor Curve
Density (g/cc)

Wt of Rammer 4.5 Kg
2

1.780

D.D.Curve
No of Layers 5
1.760 Polynomial
(D.D.Curve)
MDD
Blows per Layer 56
1.740
Initial Moisture % 4.6
1.720
Mould Volume 2126

1.700
O.M.Content 13.4
1.680 Moisture Content (%) M.D.Density 1.791
7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0

Remarks

Tested by Checked By Witness By.


Lab Technician (Cont) Material Engineer (Contractor) (Consultant)

V.Anil
V.Anil
From CP6080.AQ
Issue No 8
Date
California Bearing Ratio (CBR) Page 1 of 1
TEST METHOD:TEST METHOD:ASTM D 1883,AASHTO T193
Client Abu Dhabi Muncipality
Prroject Internal Roads and Services in Muhammad Bin Zayed City
Consultant Jacobs International Inc Req No
Cotract no MBZ 05 Sector z - 17/01 BHE Sample No 2
Cotractor Bin Haffez General Contractor Est, BHE Project Code PA 089
Sample Description Road Formation Date of Sample 28/8/2012
Source Site Date Test Started 1/9/2012
Sample By Consultant Date Test Completed 5/9/2012
Location Road MCE2 Ch:0+150.00 to 0+280.00 Ring Factor 0.2374

Compaction % at 10 Blows = 82.1 Dial Readings (kN)


Density&Moisture Wet Density O.M.C M.D.D
Penetration No of Blows
Proctor Density 2.031 13.4 1.791
Dial Reading
Achieved 1.668 13.4 1.471 (mm) 10 Blows 30 Blows 65 Blows
Compaction % at 30 Blows = 86.2
0.00 0.00 0.00 0.00
Density&Moisture Wet Density O.M.C M.D.D. 0.64 0.35 1.00 1.60
Proctor Density 2.031 13.4 1.791 1.27 0.70 1.90 3.10
Achieved 1.750 13.4 1.543 1.91 1.10 2.80 4.50
2.54 1.50 3.70 5.70
Compaction % at 65 Blows = 91.1
3.18 2.00 4.50 7.20
Density&Moisture Wet Density O.M.C. M.D.D. 3.81 2.50 5.30 8.30
Proctor Density 2.031 13.4 1.791 4.45 3.00 6.00 9.60
Achieved 1.851 13.4 1.632 5.08 3.50 6.70 10.70
Cortd.Dial Reading 10 Blows 30 Blows 65Blows 5.72 3.90 7.30 11.70
2.5 ' 1.50 2.68 3.70 6.62 5.70 10.19 6.35 4.25 7.90 12.60
5.0' 3.50 4.17 6.70 7.99 10.70 12.76 6.99 4.60 8.30 13.50
7.62 4.75 8.60 14.00
Achieved CBR Value at Comp. % 95.0 8.0 8.26 4.80 8.90 14.30
Required CBR Value at Comp. % 95.0 > 10.0
Dial Readings (kN)

Penetraction Vs Dial Reading Penetration Vs Dial Reading


16.00
14.00 10 Blow s
30 Blow s
2

65 Blow s
CBR Values

Pnetraction
C olum n AO
12.00 12.00
2

Comp %
CBR Value
Comp.%
10.00

8.00
8.00 8.0
2

6.00
4.00

4.00

0.00
2.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
Penetration (mm)
88.00 90.00
Achieved92.00
Comp.(%) 94.00 96.00

Remarks

Tested by Checked By Witness By.


Lab Technician Material Engineer (Contractor) (Consultant)
BIN HAFEEZ GEN CONT EST,
ABU DHABI UAE
JACOBS INTERNAL HOLDING INC
Determination of Plasticity Index ( ASTM D4318; AASHTO T89&90)
Client Abu Dhabi Muncipality
Prroject Internal Roads and Services in Muhammad Bin Zayed City

Consultant Jacobs International Inc Req No


Cotract no MBZ 05 Sector Z - 17/01 BHE Sample No 2
Cotractor Bin Haffez General Contractor Est, BHE Project Code PA 089
Sample Description Formation(Road) Date of Sample 28/8/2012
Source Site Date Test Started 2/9/2012
Sample By Consultant Date Test Completed 4/9/2012
Location Road MCE2 Ch:0+150.00 to 0+280.00
Determination of Plastic Limit (ASTM D4318; AASHTO T90)
Container No (No) 4 5
Cont + Wet Sample (g) 41.23 40.83
Cont + Dry Sample (g) 38.50 38.52
Container Weight (g) 28.30 30.00
Moisture Content (%) 26.8 27.1
Determination of Liquid Limit (ASTM DD4318; AASHTO T89)
No of Blows (No) 30 25 20
Container No (No) 1 2 3
Cont + Wet Sample (g) 52.41 52.11 51.47
Cont + Dry Sample (g) 46.67 46.13 45.60
Container Weight (g) 29.73 29.52 30.20
Moisture Content (%) 33.9 36.0 38.1
33.1
M o istu re co n tan t

39.0

38.0

37.0

36.0

35.0

34.0

33.0
17 19 21 23 25 27 29 31 33
Nos of blows

Liquid Limit (LL) = 36.0 Plastic Limit (PL)= 26.9

Plasticity Index (PI)= 9.1

Remarks:

Tested by Checked By Witness By.

Lab Technician Material Engineer (Contractor) (Consultant)