IGNOU MBA MS-52 Solved Assignments 2010
IGNOU MBA MS-52 Solved Assignments 2010
Note: Please attempt all the questions and send it to the Coordinator of the study
Center you are attached with
Solution: This is the initial phase of any project. In this phase information is collected
from the customer pertaining to the project and the requirements are analyzed. The entire
project has to be planned and it should be done in a strategic manner. The project
manager conducts the analysis of the problem and submits a detailed report to the top
project justification, details on what the problem is a method of solving the problem, list
of the objectives to be achieved, project budget and the success rate of completing the
project. The report must also contain information and the project feasibility, and the risks
involved in the project.
Project management life cycle is the integrated part of management. It is attach with
project responsibility or failure of a project. For the MBA assignments it is the most
valuable chapter in production management.
Trade off analysis: To understand and examine the various alternatives which could be
considered.
Estimation: To estimate the project cost, effort requires for the project and functionality
of various process in the project.
System design: Choose a general design that can fusil the requirements.
Project evolution: Evaluate the project in terms of expected profit, cost and risks involved
marketing phase.
A project proposal is prepared by a group of people including the project manager. This
proposal has to contain the strategies adopted to market the product to the customers.
Design phase: This phase involves the study of inputs and outputs of the various project
stages.
Execution phase: In this phase the project manager and the teams members work on the
project objectives as per the plan. At every stage during the execution reports are
prepared.
Control – Inspecting, Testing and Delivery phase during this phase. The project team
works under the guidance of the project manager. The project manager has to ensure that
the team working under his, implements the project designs accurately, the project
manager has to ensure ways of managing the customer, perform quality control work.
Closure and post completion analysis phase upon satisfactory completion and delivery of
the intended product or service the staff performance has to be evaluated. Document the
lessons from the project. Prepare the reports on project feedback analysis followed by the
project execution report.
The preparation stage involves the preparation and approval of project outline, project
plan and project budget.
The next stage involves selecting and briefing the project team about the proposals
followed by discussions on the roles and responsibility of the project member and the
organization.
===========================================================
Financial analysts often compare financial ratios (of solvency, profitability, growth, etc.):
* Past Performance - Across historical time periods for the same firm (the last 5 years
for example),
* Future Performance - Using historical figures and certain mathematical and statistical
techniques, including present and future values, This extrapolation method is the main
source of errors in financial analysis as past statistics can be poor predictors of future
prospects.
* Comparative Performance - Comparison between similar firms.
These ratios are calculated by dividing a (group of) account balance(s), taken from the
balance sheet and / or the income statement, by another, for example :
n / equity = return on equity
Net income / total assets = return on assets
Stock price / earnings per share = P/E-ratio
Comparing financial ratios is merely one way of conducting financial analysis. Financial
ratios face several theoretical challenges:
* They say little about the firm's prospects in an absolute sense. Their insights about
relative performance require a reference point from other time periods or similar firms.
* One ratio holds little meaning. As indicators, ratios can be logically interpreted in at
least two ways. One can partially overcome this problem by combining several related
ratios to paint a more comprehensive picture of the firm's performance.
* Seasonal factors may prevent year-end values from being representative. A ratio's
values may be distorted as account balances change from the beginning to the end of an
accounting period. Use average values for such accounts whenever possible.
* Financial ratios are no more objective than the accounting methods employed.
Changes in accounting policies or choices can yield drastically different ratio values.
* They fail to account for exogenous factors like investor behavior that are not based
upon economic fundamentals of the firm or the general economy (fundamental analysis)
Financial analysts can also use percentage analysis which involves reducing a series of
figures as a percentage of some base amount For example, a group of items can be
expressed as a percentage of net income. When proportionate changes in the same figure
over a given time period expressed as a percentage is know as horizontal analysis.
Vertical or common-size analysis, reduces all items on a statement to a “common size” as
a percentage of some base value which assists in comparability with other companies of
different sizes Another method is comparative analysis. This provides a better way to
determine trends. Comparative analysis presents the same information for two or more
time periods and is presented side-by-side to allow for easy analysis.
===========================================================
===========================================================
A big mistake inexperienced project leaders make is scheduling tasks before the tasks are
defined. Inexperienced project leaders try to combine these two planning steps
by listing the tasks to be performed and working out a schedule for the list.
Defining tasks should be done first, at least for complex projects, because
it’s just not obvious how tasks should be sequenced and structured as will be
explained below. Defining tasks means defining the inputs, the outputs and the
tasks the outputs support. Just having a list of tasks does not mean that the
inputs, outputs and the work needed to turn inputs into outputs are understood.
It should be obvious that schedules constructed without such understanding are
not likely to be executable without numerous corrections.
N-Squared diagrams are a simple but effective way to define tasks, determine the
optimum sequencing of tasks and quickly see which tasks can be done in parallel to
maximize lead and lag times. A detailed description of how to construct and interpret N-
Squared diagrams for project tasks is found in my book blog.
===========================================================
5) Draw the project diagram from the information given below. Also
identify the critical path and determine the project completion time.
Task A B C D E F G H I J K L
M
Time (Hours) 16 11 14 9 12 10 30 19 11 7 40 9
14
===============================================================
===============================================================