04 - Case History of Framework For Observational Method To Be Used For ERSS - GBW
04 - Case History of Framework For Observational Method To Be Used For ERSS - GBW
Speaker:
Er. Ng Chew Chiat, David
Prepared by:
Er. David Ng, Er. Dr. Victor Ong, Mr David Ong
ONE SMART Engineering
1
Content of Presentation:
1) Introduction on Framework of Observational
Approach
2
Content of Presentation:
1) Introduction on Framework of Observational
Approach
3
Design Parameter:
Characteristics vs Most Probable
Adopted for normal designs using Likely behaviour of the ERSS during
EC7 construction
4
Observational Method Approach
5
Design Procedure
Step 1: Characteristic Design
6
Design Procedures
Step 1: Characteristic Design
Submission:
- For Design Code Compliance (BCA/EC7)
- To ensure design can be implemented on site
with due consideration of any forms of risks.
7
Design Procedure
Step 2: Most Probable Design
8
Design Procedures
Step 2: Most Probable Design
Supplement:
- This step is good practice to explore for
potential optimisation of existing design in Step
1.
Sensitivity Study:
- Requires ability to identify most attributable
components, where change in its parameter
can lead to major evolution of ERSS system.
9
Content of Presentation:
1) Introduction on Framework of Observational
Approach
10
1. Case Study on Strut Omission
using Observational Method
(Down Town Line Project C922 –
Expo Station and Overrun Tunnels)
11
12
Overrun Tunnel along Down Town Line Project
13
14
15
Photo showing ORT (RF)
Plaza 8
Plot 61 Plot 60
(Changi City) (UE
Bizhub
DBS East)
Bank
Plaza 8
16
Photo showing ORT (ESS)
Plot 60
Plot 61
1st Base Slab
Casting(A8~A15)
17
Overrun Tunnel Cross Section:
S3 at 98.5mRL
S4 at 93.8mRL
S5 at 88.8mRL
S6 at 84.5mRL
Estuarine Layer 5 7
19
General Information on Down Town Line Project
Construction Method:
- Bottom-Up Method
- 23m wide
- 18m to 25m deep
Earth Retaining Structural System:
- 1.0m thick diaphragm wall ERSS
- ERSS embedment is 0.42H to 0.5H
(H is total excavation depth)
20
General Information on Circle Line Project
Shoring System:
- S3: H-beam at 98.5mRL
- S4: H-beam at 93.8mRL
- S5: H-beam at 88.8mRL
- S6: H-beam at 84.5mRL (Omitted)
Ground Improvement:
- No ground improvement as Final Excavation
Level is formed at OA layer
21
Step 1: Characteristic Design
(Down Town Line Project C922)
22
Design Procedure
Step 1: Characteristic Design
23
Design Procedures
Step 1: Characteristic Design
Soil Parameter:
- Soil Parameters are interpreted using
methods in accordance to local authority
requirements.
- Drained and Undrained Analyses are
performed (To adopt governing case)
24
Step 2: Most Probable Design
(Down Town Line Project)
25
Design Procedure
Step 2: Most Probable Design
26
Design Procedures
Step 2: Most Probable Design
Design Parameter:
- In view both Drained and Undrained Analyses
Conditions are performed to assess the ERSS,
the less governing case shall serve as the most
probable design.
- This enables the determination of OM level in
the review level
- The OM level sets the criteria for adoption of
Most probable Design (Undrained Case)
instead of Characteristic Design (Drained Case)
27
Design Procedures
Step 2: Most Probable Design
Potential Evidence:
- Observational Method can provide supporting
data showing potential evidence that the soil
layers are behaving under Undrained Case which
is less critical compared to Drained Case.
28
Design Procedures
Step 2: Most Probable Design Parameters
Summary table of comparisons between parameters in characteristic
design and most probable design:
Parameters Characteristic Design Most Probable Design
Number of layer of 4 layers of struts (S3, S4, S4 & S6) 3 layers of struts (S3, S4 & S5)
struts
Soil Model Dained MC Undrained MC
29
Instrumentation Results
(Down Town Line Project)
30
Instrumentation Results
Upon excavating down to
88.8mRL to install Strut S5,
the actual wall deflection is
much lower than predicted
wall deflection.
