This document outlines special procedures for a construction project, including: 1. Accelerating the work schedule if the contractor falls behind, at no additional cost to the owner. The owner may also request an earlier completion date and the contractor must provide a cost proposal. 2. The owner's safety requirements for personal protection like fall protection, protective clothing, safe tools and equipment, scaffolding, ladders, hazard protection, and safety training. 3. The contractor must report accidents requiring off-site medical treatment to the owner and implement a safety program on the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
163 views2 pages

01 3500 Special Procedures

This document outlines special procedures for a construction project, including: 1. Accelerating the work schedule if the contractor falls behind, at no additional cost to the owner. The owner may also request an earlier completion date and the contractor must provide a cost proposal. 2. The owner's safety requirements for personal protection like fall protection, protective clothing, safe tools and equipment, scaffolding, ladders, hazard protection, and safety training. 3. The contractor must report accidents requiring off-site medical treatment to the owner and implement a safety program on the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

SECTION 01 3500

SPECIAL PROCEDURES

0.1 ACCELERATION OF WORK

A. Complete the Work in accordance with Construction Schedule. If Contractor falls behind schedule, take
such asctions as are necessary, at no additional expense of the Owner, to bring progress of The Work
back in accordance with schedule.

B. Owner may request proposal for completion of The Work at date earlier than expiration of Contract
Time. Promptly provide requested proposal showing cost of such acceleration of The Work. Consult
with Owner and Architect regarding possible optins to decrease cost of such acceleration. If Owner
determines to order such acceleration of the work , change in the Contract Sum and Contract Time
resulting from acceleration will be included in a Change Order.

0.2 OWNER’S SAFETY REQUIREMENTS

A. Personal Protection:
1. Contractor shall ensure :
a. Positive means of fall protection, such as guardrails system, safety net system, personal fall
arrest system, etc., is provided to employees whenever exposed to a fall six feet or more
above a lower level.
b. Personnel working on Project shall wear hard hats and safety glasses as required by
regulation and hazard.
c. Personnel working on Project shall wear long or short sleeve shirts, long pants, and hard-
toed boots or other sturdy shoes appropriate to type and phase of work being performed.

B. Contractor Tools and Equipments:


1. Contractor shall ensure:
a. Tools and equipment are in good working condition, well maintained, and have necessary
guard in place.
b. Ground Fault Circuit Interruptors (GFCI) is utilized on power cords and tools.
c. Scaffoldings and man lifts are in good working condition, erected and maintained as required
by governmental regulations.
d. Ladders are in good condition, well maintained, used as specified by manufacturer, and
secured as required.

C. Miscellaneous:
1. Contractor shall ensure:
a. Protection is provided on protruding rebar and other similar objects.
b. General Contractor Superintendent has completed the OSHA 10-hour construction outreach
training course or equivalent.
c. Implementation and administration of safety program on Project.
d. Materials Safety Data Sheet (MSDS) are provided for substances or materials for which an
MSDS is required by governmental regulations before bringing on site.
e. Consistent safety training is provided to employees on Project.

Project Number 1 Section 01 3500


Project Name Project Date Special Procedures
2. Report accidents involving injury to employees on Project that require off-site medical treatment
to Owner’s designated representative.

END OF SECTION