31
Observed vs Prediction (Left & Right Wall)
Section Predicted Predicted Observed
Deflection based Deflection Deflection
on Characteristic based on most
Design probable design
Section B-B 15mm 7mm 5mm
(LHS)
32
Investigative Works
(Down Town Line Project)
33
Additional Design Check for Most
Probable Parameters
Investigation works:
- Analysis have been performed based on most
probable parameters of soil stiffness
35
Decision for Strut Omission
(Down Town Line Project C922)
36
Observed Level vs OM Level
37
Analyses with Characteristic and
Most Probable Parameters
Investigation works:
- Existing ERSS and struts derived from characteristic
design are checked against the forces due to
omission of strut S6 at 84.5mRL with most probable
parameters
- It has been checked at initial stage with most
probable parameters that existing struts can support
expected strut force with strut S6 omitted
- ERSS capacity has been checked with most probable
parameters and found adequate with omission of
strut S6
38
Lesson Learnt
(Down Town Line Project C922)
39
Lesson Learnt
Lesson:
- Observational Method is useful for ERSS
encountering low permeability soil layer with
significant thickness where the adoption of
Drained Condition can be very conservative
approach leading to less economical design of
ERSS.
40
Content of Presentation:
1) Introduction on Framework of Observational
Approach
41
2. Case Study on Strut Omission
using Observational Method
(Circle Line Project C828)
42
Nicoll Highway Collapse Incident - 20 April 2004
43
Realignment after Collapse – Aerial View
GMT
CONCOURSE
GMC
Boulevard Station
PLAZA Original Alignment
Launching
Shaft
Receiving
Shaft
C824
C825
Land Transport 44
Authority
Nicoll Highway Station along Circle Line Project
Nicoll Highway Station relocated 100m to the South
45
Ground Condition
40
S1 at 102mRL
FILL S2 at 99.87mRL
96.8 3rd level strut was
omitted as a result
UMC/E S3 at 86mRL
of better wall
performance
79.6
F1
67.0
LMC
47
General Information on Circle Line Project
Ground Condition:
48
General Information on Circle Line Project
Construction Method:
- Top-down Method
- 24m wide
- 20m deep
Earth Retaining Structural System:
- 1.5m thick diaphragm wall with 7m thick Jet
Mechanical Mixing (JMM) Block below base
slab level
- ERSS Toe Level at 60mbgl
49
General Information on Circle Line Project
50
51
Jet Mechanical Mixing (JMM)
53
Cross Section
S1 at 102mRL
FILL S2 at 99.87mRL
96.8 3rd level strut was
proposed to be
UMC/E S3 at 86mRL
omitted as a result
of better wall
79.6
performance
F1
67.0
LMC
54
Step 1: Characteristic Design
(Circle Line Project C828)
55
Design Procedure
Step 1: Characteristic Design
56
Design Procedures
Step 1: Characteristic Design
Soil Parameter:
- Soil Parameters are interpreted using
methods in accordance to local authority
requirements.
- Ground Improvement Block parameters adopt
generally accepted values of Su=300kPa with
Undrained Stiffness correlation of (Eu=300Su)
57
Design Procedures
Step 1: Characteristic Design
Soil Parameter:
- Achievable strength of Ground Improvement
Block is unknown
- Degree of enhancement of soil above JMM
Block is unknown. (Hence, enhancement is
ignored)
58
Step 2: Most Probable Design
(Circle Line Project C828)
59
Design Procedure
Step 2: Most Probable Design
60
Design Procedures
Step 2: Most Probable Design
Design Parameter:
- Average Design Parameters better than
characteristic are adopted
- This enables the determination of OM level in
the review level
- The OM level sets the criteria for adoption of
Most probable Design instead of
Characteristic Design
61
Design Procedures
Step 2: Most Probable Design
Evidence:
- The fruition of optimised ERSS system based on
Step 2 requires evidences that the chosen
component has performed as intended on site.
62
Design Procedures
Step 2: Most Probable Design
Comparison of Actual JMM Strength(Most probable value) against
Design Value (Characteristic value) Stiffness, E
Strength, Cu
700 Highest test result
3000
Stiffness E (MPa)
2000
Strength Cu (kPa)
1000
200
500
100
0 0
Original
original design Test results
Analysis 1 Test results
Analysis 2 Original
original design Test results
Analysis 1 Test results
Analysis 2
design (Factored)
(factored) (Unfactored)
(unfactored) (factored) (unfactored)
design (Factored) (Unfactored)
Average Strength (From Core sample) Average Stiffness (From Core sample)
Most Probable Design, Cu = 1845 kPa Most Probable Design, E = 572 MPa
Characteristic Design value = 300kPa Characteristic Design Value = 90MPa 63
JMM Block Parameter
Investigation works:
- JMM Block test results were reviewed and
was suspected to be the most plausible
reason for the reduced wall deflection. Average
Results
(Unfactored)
Average
Results
(Unfactored)
Mass Correction
Mass Correction is applied to
is applied to Average Results
Average Results (Factored)
(Factored)
JMM Block of
JMM Block of Eu=90MPa is
Su=300kPa is conservative
conservative
65
Instrumentation Results
Upon excavating down to
98.7mRL
98.7mRL, the actual wall
deflection is much lower
than predicted wall
deflection of 80mm.
Characteristic Parameters
80mm
Actual Deflection Profile
22mm
Most Probable Parameters
32mm 32mm
66
Observed vs Prediction (Wall Deflection)
Section Predicted Predicted Observed
Deflection based Deflection Deflection
on Characteristic based on most
Design probable design
80mm 32mm 22mm
67
Investigative Works
(Circle Line Project C828)
68
Soil Cement Mix Parameter
Investigation works:
- Moreover, test results for soil cement mix
above the JMM Block also shows better shear
strength and stiffness parameter compared to
adopted parameter in the original design.
69
Cross Section:
96.8
Higher Cu
values achieved
79.6 compared to
original design
67.0
57.8
70
Decision for Strut Omission
(Circle Line Project)
71
Observed Level vs OM Level
72
Content of Presentation:
1) Introduction on Framework of Observational
Approach
73
Types of ERSS suitable for
Observational Method
74
Observational Method Precursors
Design Stage:
1. ERSS with multi-layer struts (Strut Layers > 2).
2. ERSS with excavation level requiring ground
improvement.
3. ERSS in grounds with notable spread in shear
strength parameter.
4. Ground Condition showing soil with low
permeability.
75
Observational Method Precursors
76
Potential Challenges in Applying
Observational Method
77
Challenges
78
Challenges
Construction Stage:
1. Procedures for collecting/analysing the
monitoring data shall be sufficiently rapid in
relation to possible evolution of the system.
79
Challenges
Back-calculation:
1. Identification on the most attributable/most
plausible reasons leading to lesser wall
deflection with subsequent modification on
parameters to match back the observed wall
deflection.
80
Challenges
81
Challenges
Faulty Monitoring Equipment
1. Monitoring equipment shall either be
replaced or extended if it fails to supply
reliable data of appropriate type or in
sufficient quantity.
82
Conclusion
83
Observational Method
Conclusion:
1. Valuable tool in which time & cost-saving can
be acquired through optimisation of design
using observed results.
2. Observational Method is useful for ERSS in
soil with low permeability.
3. Observational Method gives higher benefit
for the types of ERSS fulfilling criteria in logic
gate shown in Annex 1.
4. Simple ERSS adopting observational method
can be very labour-intensive with little
surplus benefits.
84
Annex 1
85
Acknowledgement
86
Thank you
Speaker:
Er. Ng Chew Chiat, David
Prepared by:
Er. David Ng, Er. Dr. Victor Ong, Mr David Ong
ONE SMART Engineering
87